1 / 6

ExoMars 2016 Mission TGO Aerobraking and Science Orbit ESWT #5 ESTEC, 14 September 2013

ExoMars 2016 Mission TGO Aerobraking and Science Orbit ESWT #5 ESTEC, 14 September 2013. Daniele Temperanza , ExoMars GNC and AOCS System Engineer Michael Khan, Exomars Mission Analyst. TGO Aerobraking Timeline.

major
Download Presentation

ExoMars 2016 Mission TGO Aerobraking and Science Orbit ESWT #5 ESTEC, 14 September 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ExoMars 2016 Mission TGO Aerobraking and Science OrbitESWT #5ESTEC, 14 September 2013 Daniele Temperanza, ExoMars GNC and AOCS System Engineer Michael Khan, ExomarsMission Analyst

  2. TGO Aerobraking Timeline • Aerobraking reduces the orbit from a highly eccentric ellipse to a low near-circle, as required for science ops • Start of Aerobrakingearly Nov 16 • Solar Conjunction wait-out From apoares altitude of 7000 Km till SES angle >10̊ mid May-late Aug 17 • End of Aerobraking and start of Science Ops mid Nov 17 (including Commissioning) • End of Science Ops (after one Martian year) mid Oct 19

  3. Aerobraking Orbit • Initial periares / apoares altitude 200/33474 Km • Final orbit altitude (near-circular) 400 Km • Orbit inclination (unchanged by aerobraking) 74 deg • Longest eclipse duration encountered 160 min

  4. Aerobraking Main Control Parameters • Maximum peak heat flux 2800 W/sqm • Maximum heat load per pass 500 KJ/sqm • Maximum dynamic pressure 0.7 N/sqm • No Science Ops allowed • Aerobraking is a very critical phase and therefore only essential functions shall be supported

  5. TGO Design and Autonomy during Aerobraking • Dedicated GNC mode to deal with atmospheric passes • HGA in stowed configuration during all Aerobraking • Solar Arrays and GNC contribute to the stabilization around the aerodynamic equilibrium point during the passes • Outside passes SA and S/C pointing are constrained to guarantee power and communication • Dedicated Aerobraking Safe mode • Acquire Sun pointing and perform automatic orbit maneuvers, then allow for communication to Ground Control for investigation and recovery

  6. TGO Science Orbit • The baseline Science Orbit is a near-circular orbit with an altitude of ~ 400 Km (in line with the TGO Science AO), inclined at 74 deg with ground track that closes after 3-5 days (with gaps) • Perturbations introduce variation in eccentricity (up to 0.015) • The altitude over any given latitude may vary by +/- 50 Km around 400 Km during the course of one Martian year