Cryostat assembly, integration and commissioning procedures. M.Olcese Version: 07 May 2008. Definitions. Flanges/plates (from innermost): MC plate: mixing chamber plate HEX plate: heat exchanger plate STILL plate 4K flange: Inner Vacuum Chamber (IVC) plate 40K plate
E N D
Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008
Definitions • Flanges/plates (from innermost): • MC plate: mixing chamber plate • HEX plate: heat exchanger plate • STILL plate • 4K flange: Inner Vacuum Chamber (IVC) plate • 40K plate • 300K flange: Outer Vacuum Chamber (OVC) plate • Vessels/screens: • MC screen (upper and lower part) • HEX screen • 4K vessel: IVC vessel • 40K screen • 300K vessel: OVC vessel
Schematic: cryostat 300K, 4K flanges and 40K plate 300K, 4K vessels and 40K screen STILL top lead ring STILL plate Internal top lead shield HEX and MC plates Detector support plate Lateral STILL lead shield Detector Internal screens (STILL-HEX-MC) Lateral STILL lead shield support cradle Main external shielding
Schematic: building and platform 2° floor 1° floor Concrete walls Corridor side Parking Side of main shielding Main rail system Light platform Main platform (upper) Main platform (lower) Aux. rail system
Scenarios • Initial installation: 1.1 Installation of 300k-40k-4k plates 1.2 Dry fit of vessels and screens 1.3 Installation of STILL-HEX-MC plates • Cryostat commissioning • Detector installation • Access for maintenance
General issues • All the individual items (with few exceptions) can be brought on the main platform for the installation: • from the hut ground floor with the platform in the side position • Directly from the external corridor using an auxiliary rail system
1 Initial installation1.1 installation of top plates/flanges • The plates are delivered clean and inside plastic bags • The plates are piled up on the main platform (a platform add-on may be required to reach the 1° floor level) • The main platform is raised • Eye bolts + radial extensions (if needed) will be fixed to the plates. • The plates are lifted by means of the hoist cable system and connected to the tie rods/suspensions • It may be convenient to install, along with the plates, some of the internal components like: sections of the source tube, wire feed-throughs, IVC pumping tube, …
Initial installation 1.1: setting of plates on platform at ground level Option 1 Stack of plates in reverse order (4K-40K-300K) Platform extension Main platform
Initial installation 1.1: setting of plates on platform at ground level Option 2 Plates set on auxiliary platform from the corridor side
Initial installation 1.1: platform with plates ready for lifting
Initial installation 1.1: 300K-4K flanges and 4K plate are installed in sequence
1 Initial installation1.2 dry-fit of 300K-4K vessels and 40K screen • Purpose: • check the handling procedure and sign-off of the cable hoist system • Check vacuum tightness and deformations of OVC and IVC Issues/comments: • The internal screens (still, HEX, MC) must be installed in clean conditions, so they will not be installed in this phase through the floor opening. They will be installed and removed from the clean room at the end of the dry fit • All the screens/vessels are delivered in upright position on a basement
Initial installation 1.2: 4K (40K, 300K) vessel set on platform Option1 Option2
Initial installation 1.2: 4K (40K, 300K) vessel ready for lifting Lifting cables Lifting ears and eye bolts are installed and hoist cables connected
Initial installation 1.2: 4K (40K, 300K) vessel lifted and fixed to the 4K flange
Initial installation 1.2: testing • Leak tightness • Vacuum • Deformations
1 Initial installation1.3 Installation of STILL-HEX-MC plates
Initial installation 1.3: installation of temporary support structure The main platform is moved aside
Initial installation 1.3: the floor is closed and sealed off From this moment on the area around the cryostat will have to be kept clean at all time
Initial installation 1.3: installation of the HEX and MC plates
Initial installation 1.3: installation of the HEX and MC plates
2. Cryostat commissioning • 2.1 integration of all the internal components (DU, pulse tubes, wire inserts, source guiding tubes, suspensions) • Preliminary cooling tests and functional tests of all components • 2.2 installation of STILL lateral lead shield • 2.3 installation of the internal top lead shield and dummy detector (DD) • alignment and calibration of the detector suspension system • 2.4 Final tests • COMMENTS: • The 2.1 phase will last for quite some time and will require several openings and closings of the cryostat: it is recommended to use a temporary support structure on the main platform to store the screens/vessels. This would allow the assembly of the main external shielding in parallel and off-line • In phase 2.1 not all the screens/vessels may be needed for the tests: those internal are stored on the first floor and could be installed when needed independently from the external ones
2. Cryostat commissioning 2.1 integration of all the internal components (DU, pulse tubes, wire inserts, source guiding tubes, suspensions)
Cryostat commissioning 2.1: installation of internal components In parallel: assembly of main shielding
Cryostat commissioning 2.1: installation of internal screens (1)
Cryostat commissioning 2.1: installation of internal screens (2)
Cryostat commissioning 2.1: installation of internal screens (3) Screens lifted by the cable hoist system or by hydraulic jacks
Cryostat commissioning 2.1: installation of external vessels (1)
Cryostat commissioning 2.1: installation of external vessels (2) main shielding completed
Cryostat commissioning 2.1: cold tests • During testing: • The temporary support is removed
Cryostat commissioning 2.1: cold tests • During testing: • The platform with the main shielding is brought on-axis
2. Cryostat commissioning 2.2 installation of STILL lateral lead shield
Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (1) The floor is opened
Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (2) The 4K-40K-300K vessels are lowered into the main shield
Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (3) • Floor closed • External vessels sealed off
Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (4) Removal of internal screens
Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (5) Removal of internal screens
Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (6) Main shielding moved aside
Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (7) Temporary support added on main platform
Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (8) Platform raised and sealed
Cryostat commissioning 2.2: preparation for installation of STILL lateral lead shield (9) • Floor opened • Temporary support raised to reach floor level
Cryostat commissioning 2.2: installation of STILL lateral lead shield (1) Still lead cradle set on support
Cryostat commissioning 2.2: installation of STILL lateral lead shield (2) Platform lowered
Cryostat commissioning 2.2: installation of STILL lateral lead shield (3) Bottom lead layer and first ring added