1 / 27

Sixtrack simulations for the study of C rab cavity failures in HL-LHC

Sixtrack simulations for the study of C rab cavity failures in HL-LHC. LBS#48 meeting 16 September 2013. F. Bouly. LAYOUT.  - Introduction  - Initial conditions – Starting point  - First run and crab cavity - F ailure scenario : 1 example  - Conclusion. F.B.

lynch
Download Presentation

Sixtrack simulations for the study of C rab cavity failures in HL-LHC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sixtrack simulations for the study of Crabcavityfailures in HL-LHC LBS#48 meeting 16 September 2013 F. Bouly

  2. LAYOUT •  - Introduction •  - Initial conditions – Starting point •  - First run and crabcavity • - Failure scenario : 1 example •  - Conclusion F.B. LBS#48 16/09/2013

  3.  - Introduction Context • HL-LHC WP8 : Collider experiment interface • Evaluate the inherent constraints on beam pipe design for various options for the high luminosity insertions at HL-LHC. It will take into account physics requirements at the interaction point and in the forward region along with LHC machine constraints. • Key point • What will be the consequences of the aperture changes for HL-LHC in terms of background, radiation and protection of the central detector regions. • TAS and triplets Opened whereas the size of the detector chambers will be reduced  Background issues : Beam gas scattering – showers from TCT – IR cross-talk …  Machine protection issues and possible failure scenarios : - Crab cavity failure scenarios ◄ - Dump failures : asynchronous beam dump - UFOs - Beam-beam kick missing - Fast vacuum valves - (D1 failure scenarios) - (…) F.B. LBS#48 16/09/2013

  4.  - Introduction Goals & failure scenarios • Evaluate the risks and possible issues close to the interaction regions (IP1 &IP5) when a crab cavity fails (i.e amount of particles lost) • Maximal transverse displacement (assuming optimal voltage to compensate the crossing angle) ~1.35 (ATS optics, β*=0.15 m,ncc = 3) •  Simulations achieved with SixTrack (collimation version) : a SixTrack update was done to enable the control (ramp and change voltage and phase). Bruce Yee Rendón • Optics configuration for the study • We only look at BEAM 1 in the simulations F.B. LBS#48 16/09/2013

  5. LAYOUT • - Introduction • - Initial conditions – starting point •  - First run and crabcavity • - Failure scenario : 1 example •  - Conclusion F.B. LBS#48 16/09/2013

  6. - Initial beam distribution Starting point • All the simulations start from IP1. The distributions are given according to the twiss parameters at IP1. The distributions are assumed to be (simple) Gaussian. • 2 types of distribution were used for the simulations 1st type : Halo distribution 2nd type : Core distribution ~0.012% of a full bunch ~97.790 % of a full bunch  x-x’ plan : 3 to 5 σ  y-y’ plan : 3 to 5 σ  Z-ΔE/E plan : 0 to 4 σ+ ‘pseudo-matching’ condition  x-x’ plan : 0 to 3 σ  y-y’ plan : 0 to 3 σ  Z-ΔE/E plan : 0 to 4 σ + ‘pseudo-matching’ condition

  7. - Initial beam distribution Longitudinal (pseudo-)matching For the longitudinal plan we first assume a 2D Gaussian distribution, with particle between 0 σ to 4σ. Still we added a condition for the matching : in our case all the particles are kept inside the area delimited by the which is at 4σz (when ΔE/E = 0 ) (Pseudo-)Matched Not Matched  Particles trajectories in the longitudinal phase-space : Can be derived with the Hamiltonian : H(ΔE/E,Δφ) = H(0,Δφ0) and V = total RF accelerating voltage λRF = RF wavelength ϕs = synchronous phase h = harmonic number η = γ-2 – αc αc = momentum compaction factor F.B. LBS#48 16/09/2013

  8. - Initial settings Simulation configuration with SixTrack Collimators settings: • All the simulations start from IP1 • Run of 6.4 *106 particles for 500 turns • For these first simulations the crab cavities are kept switched-off • Simulations carried out with both distributions (“halo” & “core” ) 12 10 A Marsili et al. Collimation cleaning with ATS optics for HL-LHC Collimation Review, 2013/30/05 Aperture modifications at IP1 and IP5 : In the aperture file allapert_ats_20121023b1: _ beam pipes diameterat IP reduced _ TAN wasmissing on the left of IP1  added F.B. LBS#48 16/09/2013

  9. LAYOUT • - Introduction • - Initial conditions – Startingpoint • - First run and crab cavity • - Failure scenario : 1 example •  - Conclusion F.B. LBS#48 16/09/2013

  10. - First run and crab Halo simulation (1st Run) • Core simulation : no losses observed • Halo simulation : (9714 / 6.4*106 ) particles lost halo Final distribution after 500 turns at IP1 F.B. LBS#48 16/09/2013

  11. - First run and crab Halo simulation (1st Run) _ Initial number of particles : 6400000 _ Number of particles absorbed by collimators : 9714 _ Number of particles hitting apertures : 3 _ Number of particles lost : 9717 -> MEANING : 0.152% of the initial distribution One particular collimator is absorbing the particles : TCP.B6L7.B1 F.B. LBS#48 16/09/2013

