An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Experimental Tests of Cooling:Expectations andAdditional Needs Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory NuFact08 WG3—Valencia July 1, 2008

  2. Why Do a Cooling Experiment? • Motivation for cooling experiment • muon-based Neutrino Factory is most effective tool to probe neutrino sector and, hopefully, observe CP violation in leptons • results will test theories of neutrino masses and oscillation parameters, of importance for both particle physics and cosmology • a high-performance Neutrino Factory (≈1021e aimed at far detector per 107 s year) depends on ionization cooling • straightforward physics but not experimentally demonstrated • facility will be expensive (O(1B€)), so prudence dictates a demonstration of the key principle • a Muon Collider depends even more heavily on ionization cooling NuFact08-WG3: Zisman

  3. Aims of MICE • MICE cooling demonstration aims to: • design, engineer, and build a section of cooling channel capable of giving the desired performance for a Neutrino Factory • place this apparatus in a muon beam and measure its performance in a variety of modes of operation and beam conditions • Another key aim: • show that design tools (simulation codes) agree with experiment • gives confidence that we can optimize design of an actual facility • we test a section of “a” cooling channel, not “the” cooling channel • simulations are the means to connect these two concepts • Make simulations + test apparatus as realistic as possible • Thought-provoking question: is the cooling demo for “us” or for “them”? • the latter audience is tougher to convince NuFact08-WG3: Zisman

  4. System Description • MICE includes one cell of the FS2 cooling channel • three Focus Coil (FC) modules with absorbers (LH2 or solid) • two RF-Coupling Coil (RFCC) modules (4 cavities per module) • Along with two Spectrometer Solenoids with scintillating fiber tracking detectors • plus other detectors for confirming particle ID and timing (determining phase wrt RF and measuring longitudinal emittance) • TOF, Cherenkov, Calorimeter NuFact08-WG3: Zisman

  5. MICE Cooling Channel Eight 201-MHz RF cavities LH2 absorbers Courtesy of S. Q. Yang, Oxford Univ. NuFact08-WG3: Zisman

  6. MICE Stages • Present staging plan NuFact08-WG3: Zisman

  7. Estimated Performance (1) • Simulations of MICE performance carried out with several codes • nominal cooling performance estimated with ICOOL • full detailed simulations done with G4MICE • Typical parameters • beam • momentum: 200 MeV/c (variable) • will cover range of roughly 140–240 MeV/c • momentum spread: 20 MeV/c • x,y ≈ 5 cm; x’,y’ ≈ 150 mrad • channel • solenoid field: ≈ 3 T • : 0.42 m • cavity phase: 90° (on crest) NuFact08-WG3: Zisman

  8. Estimated Performance (2) • ICOOL simulation shows transverse emittance reduction of ≈10% NuFact08-WG3: Zisman

  9. Estimated Performance (3) • Virtual scan over emittance used to determine equilibrium emittance • transmission is 100% for input emittance below 6  mm-rad • high emittance behavior reflects “scraping” as well as cooling NuFact08-WG3: Zisman

  10. MICE Hall • Webcam is available for up-to-date views • see http://mice.iit.edu/mico/webcams/ • Many photos taken as well NuFact08-WG3: Zisman

  11. RFCC Module • Module comprises one coupling coil and 4 RF cavities • in advanced design stage • CC design and fabrication done in collaboration with ICST in Harbin, China • initial conductor order delivered • RF cavities will be similar to existing MuCool prototype • fabrication to get under way shortly NuFact08-WG3: Zisman

  12. MuCool Test Cavity 42-cm • Test cavity similar to MICE design has been fabricated • in place at Fermilab MTA • Be window design also successfully tested D. Li talk NuFact08-WG3: Zisman

  13. FC Module • Focus coil module vendor has been selected • contract award delayed until recently due to STFC funding woes • comprises two coils that can run with same or opposite polarity • 20-L LH2 absorber (plus safety windows) fits inside NuFact08-WG3: Zisman

