Proteus – Between Safran and IFS at Bergen Group Rosenberg …and more. Tom Ivar Barka Lead Planner at Bergen Group Rosenberg Bergen Group tom-ivar.barka@bergengroup.no November, 2012. Bergen Group Rosenberg. Employees. Overview of data to integrate. Activities. Act .Table. Compare.
E N D
Proteus – Between Safran and IFSat Bergen Group Rosenberg …and more Tom Ivar Barka Lead Planner at Bergen Group Rosenberg Bergen Group tom-ivar.barka@bergengroup.no November, 2012
Bergen Group Rosenberg Employees
Overview of data to integrate Activities Act .Table Compare [Level 4] AO Table [Level 5] PO Table DP Table Planners Workspace Oper Table [Level 6] Doc Table Eng. Obj. Table • Activities Table (to compare) • AO Table • PO Table • DocPkg (DP) Table • Doc. Table • Oper Table • Eng. Obj. Table • Activities and their R-Fields • Calendars (for timephasing)
All the data in one screen Act – Engineering Objects, and their milestones
All the data in one screen Act – DocPkgs - Documents
All the data in one screen Act – POs - Operations
All the data in one screen The 3 activities expanded at the same time.
Time-phasing the data And then turn on and off what you need to see
Object Statuses on a timeline Can be exported to various other formats than pdf
Split histograms On Level 4 and Level 5 data
Planners Workspace Makes a planners life easier
Overview of data to integrate Safran Data Total Plan • Projects/Tenders • MainCat List • Discipline List • Activities History • Detail history (Transparent Reports) Scenario Data • Projects • Activities TimeCatcher Formula MPP History • Actual Hrs for activities • Manpower availability • Monthly Snapshots of MainCat aggreated data
Project portfolio overview Drill down from Project level to activity level, show changes relative last month
Project portfolio overview Pivot on the delta to see changes (per MainCat) relative last month
Project portfolio overview Show historic tracking as well as live forecast.
Project portfolio overview Compare resource availability with demand for a selected set of activities
Project portfolio overview True history is shown together with live plan
Project portfolio overview 4 Key features of the solution: • Drill-Down Portfolio Overview with KPI values derived from lowest level data. • Generate Historical Tracking of Earned Value Metrics (Scope, Actuals, Earned) at aggregated level (*). Show in histogram together with forecast data from live plan. • Pulling data from resident MPP (Manpower Projection System) to get correlation between demand and supply of resources. • (*) A «Report Container» will be saved at each cutoff (Month) to allow revisiting detail status at later time – and create audit trails. • The concept of storing histotoric data at aggregated level makes system «lean» (adds to performance) while the option is open to revisit any point in history with the «same Proteus UI» with full details and reporting options.
Overview of data to integrate PDMS Data Comp Format Cost & Weight Weight Factors View User Overrides Manual Items ADMIN • Manual Items • Weight Factors
Contract follow up on weight and cost Weight and Cost Drill Down into details from project and discipline
Combining PDMS items with Comp Schedule Allows deriving costs
Contract follow up on weight and cost Raw (measurement) Data from PDMS
Contract follow up on weight Compensated Hours pr Discipline/Phase
Contract follow up on weight and cost Using Proteus to combine PDMS data with Comp Schedule to do cost and weight reports