Ad Valorem – Capital Projects

Ad Valorem – Capital Projects. April 28, 2008. Purpose. Two budget workshops this week – today and tomorrow Focus on Ad Valorem funded projects Gain Board direction Other non-ad Valorem funded projects will be reviewed at later workshops. Past Capital Accomplishments.

malana
Download Presentation

Ad Valorem – Capital Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ad Valorem – Capital Projects April 28, 2008

  2. Purpose • Two budget workshops this week – today and tomorrow • Focus on Ad Valorem funded projects • Gain Board direction • Other non-ad Valorem funded projects will be reviewed at later workshops

  3. Past Capital Accomplishments • Charlotte County has enjoyed a sustained period of building and re-building Capital Infrastructure. • The Event and Conference Center • Emergency Operations Center • New Fire Stations • Regional Parks • Mid County Regional Library

  4. Current Budget Distribution

  5. Budget Issues • Priorities from the Board of County Commissioners: • Reduce Murdock Village debt and develop a re-payment plan for the remaining debt • Consider delay of Capital Projects to help fund operations during reduced revenues from Amendment 1 and potential de-valuations

  6. The Approach • Re-think each Ad Valorem funded project in the Adopted FY07/08 CIP • Putting projects into the following categories: • Projects Eliminated • Projects Delayed • Projects Continued

  7. Projects Eliminated • Projects that are suspended and budgeted dollars can be re-directed for Murdock debt pay-down or revenue shortfall

  8. Projects Delayed • Projects that will be delayed (moved out of the CIP for FY07/08) and re-directed for Murdock pay-down or revenue shortfall. • Delay includes re-thinking and re-engineering • Delay period: 1-4 years • How will projects get re-funded? - capital millage rate .3887 - $7M

  9. Projects Continued • Currently in construction • Safety or ADA Issues • Concurrency

  10. How much to re-direct? • Goal - $22 Million • $11 M for Murdock pay-down • $11 M for Revenue shortfall Redirection comes from eliminated and delayed projects

  11. List of 42 Projects • Review key points of each project • Give staff recommendation • Seek Board agreement with staff recommendation or provide other direction

  12. The Jail Expansion • This project has significant capital and operating dollars budgeted • Will address at the end of this meeting or tomorrow to give adequate time for discussion of options and questions to BCC staff and Sheriff Office personnel.

  13. #1 – Second Floor Renovation • Project Eliminated • Amount available for re-direction = 1.9 M

  14. #2 - Human Services Building • Recommendation – delay, $ 1.6 M • Staff currently at other County locations • $271,000 spent – design and construction documents • Understanding funding needs staff recommends re-direction of funds but if funding is available this would be a high priority project.

  15. #3 – District 1 Sub Station • Staff Recommendation - delay • New Sheriff sub-station (West County) • project’s revenue source was from Impact Fees • $1 million shortfall in Impact Fees • delay until Impact Fees are collected, reduce scope of work, or consider leasing

  16. #4 – Hickory House • Delay $209,000 • Located at Dotzler Park • Project was to rehabilitate structure and open to public • Will reconsider in future CIP submittals

  17. #5 - Facility Parking and Lighting • Harold Ave. Walkway Lighting • Delay - $200,000 • Project was to improve parking and pedestrian lighting

  18. #6 - Placida Fishing Pier / Placida Park Area • Delay $246,000 • Elements of project include: preservation of Placida Bunk House and design - Rotary Centennial Park • Bridge Construction delays project 1 year • Will be considered in future CIP submittal

  19. #7 – Port Charlotte Beach Park • Continue $700,000 for boardwalk and fishing pier deck replacement • Delay $323,000 – Maintenance Building (delay and continue to seek FEMA funds) - Building was destroyed during Hurricane Charley

  20. #8 - Fishing Piers and Boardwalks • Englewood Beach Boardwalk • Continue - $612,000 • Replacement and repair of Beach Boardwalk • Eliminate - $52,000 – Kiwanis Park footbridge (cost savings from in-house labor and refined cost estimate)

  21. #9 - Harold Ave. Recreation Cntr • Continue - $190,000 for gym insulation repair and gym floor repair. • Repairs are a necessary element of project • Delay - $760,000 – entrance and pedestraian lighting not as critical and will be reconsidered in future CIP

  22. #10 – West County Boat Ramp • Continue - $142,000 to complete design and permitting • Delay - $2,092,000 – construction

  23. #11 - Tringali Park Bldg 3 • Continue $10,000 – complete analysis of structural repairs • Delay - $170,000 – Englewood Library re-use plan not needed at this time

  24. #12 - FEMA Window Grant • 5- story Murdock Admin Building • Continue - $569,000 to leverage grant $ from FEMA • Note – FEMA contribution of $1,200,000 • Design complete • Eliminate - $100,000 savings from anticipated favorable bids

