LHC scheduling applied to CLIC and ILC

LHC scheduling applied to CLIC and ILC. TILC09 & GDE AAP review – Tsukuba April 2009 K. Foraz. ILC - Civil engineering works. Shaft excavation and Cavern-halls construction based on same hypothesis as M. Gastal = unlimited resources Times derived from Amberg Studies.

Download Presentation

LHC scheduling applied to CLIC and ILC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHC scheduling applied to CLIC and ILC TILC09 & GDE AAP review – Tsukuba April 2009 K. Foraz TILC09 & GDE AAP review – Tsukuba April 2009

  2. ILC - Civil engineering works Shaft excavation and Cavern-halls construction based on same hypothesis as M. Gastal = unlimited resources Times derived from Amberg Studies Site installation & shaft excavation Tunnel excavation Cavern and halls Tunnel concrete and finishes TBM installation TILC09 & GDE AAP review – Tsukuba April 2009

  3. ILC - Civil engineering works Excavation : 9 TBM - 200m/wk Concrete and finishes: 400m/wk Site installation & shaft excavation Tunnel excavation Cavern and halls Tunnel concrete and finishes TBM installation TILC09 & GDE AAP review – Tsukuba April 2009

  4. ILC - Civil engineering works Civil engineering will give you part of machines, and not meters Site installation & shaft excavation Tunnel excavation Cavern and halls Tunnel concrete and finishes TBM installation TILC09 & GDE AAP review – Tsukuba April 2009

  5. ILC - General Services Assumptions: unlimited resources meaning 12 teams for each type of work and for each tunnel !!! (24 teams of electricians for instance) Estimated progress rate per team: around 120m/wks Survey : geodesics & marking positions Piping & ventilation Electrical general services Cabling TILC09 & GDE AAP review – Tsukuba April 2009

  6. ILC - Machine installation Assumptions: unlimited resources !!!! In summary for 7 years installation 9 TBM, 24 electricians teams, 12 cooling and ventilation teams, 12 teams for machine installation Are you able to provide all the machine components in 9 months ??? Support installation and alignment (250m/wk) Machine inst.: transport and interconnections (progress rate to be confirmed 100m/wk) TILC09 & GDE AAP review – Tsukuba April 2009

  7. Resources comparison with CLIC What would be the ILC schedule if machine installation is performed with 2 teams, & what shall be the other resources ? TILC09 & GDE AAP review – Tsukuba April 2009

  8. ILC Schedule smoothed Support installation and alignment (250m/wk) Machine inst.: transport and interconnections (progress rate to be confirmed 100m/wk) TILC09 & GDE AAP review – Tsukuba April 2009

  9. Resources comparison with CLIC TILC09 & GDE AAP review – Tsukuba April 2009