1 / 26

RBI Implementation Challenges & Resolution Strategies – Established Plants vs New Plants

Risk-Based Inspection (RBI) identifies Assets for inspection based on their associated risks rather than a predetermined fixed time interval. RBI has replaced Time-Based Inspection in the oil & gas industry. Risks are managed primarily through equipment inspection.

lteng
Download Presentation

RBI Implementation Challenges & Resolution Strategies – Established Plants vs New Plants

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ENGINEERING RBI Implementation Challenges & Resolution Strategies – Established Plants vs New Plants Reza Shahrivar, Asset Integrity Manager Keith Walton, Business Development Manager www.Lteng.co.uk LIFETECH

  2. About the Speakers & LifeTech Engineering Ltd • Introduction – RBI & the Stages of Equipment Life • Different Clients & Experiences • Data Quality and Availability • Damage Mechanisms Identification & Degradation Rate • Risk Matrix • Inspection Planning & First Inspection • RBI Team • Project Duration • Solution Strategies • Summary AGENDA

  3. 24 Years of Experience • BSc. Chemical Engineering - Technical Inspection. • MSc. Materials Engineering – Corrosion. • PhD Candidate – Life Extension • Chartered Engineer – Energy Institute. • Integrity management experience (Integrity, Inspection, Corrosion, RBI & FFS) both in the UK and overseas. • Experience of working with large operators and service companies such as Total, BP, Apache and Lloyd’s Register. • 30 Years of Experience  • BA Business Studies. • MSc Computing Science. • Experience of general management,  operations management & business  development. • 25 years involvement with the Aberdeen Oil & Gas industry in a number of AIM related roles. • Experience of working with large operators, drilling contractors and service companies such as Apache,  BP, Chrysaor, Maersk Drilling,  Petrofac, Shell, Subsea7, Total, & Wood.  About the Speakers from LifeTech Engineering Reza Shahrivar Asset Integrity Manager Keith Walton Business Development Manager

  4. LifeTech Engineering is a leading oil & gas Asset Integrity Management (AIM) service company, providing specialist software, consultancy and training throughout the Asset lifecycle. • We have established AIM, implemented RBI and carried out Life Extension studies Upstream, Midstream and Downstream. • We have developed innovative software: • RBLX for RBI, including a Non-Intrusive Inspection •             (NII) module • FITest for Fitness for Service Assessment • FUSION for Life Extension Assessment About Lifetech Engineering Ltd

  5. Risk-Based Inspection (RBI) identifies Assets for inspection based on their associated risks rather than a predetermined fixed time interval. • RBI has replaced Time-Based Inspection in the oil & gas industry. • Risks are managed primarily through equipment inspection. • Inspections are based on a Risk Matrix where: Introduction - RBI RISK MATRIX • Risk = Probability of Failure (PoF) x Consequence of Failure (PoF)

  6. The HSE report RR5091 describes 4 stages of Asset/Equipment life, each with certain characteristics, and having a different management, inspection and maintenance strategy: • Stage 1: Post Commissioning (‘Initial’) • Stage 2: Risk-Based (‘Maturity’) • Stage 3: Deterministic (‘Ageing’) • Stage 4: Monitored (‘Terminal’) • QUESTION: When should you start practicing RBI? • ANSWER: As early in the life-cycle as possible until the Asset reaches Terminal stage. • Which leads us to consider adding a stage: Stage 0 (Design and Construction Stage). • For NEW Assets, RBI should begin at Stage 0. • 1 UK HSE Research Report RR509 – Plant Ageing Introduction – The Stages of Equipment Life

  7. Inspection Period The Stages of Equipment Life+ 1 Stage 0            Stage 0: EPC (‘New Project’)                    Stage 3: Deterministic (‘Ageing’)   Stage 1: Post Commissioning (‘Initial’)     Stage 4: Monitored (‘Terminal’)             Stage 2: Risk-Based (‘Maturity’)               