  12. - First run and crab Halo simulation (1st Run) Particle absorbed at TCP.B6L7.B1 Initial position (at IP1) of the particles lost during the simulation F.B. LBS#48 16/09/2013

  13. - First run and crab Halo simulation (5th Run) 1stRun After 5 simulations : i.e. 2500turns 5th Run 5thRun of 500 turns _ Initial number of particles : 6400000 _ Number of particles absorbed by collimators : 402 _ Number of particles hitting apertures : 0 _ Number of particles lost : 402 -> MEANING : 0.006% of the initial distribution F.B. LBS#48 16/09/2013

  14. - First run and crab Crab cavities switched on • During the 5th simulation the average number of absorbed particles was below: 1/turn • It was chosen to keep this distribution as a starting point • simulations were carried out to evaluate the crabbing effect : • - 1st turn : crab cavities are switched off • - 2nd turn to 11th turn : crab cavities voltage are ramped up to their nominal voltage (for 10 turns) at IP1 and IP5. • - Last 39 turns : the crab cavities are kept switched on F.B. LBS#48 16/09/2013

  15. - First run and crab Crab cavities switched on _ Initial number of particles : 6400000 _ Number of particles absorbed by collimators : 87 _ Number of particles hitting apertures :0 _ Number of particles lost : 87 -> MEANING : 0.0013594% of the initial distribution Ramp The collimation cleaning is still dominated by: TCP.B6L7.B1 Slight increase of the losses : acceptable (?) Number of turns a bit low (?) F.B. LBS#48 16/09/2013

  16. - First run and crab Crab cavities (distributions) Final distribution after 50 turns at IP1 HALO  Both distributions were used as starting point for the study of the failure scenario  For the core simulation : No losses observed over 6.4 millions particles CORE F.B. LBS#48 16/09/2013

  17. LAYOUT • - Introduction • - Initial conditions – Startingpoint • - First run and crab cavity • - Failure scenario : 1 example •  - Conclusion F.B. LBS#48 16/09/2013

  18. - Failure scenario Failure scenario description • Phase Failure of the first crab cavity at IP5 on the left side (Beam 1) • Failure in 1 turn : the phase of the cavity drops from 0˚ to 90˚ Realistic case? • 11 turns in the simulation : 1st turn with all the CCs in normal operation Failed • NB : no losses observed for the core distribution - only the results for the halo distribution are presented F.B. LBS#48 16/09/2013

  19. - Failure scenario Losses after the failure 10 turns after the failures failure _ Initial number of particles : 6400000 _ Number of particles absorbed by collimators : 53006 _ Number of particles hitting apertures :2 _ Number of particles lost : 53026 -> MEANING : 0.82853% of the initial distribution F.B. LBS#48 16/09/2013

  20. - Failure scenario Very row estimation of the losses • The “halos distribution” represents ~ 0.0123 % of a total bunch •  Energy in the HL-LHC beam : • 2808* 2.2*1011 * 7*1012 * 1.602*10-19≈ 693 MJ • Part of the beam that we consider in the simulation • 0.0123 % * 693 *106 = 85.2 kJ Tentative of Energy deposition estimation for this specific failure scenario F.B. LBS#48 16/09/2013

  21. Some particles trajectories Normal Beam 1- IP5 – horizontal plan Immediately after the failure Failure “Left part” of IP1 Increase ~27% F.B. LBS#48 16/09/2013

  22. - Failure scenario Some particles trajectories Normal Beam 1- IP5 – horizontal plan 3 turns after the failure Failure ~5% F.B. LBS#48 16/09/2013

  23. - Failure scenario Some particles trajectories Normal Beam 1- IP5 – horizontal plan 5 turns after the failure Failure ~14% F.B. LBS#48 16/09/2013

  24. - Failure scenario 10 turns after the failure Final distribution at IP1 - 10 turns after the failure The effect of the failure at IR5 is seen at IP1 F.B. LBS#48 16/09/2013

  25. LAYOUT • - Introduction • - Initial conditions – Startingpoint • - First run and crab cavity • - Failure scenario : 1 example •  - Conclusion F.B. LBS#48 16/09/2013

  26. Conclusion • From the first picture of “halo ” simulations : risks for the experiments seem to be very low (even with a beam dump in 10 turns) • Extensive number of simulations are carried out by B.Y. Rendón (BE/ABP). Losses from the “halo distribution” for different types of failure at IP5 • Very strong failures were simulated here : phase shift of 90° in 1 turn (~100 µs) But what happen in reality? The phase and voltage shift may take more than 1 turn • A mitigation strategy can be implemented in case of a failure : switch off the crab cavities if one failure is detected. Courtesy of B.Y.Rendón • Still : _ We need more statistics (different/complementary distributions) to evaluate the global losses (apertures and collimators) _ The simulations assumed no errors : misalignement, fields _ We need a better description of the cavity discharge with a beam. F.B. LBS#48 16/09/2013

  27. Thank you F.B. LBS#48 16/09/2013

More Related