An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. P2 events & perturbations ALICE Technical Coordination Meeting

  2. Overview ALICE Technical Coordination Meeting 10.05 : Cooling water stop 11.05 : Water leak 18.05 : Power glitch

  3. 10.05 : cooling water stop ALICE Technical Coordination Meeting • 16:08, 16:24 – Power cut, affecting control of cooling water • Stop of iced water production • Slow rise in temperature of mixed water • CRs switched over to ‘backup cooling’ by CV piquet • ~17:20 – Iced water restarted, cooling down • Running in degraded mode • ~18:30 – All temperatures back to ~nominal • 11.05 ~11:00 – Back to normal operation • Caused minor perturbation in water temperatures

  4. 10.05 : cooling water stop Switchoverto backup 17:20 Ambient CR1 mixed water[return CR1] mixed water Iced water 16:08 ALICE Technical Coordination Meeting

  5. 10.05 : cooling water stop ALICE Technical Coordination Meeting • Cause: • Communication card in PLC lost due to power cuts • Impact for ALICE: • Increase of iced and mixed water temperatures (both CR and UX) • Reduced cooling efficiency; as usual, most remarkable in CR1 • Water temperatures of dipole close to switch-off limit • Remarks: • Switchover to backup water for CRs had to be done manually • Automatic switchover only on ‘no flow’, not on ‘high temperature’ • Actions: • Modify logic for automatic switchover to backup (by EN/CV)

  6. 11.05 : water leak ALICE Technical Coordination Meeting ~11:00 – A water leak in one of the racks in CR4 was reported Intervention by P2 technicians to stop the leaking purge

  7. 11.05 : water leak ALICE Technical Coordination Meeting • Cause: • Leaking purge in rack CR4-X07 • Impact for ALICE: • Switch off of 2 racks for intervention (FMD and BCM, same power) • Water spilled on back of CAEN crate of BCM • No further damage reported • Remarks: • Leak was spotted by somebody in CR4, but would also have triggered a water leak detection by DSS • Stopping the (normal) power to the rack was in principle not sufficient, as most equipment is on UPS (and would have caused major disruption when cut) • Actions: • Restart regular inspection tours • Procedure for intervention on UPS powered racks

  8. 18.05 : power glitch ALICE Technical Coordination Meeting 05:35 : short power glitch at P2 (and rest of CERN) 20% on 2-3 cycles Impact on most accelerators (beams lost) and some experiments (ALICE and LHCb dipoles)

  9. 18.05 : power glitch ALICE Technical Coordination Meeting • Cause: • Perturbation on 400kV network supplying CERN (no details from RTE yet) • Impact for ALICE: • Dipole tripped off • No other impact reported • Remarks: • Relatively minor impact • Confusion on ramping up magnet • CCC thought ALICE ramped up magnet • ‘Forgot’ to reset beam permit → Required additional ramp down - ramp up • Actions: • Again, strengthen procedure with CCC on ramping magnets • Automatic reset of beam permit by magnet safety system before ramp-up

  10. ALICE Technical Coordination Meeting