Mid-States Highway-Rail Grade Crossing Safety Conference May 20, 2008. RAILROAD BRIDGE DESIGN GUIDELINES (Overpasses & Underpasses). KANSAS CITY SOUTHERN RAILWAY. BRIDGE DESIGN GUIDELINES ( O.P. & U.P.). Design Parameters:. Future Plans of Railroad Bridge Layout
E N D
Mid-States Highway-Rail Grade Crossing Safety ConferenceMay 20, 2008 RAILROAD BRIDGE DESIGN GUIDELINES (Overpasses & Underpasses) KANSAS CITY SOUTHERN RAILWAY
BRIDGE DESIGN GUIDELINES ( O.P. & U.P.) Design Parameters: • Future Plans of Railroad • Bridge Layout • Clearances – Horizontal & Vertical • Drainage – Railroad & Highway • Agreement - RoW Easement and C & M • Construction Schedule • Construction Sequence • Construction Inspection and Monitoring • Utilities on Proposed Bridge • Cost Sharing
BRIDGE DESIGN GUIDELINES ( O.P. & U.P.) 1. Future Plans of Railroad • Rail Traffic • Number of Tracks • Service Roads • Signals • Transload / Intramodal / Switching Yards Expansion • Business Expansion • Track Raises
BRIDGE DESIGN GUIDELINES ( O.P. & U.P.) 2. Bridge Layout • Piers • Foundations • Roadway Embankments • Location of Future Railroad Structures like future tracks, signal equipment, drainage, service roads, etc.
BRIDGE DESIGN GUIDELINES ( O.P. & U.P.) 2. Bridge Layout
BRIDGE DESIGN GUIDELINES ( O.P. & U.P.) 3. Clearances • Horizontal • Vertical
BRIDGE DESIGN GUIDELINES ( O.P. & U.P.) 4. Drainage • Existing Railroad Drainage Ditches • Future Drainage Ditches • 100 Yr Flood Elevations • Impact of New Highway Structure on Drainage • Impact on Existing Railroad Drainage Structures • Highway Drainage Design - Rip Rap, Culverts (size & Locn.) ,Scuppers, Snow Removal, etc. • Design Calculations submittal • Erosion Control
BRIDGE DESIGN GUIDELINES ( O.P. & U.P.) 5. Agreement- ROW Easement and C&M • Property Ownership • Property Description • Compensation • Easement Agreement • Construction & Maintenance Agreement Note: No construction to begin until both Agreements are executed.
BRIDGE DESIGN GUIDELINES ( O.P. & U.P.) 6. Schedule • Funding • Letting Date • Construction Schedule • Flagging • Curfews • Inspection by Railroad • Shop drawing submittals
BRIDGE DESIGN GUIDELINES ( O.P. & U.P.) 7. Construction Sequence • Soil Testing • Construction Equipment Rigging • Foundation Excavation and shoring • Installation of Super Structure • Temporary Crossing • Drainage Structure Installation
BRIDGE DESIGN GUIDELINES ( O.P. & U.P.) 8. Construction Insp. & Monitoring Inspection of Construction during: • Excavation • Pile Driving • Erosion Control • Foundation • Sub-Structure • Super Structure • Final
BRIDGE DESIGN GUIDELINES ( O.P. & U.P.) 9. Utilities on Proposed Bridge • Street Lighting Allowed-To be shown in Plans • All other Utilities-Need Railroad Approval (Separate Crossing Applications required) • Mounting Details-To be shown on Drawings
BRIDGE DESIGN GUIDELINES ( O.P. & U.P.) 10. Cost Sharing • Stated during Project Proposal to Railroad • % Share stated in the Construction and Maintenance Agreement • Schedule of Payment clearly Agreed upon in the Agreement