David Hackett, Nodal EMS PM Apr 22, 2008. Nodal EMS Update. EMS CIM Importer Pre-FAT currently in progress. CIM File Importer. User Interface. Graphic Modeler. CIM Importer FAT currently scheduled to end May 02, 2008 (moved from April 18, 2008)
E N D
David Hackett, Nodal EMS PM Apr 22, 2008 Nodal EMS Update Texas Nodal Program Update
EMS CIM Importer Pre-FAT currently in progress CIM File Importer User Interface Graphic Modeler • CIM Importer FAT currently scheduled to end May 02, 2008 (moved from April 18, 2008) • SPR / bug fix cycle in progress, scheduled to end April 25, 2008 • Confidence level of FAT completion by May 02, 2008 is low • 10 Sev 1s / Sev 2s out of 42 defects written • ERCOT is ready to retest as fixes become available C I M I M P O R T E R CIM Based Data Repository Model Workspace DynRatings Tables Netmom Tables RASmom Tables CTGS Tables Genmom Tables OAGmom Tables SCADAmom Tables DynRatings Exporter Netmom Exporter RASmom Exporter CTGS Exporter Genmom Exporter OAGmom Exporter SCADAmom Exporter ICCP SCADA Dynamic Ratings Network Applications Generation Testing incomplete Sev 1 / Sev 2 issues Pre-FAT Complete With minor issues Texas Nodal Program Update
Most functionality in EMS 3C and EMS 4 deployed to EDS • Resource Qualification Testing Monitor FAT in progress- expected completion April 25, 2008 (delay due to AREVA lead developer car accident) • Mid Term Load Forecast FAT in progress – expected completion April 25, 2008 • VSAT and TSAT FAT delayed due to hardware issues, expected resolution date – May 2, 2008; pre-FAT completed in March • EMS 5 (Voltage Support & Outage Evaluation) on track for FAT start in late May 2008 (AREVA is working an resource issue) (Includes final testing of the study applications) Texas Nodal Program Update