1 / 39

PUBLIC OPEN DAY : 12 April 2012

Deepening, Lengthening and Widening of Berth 203 to 205, Container Terminal, Pier 2, Port of Durban. PUBLIC OPEN DAY : 12 April 2012. WELCOME & INTRODUCTION. WELCOME! Thank you for taking the time to attend the Public Open Session.

makya
Download Presentation

PUBLIC OPEN DAY : 12 April 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Deepening, Lengthening and Widening of Berth 203 to 205, Container Terminal, Pier 2, Port of Durban PUBLIC OPEN DAY: 12 April 2012

  2. WELCOME & INTRODUCTION WELCOME! Thank you for taking the time to attend the Public Open Session. Your presence is appreciated ...Please take a seat and watch the presentation. After the presentation you will have an opportunity to ask the technical and environmental teams questions. Should you have any comments please complete a reply form. We value your contribution to the EIA process. 2

  3. VENUE LAYOUT 3

  4. MEET THE PROJECT TEAM Proponent Consultants 4

  5. WHY HAVE A PUBLIC OPEN DAY??? To provide an introduction, background and overview to the project to you; To discuss the environmental authorisation processes; and To provide an opportunity for you to submit and raise your comments for consideration by the project team. 5

  6. WHY IS THIS PROJECT NECESSARY??? The current quay walls at Berth 203 to 205 are over 50 years old and is beyond its original design limits. Hence, the quay walls are considered unsafe and need to be upgraded. At the same time the Port of Durban has experienced a steady growth in container numbers and vessel sizes. Therefore, the design for the upgrade to the existing quay walls needs to take into account the larger vessels entering the Port. As the berth channel is not deep enough, large vessels can only enter and leave the Port at high tide which negatively impacts the efficiency of the Port. Further, the Port of Durban is considered a ‘hub’ port and to maintain this status, it needs to accommodate the larger vessels which will improve its efficiency. Hence, the upgrade of the unsafe quay walls presents an opportunity to improve the safety and efficiency of the Port of Durban. 6

  7. WHERE IS THE PROJECT LOCATED??? FOCUS OF THE PROPOSED PROJECT IS PIER 2 PIER 2 PIER 1 DURBAN CONTAINER TERMINAL COMPRISES OF 15 BERTHS CAN ACCOMADATE 8 POST PANAMAX VESSELS

  8. WHERE ARE BERTHS 203 to 205 LOCATED? 203 204 205 WATER DEPTH -12.8m CDP EXISTING CRANE ASSEMBLEY AREA TOTAL EXISTING BERTH LENGTH OF 914m EXISTING SANDBANK

  9. WHAT IS THE PROBLEM WITH THE EXISTING QUAY WALLS??? • It was built in the 1960s and does not meet the minimum Eurocode 7 Safety Standards; • The berth channel is not deep enough as a result scour holes have formed which has undermined the structural stability of the existing quay wall; • The berths are only 914m long and it needs to be 1190m to accommodate three Super Post Panamax vessels; and • The current quay wall cannot safely accommodate the larger Ship to Shore cranes.

  10. WHAT EXACTLY IS THIS PROJECT ABOUT??? The project involves: The westward lengthening of Berth 205 by 170m; The eastward lengthening of Berth 203 by 100m; The widening of Berths 203 to 205 by 50m; The deepening of the Berth channel, approach channel, and vessel turning basin from the current -12.8m CDP to -16.5m CDP; Excavating the trench for the new quay wall structure from -12.8m CDP to -19m CDP (for caisson option only); The offshore disposal of dredge material; The offshore sand winning for infill material; and The installation of new Ship to Shore (STS) cranes and associated infrastructure. 10

  11. WHAT ALTERNATIVES WERE CONSIDERED? The EIA Regulations require that we consider different alternatives. For this project no location alternatives were considered as the upgrade is confined to the existing unsafe quay walls. Instead, technical alternatives were identified. Initially, seven different technical quay wall types were assessed and the following three were found to be most feasible: • Deck on Pile Quay Wall; • Sheet Pile Quay Wall; and • Caisson Quay Wall. 11

  12. TECHNICAL ASPECTS OF THE PROJECT Now that you understand where the project is located, why it is necessary and what it will entail, please welcome Mr. Ivan Moonsamy, Project Manager from TNPA who will take you through the technical aspects of the project. Please raise all questions at the technical table and not during the presentation. All questions will be recorded and included in the final Scoping Report. 12