  14. LH2 System • LH2 system design is based on using metal hydride bed as storage tank • Design has passed two international safety reviews • R&D system presently being fabricated in industry NuFact08-WG3: Zisman

  15. LH2 R&D System • LH2 R&D system will be assembled and tested at RAL • intent is to validate the system and make it the “first article” (of 3) • both components and computer controls must be vetted NuFact08-WG3: Zisman

  16. Absorber Windows • Required windows must be large (300 mm diameter), thin (~125 m) and strong (4x safety factor) • Aluminum windows designed by Oxford and built at U.-Miss. • 125 m; machined from single piece of Al • burst at 140 psi (nearly 10 atm) NuFact08-WG3: Zisman

  17. Future Activities • Assuming MICE is successful, it will demonstrate • an understanding of 4D cooling process • an understanding of the technical challenges that must be met • component design • system-level operational issues • This should suffice for developing a Reference Design Report for a Neutrino Factory (an IDS-NF task) • demonstration of magnetically insulated cavity performance beneficial • What else is missing? • an equivalent demonstration of 6D cooling (for a collider) • a demonstration of “final” transverse cooling (for a collider) • Are these necessary for designing a Muon Collider? • for getting funding approval? • or only for building one? NuFact08-WG3: Zisman

  18. Magnetic Insulation • Before proceeding to a realistic 6D cooling demonstration, substantial component R&D must be done • means to avoid, or at least mitigate, degradation of RF gradient in strong B field is most critical • e.g., magnetically insulated open cell (Palmer’s concept) • suitable wedge-shaped absorbers (LH2 or otherwise) • practical and affordable high-field solenoids for collider final cooling 201 MHz (subsequent test) 805 MHz (initial test) NuFact08-WG3: Zisman

  19. Muon Collider Scheme Fits on Fermilab site Based on Project X at Fermilab NuFact08-WG3: Zisman

  20. 6D Cooling at RAL (1) “HCC” • RAL muon beam facility will continue to be valuable after MICE is completed • continuing to a 6D cooling demonstration is attractive option • “Poor man’s” test of 6D cooling in MICE • “Rich man’s” test of 6D cooling, e.g., FOFO snake, Guggenheim, HCC NuFact08-WG3: Zisman

  21. 6D Cooling at RAL (2) • Several issues to consider • timetable for doing such experiments • cost • available effort for planning and execution • Possible (fast-track) Muon Collider timetable and cost estimate presented to P5 by Palmer NuFact08-WG3: Zisman

  22. Comments • Based on putative collider timeline we see • feasibility study complete in 2012 (same as RDR for Neutrino Factory) • RDR complete in 2015 • CDR complete in 2018 • My view • impractical to complete convincing 6D cooling demo(s) by 2012 • completing MICE will be a pacing item (if continuing at RAL) • component R&D is also a pacing item (even if not continuing at RAL) • demo experiment(s) may be too late for RDR as well • with adequate budget + staffing, might get one done • in any case, progress on component design will be useful for RDR • aim for completing all demo experiment(s) no later than the CDR phase • in time for input to (expected) international design and cost review NuFact08-WG3: Zisman

  23. Summary • MICE making excellent progress • design of coupling coils complete; fabrication started (ICST Harbin) • RF cavity design finalized; procurements initiated • focus coil module contract placed • LH2 R&D system being prepared at RAL • MICE should answer most questions of 4D cooling • we are looking forward to first ionization cooling measurements! • remaining issue is final cooling for collider • same physics but very challenging components (~50 T solenoids) • 6D cooling will likely require a substantial experiment • adopting “Guggenheim” or “FOFO snake” scheme would reduce the cost (almost same components as MICE) • Strong R&D program to develop and test key components must continue and expand NuFact08-WG3: Zisman

  24. Final Thought • Challenges of a muon accelerator complex go well beyond those of standard beams • developing solutions requires substantial R&D effort to specify • expected performance, technical feasibility/risk, cost (matters!) Critical to do experiments and build components. Paper studies are not enough! NuFact08-WG3: Zisman