  25. #13 - Fire Training / Burn Building • Continue - $369,000 – to construct new building – recommend continuing as this is partly funded from Sales Tax Extension along with FEMA. Eliminate - $375,000 – reduction in size of building and site work

  26. #14 - Small Building Repairs and Upgrades • Continue - $252,000 for Englewood Library structural repairs and Cookie House preservation plan • Englewood Library structural repairs are critical due to water damage • Cookie House – to develop preservation plan that would protect the structure from further deterioration

  27. #15 - Ainger Creek Boat Ramp • Eliminate $110,000 (Ad Valorem funding only) • Other funding sources will allow project to proceed with a decreased scope of work or seek other funding • This project was to create a formal paved parking area.

  28. #16 – Horse Arena • Delay - $81,000 – Score Tower replacement (damaged from Hurricane) • FEMA and Insurance not adequate for re-building at current standards • Will seek other funding sources

  29. #17 – South County Annex • Project Eliminated • Amount available for re-direction = $850,000

  30. #18 - Spring Lake Park Restroom • Delay - $50,000 • Plan was to construct new restroom – recommend delay construction until alternate funding is available through parking fees or Boater Improvement Funds.

  31. #19 – Carmalita Park • Delay -Concession Building replacement - $383,000 • Destroyed by Hurricane • FEMA and Insurance funds inadequate

  32. #20 – Holiday Lakes Boat Ramp • Eliminate - $75,000 for parking improvements and dock repair • Eliminate Ad Valorem funding only – Boater Improvement Funds ($50,000) will allow for a reduced scope of work • Seeking additional Boater Improvement Funds

  33. #21 - Bayshore Live Oak Park • Continue - $149,000 Interpretive Sign Program – park of Master Plan • Delay - $125,000 playground • Delay of playgrounds – countywide discussion to include Oyster Creek and Charlotte Sports Park

  34. #22 - Renovation of Fire Stations • Continue - $2,689,000 – to complete construction of: Station #9 (S.R. 31) Station #11 (Harbour Heights) • This completes an on-going program of renovating fire stations • Eliminate - $400,000

  35. #23 - Oyster Creek Regional Park • Delay - $55,000 – to complete Park Signage

  36. #24 - Sunrise Park • Continue - $200,000 to complete contracted construction work • On Edgewater Drive • Project: - Fishing dock, restroom, canoe launch and parking, etc.

  37. #25 - Event and Conference Center • Continue and complete construction

  38. #26 - Florida Friendly Landscape • Eliminate $80,000 (Ad Valorem) • Project continues (reduced scope) with Native Tree Trust Funding

  39. #27 - Pavement Maint. & Resurfacing • Delay - $987,000 • Various County locations – program expands, resurfaces, re-stripes and maintains parking areas • This action delays this program for 1-year

  40. # 28 - Security Upgrades • Postpones security for 2nd floor of newly renovated historic Courthouse - $179,000 • Will re-program when Court occupies the space

  41. #29 - Playground Replacement and Purchase • Delay - $425,000 Locations include: • Oyster Creek Reg. Park – • Charlotte Sports Park and • Various replacements • Delay period – based on funding availability and prioritization

  42. #30 - Park Land Acquisition • Delay $160,00 • Funding was for purchase of properties near existing park facilities

  43. #31 - Parking / Stormwater Improvements • Harbour Heights Park • Delay - $540,000 • This funding was to address an existing drainage / flooding item

  44. #32 - Various Facility Improvements • Continue - $300,000 • Delay - $380,000 • Program continued for improvements and renovations to county facilities to comply with building codes and ADA requirements

  45. #33 - Sports Lighting • Continue - $20,000 – replacement of Camalita Field #3 – electrical switch gear due to critical safety issue. • Delay - $180,000 – New skate park lighting at Oyster Creek Regional Park. The $180,000 was to supplement a $20,000 donation for the skate park lighting.

  46. #34 - ADA Renovations • Continue - $415,000 • Historical Center • Cedar Point • Harold Ave. Park • ADA and Safety requirements

  47. #35 - Ambulance Replacement • Continue $360,000 to replace two (2) ambulances due to high milage • This is an on-going annual replacement program • Eliminate - $18,000 – favorable pricing

  48. #36 - Family Services Center • Continue - $200,000 • Eliminate - $2,000,000 • Delay - $1,600,000 • Continue – ADA & Safety issues • Delay – re-evaluate highest priorities and have future discussion with Board • Eliminate – previously requested expansion

  49. #37 – West County Regional Library • Delay - $863,000 – (design) • Spent to date – $337,000

  50. #38 – RR Trestle Removal / Repair • Delay - $700,000 • Locations: Boca Grande and Myakka River • Board previously discussed – contract not awarded