OAKLAND UNIVERSITY. SOUTH FOUNDATION HALL CLASSROOM IMPROVEMENT PROJECT. OU General Purpose Classrooms. There are 101 general purpose classrooms (GPC) located in 11 buildings 60 GPC are located in buildings built between 1959 and 1970 GPC receive basic maintenance
E N D
OAKLAND UNIVERSITY SOUTH FOUNDATION HALL CLASSROOM IMPROVEMENT PROJECT
OU General Purpose Classrooms • There are 101 general purpose classrooms (GPC) located in 11 buildings • 60 GPC are located in buildings built between 1959 and 1970 • GPC receive basic maintenance • GPC upgrades have been limited due to a lack of improvement funds • Instructional technology service to most of the older classrooms is provided on a mobile delivery basis
Why South Foundation Hall (SFH)? • South Foundation Hall houses the highest number (37) of general purpose classrooms • SFH is the most heavily utilized classroom building with over 1,800 students in the building during any given class period • 31 SFH classrooms are equipped at a Level I technology standard which means resources are provided on a delivery basis • Begins to address the need for improvements and upgrades to existing general purpose classrooms
South Foundation Hall Classroom Improvement ProjectBudget A budget of $522,000 was established to upgrade the technology and physical environment on the first floor of South Foundation Hall including all 13 classrooms, the corridor, and the stairwells • Construction $97,037 • Technology $248,690 • Furniture 176,100
SOUTH FOUNDATION HALL CLASSROOM IMPROVEMENT PROJECT OUTCOME • Physical improvements include lighting, painting of all classrooms, corridor and stairwells, new floors and new classroom furniture • Technological improvements include all 13 first floor classrooms with the current Level III standard • Look and feel of a new first floor and stairwells • Faculty and Students will see the difference
SOUTH FOUNDATION HALL CLASSROOM IMPROVEMENT PROJECT TIMELINE • Renovations are scheduled to begin Monday, May 2, 2005. • Completion expected before Wednesday, August 31, 2005. • Fall 2005 classes begin Wednesday, August 31 at 5:00pm.
SOUTH FOUNDATION HALL CLASSROOM IMPROVEMENT PROJECT COMMITTEE Steve Shablin – Office of the Registrar Janet Hepburn – Capital Planning George Preisinger – Classroom Support Kathy Rowley – Office of the Registrar Steve Zmich – Capital Planning
OAKLAND UNIVERSITY SOUTH FOUNDATION HALL CLASSROOM IMPROVEMENT PROJECT