  8. Stage 0: New Project Risk Assessment  • An RBI assessment made on new equipment, while in the design stage, can yield important information on potential risks.  • This allows potential risks to be minimized by design and have an RBI plan in place prior to actual installation. • Follow API 580 guidelines The Stages of Equipment Life Stage 0

  9. Stage 1: Post Commissioning & Early Life • As new equipment comes into service there may be a relatively higher rate of damage accumulation and issues requiring attention. There are two main causes:  • Experiencing service conditions for the first time reveals a weakness or fault in the design, materials or fabrication, e.g. incorrect dimensions, faulty material, welding procedures or fabrication defects. The Stages of Equipment Life • Bedding-in effects experienced by equipment when it enters service, e.g. installation stresses, variations in service conditions, leaking valves, incorrectly fitted bolts or seals. .  Stage 0

  10. Stage 2: Risk-Based (‘Maturity’)  • Equipment is predictable, reliable and is assumed to have a low and relatively stable rate of damage accumulation. • Few issues require attention and equipment is operating within design limits.  • Examination and inspection, maintenance and NDT are used generally to confirm the basis for these assumptions, and their scope and periodicity can be risk-based.  The Stages of Equipment Life Stage0

  11. Stage 3: Deterministic (‘Ageing’)  • Equipment has accumulated some damage and the rate of degradation is increasing. • Signs of damage and ageing are starting to appear. • It is more important to determine the extent and rate of damage quantitatively and to make an estimate of remaining life (FFS).  • A more proactive approach to equipment management, inspection and NDT is required.  • Movement towards fitness-for-service and remaining life assessment of equipment.  The Stages of Equipment Life Stage 0

  12. Stage 4: Monitored (‘Terminal’) • As accumulated damage becomes increasingly severe, equipment will need to be repaired, refurbished, decommissioned or replaced.  • The rate of degradation becomes increasing rapidly and difficult to predict. • In this Stage, the main emphasis is on guaranteeing adequate safety between examinations while keeping equipment operating as long as possible.  The Stages of Equipment Life • Equipment is managed through on-line monitoring of the damaged areas, or by more frequent NDT to assess flaws & make repairs.  • Reduction of the duty may be an option to maximise usefulness before decommissioning.  • By this Stage no guarantees can be made about future service life beyond the next examination. Stage 0

  13. Facilities approaching the end of their economic or operating service life are a special case where application of RBI can be very useful – gain the maximum remaining economic benefit from an asset without undue personnel, environmental, or financial risk; the basic doctrines of RBI1. • Inspection efforts focus directly on high-risk areas where the inspections will provide a reduction of risk during the remaining life of the plant.  • Inspection activities that do not impact risk during the remaining life are usually eliminated or reduced. • 1 API 580 RBI at End of Facility Life Stage

  14. RBI at Different Stages of Equipment Life

  15. RBI for New Projects vs Established Projects

  16. Different Clients & Experiences • New Projects • Normally:  • Time limitation, end of the EPC work. • Restricted budget. • Limited experience of implementing RBI & low priority at EPCs. • Most of the comments regarding RBI from the future operator will come  • at the end, therefore, • limited time to resolve – • pressure to deliver into • service.  • EstablishedProjects  • Normally: • Established system, difficult to make changes (custom & practice). • Busy with day to day operation (task overload). • Additional task for the plant engineers. • Have to integrate many established procedures into the RBI system.  Current Operator Future Operator EPC Company RBI Contractor RBI Contractor

  17. Data Quality & Availability • EstablishedProjects • Low quality drawings. • Missing drawings. • Discrepancy between data from line list, P&IDs, Inspection reports, general arrangement drawings, etc. New Projects • Data available electronically.  • Drawings and data are updating during the RBI project. • Isometric drawings not available. • Baseline data will come shortly after the RBI project!

