1 / 13

Gas System Commissioning Procedures and Status Overview

Understand the detailed commissioning steps and status updates for the gas system in December 2006, including lab tests and production cycles. Learn about leak tests, cable checks, and new functionalities integrated into the system. Discover the progress and plans for 2007, with valuable insights into commissioning procedures and conclusions.

luisscott
Download Presentation

Gas System Commissioning Procedures and Status Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gas system Commissioningprocedures and status S. Haider PH/DT1

  2. Overview • What is commissioning for us • Status • Alice • Atlas • Plans for 2007 • Conclusions Gas system commissioning Dec 2006 S.Haider PH/DT1

  3. 10 • Leak + functional test • Verification (pipes+cables) 5 Production cycles of the gas system hardware • Construction • Installation • Commissioning • Running-in Gas system commissioning Dec 2006 S.Haider PH/DT1

  4. Lab tests 60 Production cycles of the gas system software • Collect options • Production of code • Installation Gas system commissioning Dec 2006 S.Haider PH/DT1

  5. Commissioning steps (1/2) In general Commissioning is a Verification of functionality (hardware + software debugging phase) • Installation of PLC, WebMas and PVSS software • Test Profibus and CANbus lines from PLC to field nodes • Cable check from control racks to gas racks • With control interface we take output objects into manual mode and operate them (valves, pumps, MFCs, LEDs,…) • For input devices we: • Take off the device-connector in the rack and observe the state change on the control interface • Provoke a reading with a change of pressure or flow in an other part of the system. Gas system commissioning Dec 2006 S.Haider PH/DT1

  6. 1) computers 2)+3) cable IO check 4) 1st parameters 5) New functionality 6) interlocks 7) Leak tightness 8) Gas to chamber Commissioning steps (2/2) • Activate first set of parameters • Verify new functionality (where applicable) • Eg MDT mixer with liquid injection,- or RPC humidifier • Verify chamber pressure interlocks • Verify leak tightness of inter-area piping • Run gas through chambers Gas system commissioning Dec 2006 S.Haider PH/DT1

  7. Status • The following slides do not take into account: • Purifiers • Membranes • Liquifiers • Analysis modules • Only racks installed up to NOW are considered Gas system commissioning Dec 2006 S.Haider PH/DT1

  8. n/a 100% ok 1 rack of 2 ok not applicable to be done ALICE commissioning status Dec 2006 1/2 Gas system commissioning Dec 2006 S.Haider PH/DT1

  9. n/a all installed ok 1 rack of 2 ok not applicable to be done ATLAS commissioning status Dec 2006 1/2 Gas system commissioning Dec 2006 S.Haider PH/DT1

  10. Most commonly found mistakes • Cable + pneumatic lines • Swapped • Wrong labeled • Come to wrong rack in UX • Cut BUT: - “Whatever can be fixed within one day is not considered a mistake !” - MDT has 304 pneumatic lines of which only ~ 15 were wrong !!! Gas system commissioning Dec 2006 S.Haider PH/DT1

  11. Commissioning Estimate vs reality up to now days S all ~ 60!!! ……….ATLAS………. …CMS… ……………ALICE…………….. ……..LHCb…….. Gas system commissioning Dec 2006 S.Haider PH/DT1

  12. IT/CO software Installation work Commissioning CMS IT/CO Analysis, updates, etc… Purifier+Membrane instal. Commissioning of Purif+Membr. ATLAS BIG Wheels TOTEM Commissioning plan for 2007 2007 Jan Feb Mar Apr May Jun Jul Aug Sep IT/CO software Installation work Commissioning LHCb Gas system commissioning Dec 2006 S.Haider PH/DT1

  13. Conclusions • Commissioning procedures are very well tuned by now. • The teams ( ours + IT/CO) work extremely efficiently • ALICE and ATLAS systems will be ready to deliver gas to chambers by end Jan 2007 (installed racks only) • By about July 07all gas systems(but TOTEM) will/should be commissioned • No “show stoppers” in sight so far (let’s keep fingers crossed…) Gas system commissioning Dec 2006 S.Haider PH/DT1

More Related