  13. VESSEL SIZES AT DCT DCT is presently operating vessels of 6000 TEU and greater The original quaywall was designed to accommodate a 1000 TEU vessel with wharf cranes

  14. EXTENSIONS 170m Extension of Berth 205 100m Extension of Berth 203

  15. BAYHEAD LOT10 Lot 10 Casting Yard and Storage Area to be used during the proposed project

  16. PROJECT DESCRIPTION - ALTERNATIVES Deck On Pile Quay Wall 16

  17. DECK ON PILE 17

  18. PROJECT DESCRIPTION - ALTERNATIVES Sheet Pile Quay Wall 18

  19. SHEET PILE 19

  20. PROJECT DESCRIPTION - ALTERNATIVES Caisson Quay Wall 20

  21. CAISSON 21

  22. DCT BERTH DEEPENING PROJECT – BERTHS 203 TO 205 HOW WILL THE PROJECT BE PHASED??? PHASE 1 – JULY 2013 TO DECEMBER 2014 EXTEND BERTH 205 AND DREDGE APPROACH CHANNEL AND BASIN PHASE 2 – JAN 2015 TO JULY 2016 PHASE 3 – AUG 2016 TO DECEMBER 2017 EXTEND BERTH 203 203 204 205

  23. DREDGING AND OFFSHORE DISPOSAL Approach Channel and basin will be deepened from existing -12.8m CDP to -16.5m CDP by dredging. Estimated 4.5 million m3 of material will be dumped offshore Lot 10 Casting Yard and Storage Yard

  24. DREDGING AND OFFSHORE DISPOSAL • Disposal of material at current offshore disposal site 24

  25. DREDGING AND OFFSHORE DISPOSAL • Disposal of material at current offshore disposal site 25

  26. OFFSHORE BORROW AREAS

  27. Thank you Ivan. By now you should have a better understanding of the details of this project. The following slides are about the environmental process that will be followed. If you are not interested in watching the remaining 12 slides, please proceed to the technical table. 27

  28. ENVIRONMENTAL AUTHORISATION PROCESSES 28

  29. ENVIRONMENTAL AUTHORISATION PROCESSES Proposed Approach NEMA - EIA Proposed Approach MPRDA – Offshore Borrow Pits Proposed Approach NEM: ICM – Dumping at Sea Permit 29

  30. PUBLIC PARTICIPATION PROCESS TO DATE • To date the following as been undertaken: • The landowner (Transnet) was notified; • A focus group was convened; • A random survey was conducted; • Adjacent landowners within 100m were notified; • On site notices and adverts were placed; and • A project specific website domain was registered. 30

  31. PROOF OF LANDOWNER NOTIFICATION

  32. OUTCOME OF RANDOM SURVEY 32

  33. PROOF OF SITE AND ADVERT NOTIFICATION 33

  34. LOCATION OF DRAFT SCOPING REPORT The draft Scoping Report was made available at the following venues for review. I&APs on the Durban Bay Estuarine Management Plan Database were notified and encouraged to review the scoping report. • Seafarers Club • Central Library In addition, the draft Scoping Report was made available on the project website : www.berth203to205expansioneia.co.za The draft Scoping Report is available for public review from 9 March 2012 to 30 April 2012 (50 days) 34

  35. AUTHORITIES MEETING • The following authorities were invited to a meeting held on 29 February 2012 to discuss the project: 35

  36. OTHER LICENSING PROCESSES • A Mining permit for the offshore borrow pit will be made to DMR in terms of the MPRDA. • A Dumping At Sea Permit for the offshore disposal site for the dredge material will be made to the DEA in terms of the NEM:ICM. 36

  37. SPECIALIST STUDIES TO BE UNDERTAKEN Estuarine/Marine Biodiversity Assessment; Marine Archaeology Assessment; Local Economic Impact Assessment; Sediment and Chemical Analysis of Dredge Material; Ecological Assessment of Impacts on the Central Sandbank; Assessment of Indirect Impacts on the Little Lagoon; Sediment Plume Analysis for Offshore Sand Winning; Shoreline Stability for Offshore Sand Winning; Wave Energy Analysis as part of Technical Studies; and Geotechnical Study as part of Technical Studies. 37

  38. WHAT IMPACT DOES THIS PROJECT HAVE ON THE 1999 RoD??? 38

  39. This brings us to the end of the presentation. We trust that you have sufficient information on the project. Please raise all questions at the technical station. We encourage you to complete a reply form before you leave if you have any comments. Should you prefer, please free comment anonymously. THANK YOU FOR YOUR TIME. 39

More Related