Golden Quadrilateral. Golden Quadrilateral Status August 31 2002. † Estimated Cost. North South & East West Corridor Status : August 31 2002. Completion Schedule for 494 Km (29 Contracts). Overall Contracts Status Status : August 31 2002. Contracts
E N D
Golden QuadrilateralStatus August 31 2002 † Estimated Cost
North South & East West CorridorStatus : August 31 2002 Completion Schedule for 494 Km (29 Contracts)
Overall Contracts StatusStatus : August 31 2002 Contracts No. Cost Expenditure(Rs. Crs.) (Rs. Crs.) • Total ongoing 133 18,579 9,179 On GQ 95 15,951 6,286 On NS & EW 29 1,863 1,166 Others & Port Connectivity 9 766 1,727
Contracts Award to various ContractorsStatus : August 31 2002 No of Contracts Length Awarded Cost (in km) (Rs Crs) Total No. of Contractors 133 5,322 18,579 • Indian Firms 86 2,876 10,490 • Joint Ventures 35 1,792 6,115 • Foreigners 12 654 1,974