  18. Damage Mechanisms Identification & Degradation Rate • EstablishedProjects • Client wants to address specific Damage Mechanisms; however, these are not dealt with in • API 581. • Use API 571 in addition, however, no calculations in API 571. • Different degradation rates & DMs present on different lines in a Corrosion Loop. New Projects • No real data available as first inspections have not started. • Theoretical models are used to estimate the corrosion rates. • Theoretical models are used to estimate cracking susceptibilities. • Essential to record all assumptions made for future reference.

  19. Risk Matrix • EstablishedProjects • There is no confusion about the risk matrix. • There may, however, be more than one historical RBI risk matrix; these may differ in their assessments and lead to conflicting inspection plans. • Customisation of the API 581 Risk Matrix.  New Projects • There may be confusion between the Project risk matrix and the RBI risk matrix; these are not the same. • Project risk matrix addresses the issues which could prevent timely delivery of a project, e.g. availability of raw materials and spare parts, labour shortages, etc. • RBI risk matrix addresses the issues which could affect equipment performance during operational life, e.g. Damage Mechanisms and other external factors.

  20. Inspection Planning & First Inspection • EstablishedProjects • Difficult to change historical inspection intervals – custom & practice is prevalent. • Various established references & criteria in defining time-based intervals. • Established, time-base inspection plans used for producing WSEs; need to be revise to address new inspection plans due to the move to RBI .  • Difficult to change established habits; acceptance and buy-in from inspection engineers is essential. New Projects • Need to combine RBI inspection plans with the First Inspection plan (normally time-based). • Time-Based first inspection (every 2 years).

  21. RBI Team EstablishedProjects • Inspection Engineer plays a critical role in reviewing inspection history. New Project • Corrosion Engineer plays a critical role  to identify potential DMs and their effects (corrosion rates).

  22. Project Duration New Project • Shorter projects due to readily available data (electronic format) and inspection reports not yet generated (normally less than a year). • Is a blank canvas on which to establish a robust approach to RBI assessment. EstablishedProjects • Longer projects due to data unavailability, data quality and inspection reports (normally more than a year). Analysis Data Gathering Analysis Data Gathering Project duration Project duration

  23. Solution Strategies New Project • Use an RBI software with the ability to calculate theoretical degradation rates. • Establish connection with the future operators as well as the EPC contractor. • Consider time wasted for revision of any work due to newly updated documents & drawings, e.g. Mark up of Corrosion loops on P&IDs. • Ensure that the first post-commissioning inspection requirements are considered in the RBI plans.  • Use an experienced RBI team, particularly the corrosion engineer.

  24. Solution Strategies EstablishedProjects • Create a joint team between the contractor & company.  • Involve plant inspectors, corrosion engineers & process engineers from the start. • Make data assumptions for low risk equipment & piping (e.g. utility) to save time. • Decide about risk matrix & risk targets at beginning of the project. • Register inspection effectiveness per each inspection for future references. • Use representative dead legs instead of assessment of all dead legs. • Use representative nozzles instead of assessment of all nozzles. • Do several tasks in parallel to save time e.g. mechanical data gathering in parallel with inspection reports review. • Use experienced RBI team, particularly inspection engineers.

  25. Summary • RBI can be done for all Stages of equipment life, ideally RBI should be addressed at EPC stage (Stage 0) before initial inspection. • There are different challenges for each Stage. • Note the challenges and have a robust strategy in place for each Stage. • Define and agree clear Scopes of Work. • Work schedules should be realistic, consider all issues and challenges. • A competent and reliable software is required which can address each Stage. • Assemble a competent team of specialists, comprising of Client and RBI Contractor personnel. • Regular review meetings and open communication between all parties is essential. • Lessons learned workshops should be conducted at set periods of the project.   • Present and discuss RBI results with technical authorities and management; agree future programme of work.

  26. Thank you LifeTech Engineering Ltd Reza.Shahrivar@Lteng.co.uk Keith.Walton@Lteng.co.uk +44 (0)1224  824112

More Related