220 likes | 293 Views
VDOT/VSP Joint Safety Operations Center. Robb Alexander Operations Director, Central Region. NORTH. Joint Safety Operations Center (JSOC). 1980s – Preliminary Engineering building 1999 – Richmond Traffic Operations Center 2013 – Concept of a VDOT/VSP co-located facility
E N D
VDOT/VSP Joint Safety Operations Center • Robb Alexander • Operations Director, Central Region Virginia Department of Transportation NORTH
Joint Safety Operations Center (JSOC) • 1980s – Preliminary Engineering building • 1999 – Richmond Traffic Operations Center • 2013 – Concept of a VDOT/VSP co-located facility • 2015 – Combine all 3 functions into one facility • VDOT Richmond District Engineering functions • VDOT Richmond Traffic Operations Center • VSP Division 1 Headquarters + Communications Center Virginia Department of Transportation
Richmond TOC today Virginia Department of Transportation
Project Team • Executive Sponsor – VDOT District Engineer • Tom Hawthorne • Rob Cary • Bart Thrasher • Project Manager – Assistant District Administrator - Business • Lezlie Ellis • Operations Center Lead • Robb Alexander • VDOT Architect • Beth Rappaport • Mike Fried • VSP Facilities • Ronnie Rice Virginia Department of Transportation
Timeline • A/E Services and Construction Administration • June 6, 2016 – RFP issued • Hammel, Green, and • Abrahamson, Inc. (HGA) • November 1, 2016 - Contract executed • Contractor Pre-Qualification • July 14, 2017 – RFQ issued • Four contractors deemed qualified • February 9, 2018 – low bid contract awarded to KBS, Inc. • April 26, 2018 – Groundbreaking Ceremony Virginia Department of Transportation
Design Basics • Three-story structure, approx. 85,000 sqf • Must fit on existing property • Category 3 rating • Physical separation between VSP and VDOT • State-of-the-art Operations Center with Data Center • “Inspire innovation and collaboration and pay homage to the achievements of civil engineering and reflect a culture of service to our fellow citizens.” Virginia Department of Transportation
Other Challenges • Construction within an active VDOT complex • Fiber-optic connection to I-95 • 2 private easements • 1 railroad agreement • Wireless tower for VSP radio system • Funding • Designing a building that integrates with existing buildings both in scale and materiality. Virginia Department of Transportation
Site Plan VDOT ENTRANCE COURTYARD VSP ENTRANCE Existing Buildings to Remain VSP ENTRANCE VDOT ENTRANCE • VDOT Colonial Heights 2019 Virginia Department of Transportation VDOT Colonial Heights 2015
Concept Diagram NEW GROUND LEVEL TO VISUALLY RELATE BOTH IN HEIGHT AND FINISHES TO EXISTING MASONRY BUILDINGS • GLASS BOX RAILROAD TRACKS • UPPER LEVELS THAT BRIDGE ACROSS LOBBY EXISTING MASONRY BUILDINGS • MASONRY GROUND LEVEL TO INTEGRATE WITH COMPLEX • VDOT Colonial Heights 2019 Virginia Department of Transportation NORTH
A New Vision EXISTING MASONRY BUILDINGS • View from South-East Corner Virginia Department of Transportation NORTH
A New Vision VSP LOBBY • View from South-West Corner Virginia Department of Transportation NORTH
A New Vision SEE-THROUGH LOBBY LEADING TOWARD NEW COURTYARD • VDOT Lobby Virginia Department of Transportation NORTH
A New Vision VISUAL CONNECTION TO 2ND LEVEL • Joint Operation Center Virginia Department of Transportation NORTH
Humble beginnings Virginia Department of Transportation
Clearing complete – foundation underway – May 2018 Virginia Department of Transportation
Structure taking shape – October 2018 Virginia Department of Transportation
November 2018 Virginia Department of Transportation
Snow – December 11, 2018 Virginia Department of Transportation
April 2019 Virginia Department of Transportation
Future timeline • Substantial completion – 9/3/19 • First VDOT occupancy – 60 days • TOC operational – mid-November • VSP move-in – early 2020 Virginia Department of Transportation
Lessons Learned • Visit other facilities • Carefully select architects, consultants, and contractors • Pre-qualify where possible • If possible, hire a systems integrator • Identify financial obligations of all partners • Once construction begins, resist temptation to change • Always consider the future • Technology and people Virginia Department of Transportation
Questions? • Robb Alexander • Operations Director, Central Region Virginia Department of Transportation NORTH