110 likes | 229 Views
NorthGrid status. Alessandra Forti Gridpp15 RAL, 11 th January 2006. Sites Resources Summary. Sites Resources Summary. Lancaster. 60 TB installed with dcache Will upgrade to newer version later in the month 10 TB installed with DPM for testing
E N D
NorthGrid status Alessandra Forti Gridpp15 RAL, 11th January 2006
Sites Resources Summary Alessandra Forti GridPP15 RAL
Sites Resources Summary Alessandra Forti GridPP15 RAL
Lancaster • 60 TB installed with dcache • Will upgrade to newer version later in the month • 10 TB installed with DPM for testing • They’ll be integrated in dcache at the end of the tests • SC3 tests using ukLight • using FTS, single file stream, 50GB of files @150Mbps • using srmcp using up to 10 parallel file streams with 6 file stream achieved instantaneous rate up to 702Mbps with an aggregate rate of 3GB/minute. • SC4 LFC has been installed but never been tested • Second site in UK to complete Security Service Challenges Alessandra Forti GridPP15 RAL
Liverpool • Certified at the end of October • with only 3 nodes due to cooling problems • Increased to 20 nodes today • 210 will be added after gridpp15 • Dcache 1.6.5 on 2.2 TB • University firewall problems • RBs are filtered • Second site in UK to install correctly RGMA secure connector. Alessandra Forti GridPP15 RAL
Manchester • Old cluster (40 kSI2k) has been decommissioned • The new cluster is undergoing the acceptance tests. • First 800 nodes have been accepted. • 100 nodes have been given to the engineers in exchange of power and cooling. Perhaps we can convince them to use the grid (and keep the nodes) in exchange of hardware and software support. • The structure is in place. • Servers, networking…. relationships with MCC people couldn’t be more cooperative and friendly. • IPs, domain name, machine names, site name have changed • Not certify yet. Certification within the end of January • First 20 nodes have been put online for SC4 transfer tests. • Nearly 350 Mb/s rate on university production network. • Planning to have a private fiber to increase the rate and to connect to ukLight. Alessandra Forti GridPP15 RAL
Sheffield • Lost unfunded support • Now have only .5 funded FTE. • Installed dcache but not tested it yet • Progress slow due to other work pressures • Cooling failures in December • Offline since yesterday • Major hardware problems Alessandra Forti GridPP15 RAL
CPU Usage by VO (KSI2K hours) Nb: This can be extracted from APEL – http://goc.grid-support.ac.uk/gridsite/accounting/custom.php Alessandra Forti GridPP15 RAL
CPU used per VO over quarter (KSI2K hours) Alessandra Forti GridPP15 RAL
Tier-2 planning for next quarter • All Prepare for SC4 • All upgrade dcache to latest version. • All upgrade to 2.7.0 • Lancaster incorporate 10TB DPM test machines into dcache • Lancaster improve network configuration for production system • Liverpool install more nodes (only 3 at the moment) • Manchester deliver new resources • Manchester set up production VOMS for GridPP • Sheffield test dcache installation Alessandra Forti GridPP15 RAL
Summary & outlook • Improved cooperation among new posts. • Liverpool finally became a green dot on the map, improved support for LCG. • Sheffield few support problems since the non-funded people quit. The ‘new’ post is not full time and he is only 1 person. This needs to be addressed. • Sheffield has also had major hardware and cooling failures. • Manchester has almost completed the acceptance tests. SC4 deliverables were completed. • Manchester is still actively working on VOMS deployment and we are ready for a production system. See Andrew McNab Talk • Lancaster successfully carrying on SC3 and testing different SRM solutions (DPM) . They have also been the best site in NorthGrid (UK) for resource usage last quarter. Alessandra Forti GridPP15 RAL