Time Meeting Apr 22 , 2014. Agenda Safety Schedule Machine and system reports. Safety and training. Ed Lessard. Schedule. NSRL 14A run ends in the middle of May, 14B run from May 27 to Jun 20. BLIP is running, at 110 uA . AGS setup pp is ongoing, ends in middle of May.
E N D
Time MeetingApr 22, 2014 Agenda • Safety • Schedule • Machine and system reports Time Meeting, Run 14
Safety and training • Ed Lessard Time Meeting, Run 14
Schedule NSRL 14A run ends in the middle of May, 14B run from May 27 to Jun 20. BLIP is running, at 110 uA. AGS setup ppis ongoing, ends in middle of May. 4. Two options are in discussion after high energy Au run. One is go back to low energy Au, the other is He-3 on Au. Time Meeting, Run 14
Schedule 56 MHz first conditioning on Monday, reached ~300 kV Wednesday (04/23), APEX, 08:00 AM -midnight Wednesday, pp source maintenance Friday (04/25), machine development at the end of store for beta star squeeze Time Meeting, Run 14
Machine and system reports • RHICMei Bai • STARShusu Shi • PHENIX Klaus Dehmelt • BLIPSuzanne Smith • OperationsPeter Ingrassia • CeCIgor Pinayev Time Meeting, Run 14
Next Time Meeting • Next Time Meeting: Tuesday, April. 29 1:30PM, Snyder Time Meeting, Run 14