60 likes | 141 Views
Briefing to Christchurch MPs and representatives 20 April 2011. Aaron Muir Project Director, Fletcher EQR Walter Friedel Project Manager, Clean Heat Hub. Establishment / Focus. 14 geographical Hubs established 5 others being established Specialised Clean Heat Hub
E N D
Briefing to Christchurch MPs and representatives20 April 2011 Aaron Muir Project Director, Fletcher EQR Walter Friedel Project Manager, Clean Heat Hub
Establishment / Focus • 14 geographical Hubs established • 5 others being established • Specialised Clean Heat Hub • Emergency focus since Feb 22 event • Separate but parallel focus on Winter Heat • Resources diverted from ‘full repair’ programme except in areas with less severe damage
Resources • Working with local contracting companies • 3,500 applications (all trades) • 1,163 have supplied accreditation information. • 395 accredited to date • 70 non-accredited working on emergency basis • 2,500 tradesmen inducted • Accredited contractor manages each job, with trades sub-contracted
Winter heat establishment • Priority = sole source of heat lost, and vulnerable through personal circumstances • Clean Heat Hub • Claims administration • Contract management • Consent exemptions / inspections process for Solid Fuel Burners • Approximately 140 heat pump installers • Approximately 40 solid fuel burner installers • Outbound call centre focused on priority claims • Contact via 0800 DAMAGE (0800 326 243) or heating@eqr.co.nz • We will also accept information on third parties who are unable to contact us directly
Winter heat progress • Expect to complete 4,500 priority cases by mid-May • 10,000 chimney claims closed to date • 5,278 allocated • 3,500 opted out • 1,500 not contactable • 1,360 installations / repairs completed to date • Heat pumps • 1,100 installed to date / 3,000 on order • Industry capacity 1,250 per week – Lead times average 2 weeks • Solid fuel (new and repairs) • 260 completed to date / 2,250 on order • Industry capacity 200 per week – Lead times average 1 mth, rising to 2 mths • Identifying new priority cases • EQC claim process • Co-operation with government, charitable and other agencies • 50,000 calls completed by Clean Heat Hub – 2,000 to 3,000 calls per day
Other repairs • 802 ‘full repair’ claims completed and 2,742 in progress at 15 April • 6,200 emergency repair projects (excluding winter heat) completed • 1,700 currently in progress • Response time 1-7 days for the most urgent cases • Total claim numbers will be higher than the 60,000 first envisaged • Average claim size also likely to grow – initial expectation was $30,000 average