1 / 10

GLAST Large Area Telescope: Mechanical Systems Peer Review 27 March 2003 Section 4.4

Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: Mechanical Systems Peer Review 27 March 2003 Section 4.4 Heat Pipe Thermal Design Aaron Avallon Heat Pipe Product Center Design Engineer aaron.r.avallon@lmco.com. Heat Pipe Performance Requirements.

malana
Download Presentation

GLAST Large Area Telescope: Mechanical Systems Peer Review 27 March 2003 Section 4.4

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Mechanical Systems Peer Review 27 March 2003 Section 4.4 Heat Pipe Thermal Design Aaron Avallon Heat Pipe Product Center Design Engineer aaron.r.avallon@lmco.com

  2. Heat Pipe Performance Requirements Based on: Results of Overall LAT Thermal Math Model Verification Methods A: Analysis T: Test Margin is determined by: EP/Req Must be > 1.3

  3. Heat Pipe Sizing (1 of 2) • All worst case pipe requirements derived from detailed thermal model hot case with the following assumptions and results • Top Flange • 1 of 5 pipes failed • Cumulative heat load and transport requirement calculated directly from Heat Flux (W/m) vs Length Along Pipe (mm) graph • Results in a 9.2 W-m requirement for each pipe • Downspout • 1 of 6 pipes failed • Maximum environmental load on one radiator panel • Maximum dissipation from the grid of 252 W • All grid heat load must be transported to one radiator • Resulting power requirement for each pipe is 40 W

  4. Heat Pipe Sizing (2 of 2) • X-LAT • 1 of 6 pipes failed • Cumulative heat load and transport requirement calculated directly from Heat Flux (W/m) vs Length Along Pipe (mm) graph • Results in a 59.5 W-m requirement for each pipe • VCHP • 1 of 6 pipes failed • Maximum environmental load on one radiator panel Maximum dissipation from the LAT of 612 W to be dissipated into one radiator panel • Resulting power requirement for each pipe is 94 W

  5. Heat Pipe Qual/Acceptance Tests (1 of 2) • Qualification Tests • Extrusion charge optimization (VCHP only, new extrusion) • Burst: 4 * MEOP (Maximum Expected Operating Pressure) • Constant Conductance Heat Pipe Acceptance Tests • Leak: Ammonia leak < 1x10-7 scc/sec • Proof Pressure: Greater of 1.1 * MPP (Maximum Processing Pressure) or 1.5 * MEOP • Non-Condensable Gas: Verify acceptable level • Transport: Capability > 1.3 times requirement • Ammonia Charge: Mass recorded before and after charging

  6. Heat Pipe Qual/Acceptance Tests (2 of 2) • Variable Conductance Heat Pipe Acceptance Tests • Leak: Ammonia leak < 1x10-7 scc/sec • Proof Pressure: Greater of 1.1 * MPP (Maximum Processing Pressure) or 1.5 * MEOP • Transport: Capability > 1.3 times requirement • Control Gas (He/Ne) Charge Quantity: Verify correct quantity • Ammonia Charge: Mass recorded before and after charging • Wicking: Tested to insure sufficient wicking (In process test) • Control Performance: Deferred to radiator assy level

  7. Heat Pipe Structural Analysis (1 of 2) • Top Flange and Downspout Heat Pipes external loads insignificant relative to internal loads due to mounting configuration • Structural integrity demonstrated by heat pipe Qual./Acceptance tests • X-LAT Heat Pipe covered in X-LAT Plate structural analysis presentation • VC Heat Pipe covered in Radiator Assembly structural analysis presentation, preliminary analysis covering reservoir and transition complete with the following assumptions and results: • MEOP of 377 PSI (140ºF)**(requirements changed to 490 PSI) • MPP of 882 PSI (210 ºF) • Acceleration loads of 35 G’s replace external flight loads

  8. Heat Pipe Structural Analysis (2 of 2) MEOP: Maximum Expected Operating Pressure MPP: Maximum Processing Pressure

  9. VCHP Reservoir & Radiator Sizing • Reservoir Sizing: • Hot case effective sink temperature = 233 K • Cold case effective sink temperature = 193 K • Computed storage volume ratio = 1.1 (-10ºC to +15ºC) • Required reservoir volume = 75 cc

  10. Document Status

More Related