Progress Report. FAIR @ Darmstadt. F acility for A ntiproton & I on R esearch. Nuclear Structure & Astrophysics (Rare-isotope beams). Hadron Physics (Stored and cooled 14 GeV/c anti-protons). SIS18. p-Linac. SIS100 /300. UNILAC. QCD-Phase Diagram (HI beams 2 to 45 GeV/u).
E N D
Progress Report NuPECC, Copenhagen, 15/6/12
FAIR @ Darmstadt NuPECC, Copenhagen, 15/6/12
Facility for Antiproton & Ion Research Nuclear Structure & Astrophysics (Rare-isotope beams) Hadron Physics (Stored andcooled 14 GeV/c anti-protons) SIS18 p-Linac SIS100/300 UNILAC QCD-Phase Diagram (HI beams 2 to 45 GeV/u) HESR Rare-Isotope Production Target Fundamental Symmetries & Ultra-High EM Fields (Antiprotons & highly stripped ions) Anti-Proton Production Target Dense Bulk Plasmas (Ion-beam bunchcompression & petawatt-laser) CR &RESR Cryring NESR Materials Science & Radiation Biology (Ion & antiproton beams) 100 m Accelerator Physics NuPECC, Copenhagen, 15/6/12
CivilConstruction NuPECC, Copenhagen, 15/6/12
CC PlanningActivities NuPECC, Copenhagen, 15/6/12
Licensing 31.08.11 19.01.12 21./23.11 02.02.12 07.03.12 12.02.12 NuPECC, Copenhagen, 15/6/12
Preparatory Work NuPECC, Copenhagen, 15/6/12
Aerial View NuPECC, Copenhagen, 15/6/12
Accelerator Challenges Compact & cost effective accelerators Fast cycling superconducting magnetsdB/dt~ 4T/s Precision beams Electron & stochastic cooling XHV @ high beam intensities Extremely high vacuum ~10-13mbar Fast acceleration High gradient, variable frequencyFerrite & MA loaded cavities NuPECC, Copenhagen, 15/6/12
Accelerators • 113 SIS100 dipolesorderedfrom Babcock Noell in Jan. 2012 (German in-kind contribution) • Manyotherpartsof SIS100 and CR in preparation. • HESR readytobesubmittedfortender. • IKRB meetingat FAIR on 28/3/12 • MAC meetingat FZ Jülich on 2/4/12 Compact & cost effective Fast cycling superconducting magnetsdB/dt~ 4T/s NuPECC, Copenhagen, 15/6/12
FAIR Experiments CBM APPA Super-FRS PANDA NuSTAR NuPECC, Copenhagen, 15/6/12
Experiments • Collaborations finish R&D phase • Collaborations submit complete sets of TDRs to FAIR • FAIR establishes Expert Committee Experiments, ECE • TDR Review Panels: ECE members (+ external experts) • FAIR organises/monitors the co-ordination of experiments with • Civil construction & setup of accelerators/storage rings • Collaborations identify critical pathways regarding • Timelines, milestones & deliverables • Collaborations submit risk management plans • To be assessed by FAIR & integrated into Risk Reports to AFC and Council • Funding Issues • FAIR establishes Resources Review Boards for each Collaboration consisting of all Research Councils participating in the experiment(s) • Funding Agencies, Collaborations and FAIR negotiate Construction MoUs NuPECC, Copenhagen, 15/6/12
OrgChart NuPECC, Copenhagen, 15/6/12
Timeline 2011 2012 2013 2014 2015 2016 2017 2018 2019 12 9 11 6 7 8 10 Building permits Site preparation Civil construction contracts Building of accelerator & detector components Completion of civil construction work Installation & commissioning of accelerators and detectors Start Data taking 10 6 7 12 8 9 NuPECC, Copenhagen, 15/6/12 11