1 / 24

GOLD FIELDS LA CIMA S.A.A.

GOLD FIELDS LA CIMA S.A.A. JUNTA GENERAL DE ACCIONISTAS. 30 de Marzo de 2011. “ SI NO PODEMOS OPERAR DE FORMA SEGURA, NO OPERAMOS”. MINA CERRO CORONA. SEGURIDAD, NUESTRO PRIMER VALOR. AGENDA. Resultados 2010 Seguridad Medio Ambiente Producción Costos e Inversión Ratios Financieros

mahlah
Download Presentation

GOLD FIELDS LA CIMA S.A.A.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GOLD FIELDS LA CIMA S.A.A. JUNTA GENERAL DE ACCIONISTAS 30 de Marzo de 2011

  2. “ SI NO PODEMOS OPERAR DE FORMA SEGURA, NO OPERAMOS” MINA CERRO CORONA SEGURIDAD, NUESTRO PRIMER VALOR

  3. AGENDA • Resultados 2010 • Seguridad • Medio Ambiente • Producción • Costos e Inversión • Ratios Financieros • Prioridades estratégicas para el 2011 MINA CERRO CORONA

  4. Resultados 2010 • Resultados 2010 • Seguridad • Medio Ambiente • Producción • Costos e Inversión • Ratios Financieros • Prioridades estratégicas para el 2011 MINA CERRO CORONA

  5. Seguridad • Cero incidentes fatales • Cero incidentes con tiempo perdido • Primer puesto en el Premio Nacional de Seguridad Minera en la categoría de Tajo Abierto otorgado por el Instituto de Seguridad Minera (ISEM) • Certificación Internacional OHSAS 18001-2007 en junio 2010 • Auditoría de Dupont - reforzamiento de cultura de seguridad Operación SeGURA MINA CERRO CORONA

  6. Resultados 2010 • Resultados 2010 • Seguridad • Medio Ambiente • Producción • Costos e Inversión • Ratios Financieros • Prioridades estratégicas para el 2011 Operación RESPONSABLE MINA CERRO CORONA

  7. Medio Ambiente • Re-certificación ISO 14001 • La distinción “Sello Verde” acreditada por la Municipalidad de Cajamarca • Modificación del EIA incluyendo Salaverry aprobada • Actualización del Plan de Cierre de Mina aprobada • Autorización para operar la presa de Las Águilas fue aprobada Operación RESPONSABLE MINA CERRO CORONA

  8. Resultados 2010 • Resultados 2010 • Seguridad • Medio Ambiente • Producción • Costos e Inversión • Ratios Financieros • Prioridades estratégicas para el 2011 SUPERANDO LAS METAS PROPUESTAS MINA CERRO CORONA

  9. Producción • 13.2 Millones de toneladas minadas (↑ 3% vs. 2009) • Planta - foco en optimización • 6.1 millones de toneladas tratadas totales (↑ 2% vs. 2009) • 779 toneladas tratadas por hora (↑ 7% vs. 2009) • Incremento en recuperación de cobre (84%) y oro (66%) • Año record de producción • 196,000 dmt de concentrado producido (↑17% vs. 2009) • 41,000 toneladas de cobre producidas (↑12% vs. 2009) • 152,000 onzas de oro producidas(↑11% vs. 2009) • 406,000 onzas equivalentes de oro producidas (↑22% vs. 2009) SUPERAMOS LAS METAS PROPUESTAS MINA CERRO CORONA

  10. Resultados 2010 • Resultados 2010 • Seguridad • Medio Ambiente • Producción • Costos e Inversión • Principales Ratios Financieros • Prioridades estratégicas para el 2011 COSTOS E INVERSIÓN EN LINEA CON EL PLAN MINA CERRO CORONA

  11. Resultados 2010 - Costos 2009 Cash Cost $368/oz NCE $629/oz 2010 Cash Cost $364/oz NCE $531/oz REDUCCIÓN SIGNIFICATIVA EN EL NCE/OZ MINA CERRO CORONA

  12. Inversiones de Capital Presa de Relaves $55 MM en 2010 US$69 MILLONES INVERTIDOS EN 2010 MINA CERRO CORONA

  13. Presa de Relaves MINA CERRO CORONA Presa de relaves - 2009

  14. Presa de Relaves MINA CERRO CORONA Presa de relaves - hoy

  15. Presa de Relaves MINA CERRO CORONA Presa de relaves - 2009

  16. Presa de Relaves MINA CERRO CORONA Presa de relaves - HOY

  17. Presa de Relaves MINA CERRO CORONA Presa de relaves

  18. Presa de Relaves MINA CERRO CORONA Presa de relaves

  19. Resultados 2010 • Resultados 2010 • Seguridad • Medio Ambiente • Producción • Costos e Inversión • Principales Ratios Financieros • Prioridades estratégicos para el 2010 Sólida performance financiera MINA CERRO CORONA

  20. Indicadores Financieros Sólida Performance financiera MINA CERRO CORONA

  21. Balance 2010 • Desempeño de la Operación en Cerro Corona • Año record de producción segura • Certificación OHSAS 18001 • Re-certificación ISO 14001 • Recrecimiento de la presa de relaves en cronograma y presupuesto • Sólida performance financiera • Control de costos e inversiones • Incremento en márgenes (71% margen operativo) • Reestructuración de deuda - disminución del costo de financiamiento • Cumplimiento de compromisos sociales • Electrificación rural • Agua para comunidades • Convenio de aporte voluntario 2010 – UN AÑO CON RESULTADOS POSITIVOS MINA CERRO CORONA

  22. Prioridadespara el 2010 • Resultados 2010 • Seguridad • Medio Ambiente • Producción • Costos e Inversión • Principales Ratios Financieros • Prioridades estratégicas para el 2011 MEJORA CONTINUA Y CRECIMIENTO MINA CERRO CORONA

  23. Prioridades 2011 • Certificación del Sistema Integrado OHSAS 18001 - ISO 14001 • Optimización de la capacidad de producción – proyectos mejora continua • Recrecimiento de la presa de relaves • Nivel 3746 a fines de Agosto • Optimización encima del nivel 3746 • Evaluación de alternativas para incrementar capacidad de relaves • Estudio de factibilidad y permisos para la planta de óxidos • Ejecución del aporte voluntario • Estimados 2011 • Producción 330 – 360 k oz eq • Cash Cost $420/oz eq • NCE $700/oz eq PRIORIDADES ESTRATEGICAS PARA EL 2011 MINA CERRO CORONA

  24. MINA CERRO CORONA JUNTA GENERAL DE ACCIONISTAS 2010

More Related