Relocation and shielding activities Status and roadmap R2E project meeting, 7th April 2011 A. L. Perrot
R2E shielding activities • Integration • - all shielding walls = integrated; agreed by LHC integration team • - official approval process to be launched through ICL • Deadlines: • Points 8: 13 April • Point 1: 20 April • Point 5: 4 May • - simplified models still needed afterwards for implementation in CATIA models • Orders • all blocks are now ordered • Point 1 RBs special shape ‘frites’: 18th/19th April technical reception in Austria of the first 2 blocks by M. Lazzaroni and C. Saint Jal • pre-series of blocks 4x4 x2, 6x3x3: check by June in Bulgaryby M. Lazzaroni and C. Saint Jal • Logistics • Cleaning and painting of the ‘old’ blocks = finished yesterday • Storage place: blg 157 implementation storage area under progress 1
R2E shielding activities • planning • Blocks delivery • all @ CERN in November 2011 • 4x4x2 & 6x3x3 : all delivered @cern in November 2011; • ‘frites’: all delivered @cern in June 2011 • bricks: order sent yesterday - all delivered @cern end of June 2011 • 2011-2012 Xmas activities goals • Point 1:UJs & RBs, • be ready for Point US85 UJ17/16 - RB 16 UJ13/14 - RB 14 IP1 US85 LHC tunnel Courtesy M. Lazzaroni Courtesy A. Tursun, J.- M. Bianco, F. Delsaux 2
R2E relocation activities • Integration studies • - Point 8: finished • Point 5: see the end of the tunnel; finished by the end of April • Point 1: new proposal under check; need to know the exact position of the area to empty -> CE input. • Point 7: need the ‘Safe room’ study conclusions to go ahead • Approval through ICL- deadlines • Point 8: 20th April; • Point 5: 4th May; • Point 1: 8th June; • Point 7: ? • 2011-2012 Xmas shutdown goals • anticipate possible relocations – list of activities by June • mark on floor all the future equipment locations; • - Point 8: valves positionners(t.b.c), cooling cabinet in UJ87-> UA87; • Point 1: fire detectors; • Point 5: survey GGPSO installation in by-pass 3
R2E relocation study in Point 1 Point 1- Relocation TODAY UJ16 UL16 Courtesy A. Tursun, Y. Muttoni 4 A. L. Perrot, 2nd March 2011
Situation in UL14/16 after relocation (present study) RYLC 01 RYLB 01 RYMCB 01-04 RYSC 01 QYC 02 QYC 01 (additional rack) RYCA 01 RYCA 02 DYXA 01 additional rack 2 Power Converters area to be reconsidered DYPG 01 CYCIP 01 Courtesy A. Tursun, Y. Muttoni “LHC Performance Workshop”, 25 January 2011, A. L. Perrot DYPG 02 TYCFL 01 Fire detectors
Situation in UL14/16 after relocation (new proposal) RYLC 01 RYLB 01 RYSC 01 B QYC 02 QYC 01 (additional rack) RYCA 01 RYCA 02 RYMCB 01-04 C 2 Power Converters A area to be reconsidered distance A-B= 18.5m distance A-C= 25m DYPG 01 CYCIP 01 TYCFL 01 to be relocated in US15 level 2 close to TYCCR01 rack DYPG 02 DYXA 01 Fire detectors