PennDOT’s 2010 Program

11 th Annual Pennsylvania Concrete Conference. PennDOT’s 2010 Program. Rebecca S. Burns, P.E. Acting Director Bureau of Construction and Materials. January 26 th -27 th , 2010 - Grantville, PA. 2009/2010 Construction Program. 2010 Program Asset Management Things to Come.

lyre
Download Presentation

PennDOT’s 2010 Program

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 11th Annual Pennsylvania Concrete Conference PennDOT’s 2010 Program Rebecca S. Burns, P.E. Acting Director Bureau of Construction and Materials January 26th-27th, 2010 - Grantville, PA

  2. 2009/2010 Construction Program • 2010 Program • Asset Management • Things to Come • Letting Trends • ARRA Status • Design Build • Material Trends

  3. Historic Letting Trends * Includes Base Program + $62 Million in ARRA Funding for 23 Projects

  4. Project Type Breakdown * Projected

  5. ARRA • $1.026 Billion* in ARRA funding • 282 contracts bid for 326 projects • 91% let on original scheduled date • 2009 - $863M • 2010 - $ 61M * includes construction oversight

  6. 2009 Design Build Trends Data Source: ECMS contracts bid in calendar year 2009, by cost [excludes municipal contracts]

  7. 2009 Average Number of Bidders

  8. Inflation Indices FHWA/PENNDOT Highway Admin Bid Index for PA (BPI) Engineering News Records Construction Cost Index (CCI) Bureau of Labor and Statistics Consumer Price Index (CPI) 3% Trend Line

  9. Producer Price Indices – Competitive Building Materials Data Source: Portland Cement Association Market Research December 15th, 2009

  10. Materials Usage Totals Data Source = Projected Material Usage from Annual District Surveys

  11. 2010 Construction Program $1.8 Billion* *Unknowns: Act 44 Funds, Reauthorization of Highway Trust Fund, Motor License Funds, Economic Stimulus

  12. 2010 Letting Schedule • 675 Projects Projected for 2010* • 209 projects populated in ECMS • 11% have Concrete Paving • 6% with Concrete Pavement Rehabilitation (CPR) Operations

  13. Concrete Pavements

  14. Concrete Pavement Rehabilitation (CPR)

  15. Asset Management

  16. What’s Next • A second Federal Stimulus package, known as Job Creation, is in development in the US Congress. • Passed the House of Representatives awaiting action by the Senate • PennDOT can respond as needed with up to 300 additional highway and bridge projects.

  17. We Look Forward to Working with ACPA in 2010! Thank-You!