Stormwater Maintenance and Replacement Program

Stormwater Maintenance and Replacement Program. November 21, 2006 Patricia Biegler, P.E. Richard Broad, P.E. Background. August 2000. 2001. 2006. $1.75 /ERU/Month. $2.55 /ERU/Month. Fee. $2.55 /ERU/Month. Pipe. 275 miles. 1,000 miles. 1,100 miles. Public Ditch. 1,320 miles.

marc
Download Presentation

Stormwater Maintenance and Replacement Program

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Stormwater Maintenance and Replacement Program November 21, 2006 Patricia Biegler, P.E. Richard Broad, P.E.

  2. Background August 2000 2001 2006 $1.75/ERU/Month $2.55/ERU/Month Fee $2.55/ERU/Month Pipe 275 miles 1,000 miles 1,100 miles Public Ditch 1,320 miles 2,500 miles 2,700 miles Documented Citizen Calls 2,999 7,475 11,397 Projected Ditch Clearing Level of Service 5 – 7 Years* 10 – 15 Years 10 – 15 Years Ditch Cleaned 90 miles* ** 36 miles Backlogged Cave-Ins 600 ** 1,000 + * Using Streets Crews & Temps ** Not Available

  3. Current Funding FY 06-07 OPERATING CAPITAL TOTAL Stormwater Fee $3.3 M $1.3 M $4.6 M Drainage (General Fund: Roughly 40% from State Maintenance) $1.8 M - $1.8 M TOTALS $5.1 M $1.3 M $6.4 M Other Funding Sources State Maintenance Pro-rata Grants General Fund

  4. Stormwater Program Components • Environmental • Permitting and Water Quality • Inspections • Maintenance • Ditches, Pipes, Lakes, Curbs & Gutters, + Structures • Emergency Response • Capital Needs • Provide Flooding Protection • Improve Level of Protection • Neighborhood Appearance Yellow Red Red

  5. Issues • Loss of Capital Buying Power • Fee Increase in 2000 of $0.85/month/ERU • Increased Regulatory Requirements • Testing, Inspection & Enforcement • Wetlands Permitting • Operating Increase • Salaries & Fringes • Materials • Contracts • Debris Hauling & Disposal • Transportation of Debris • Property Issues • Land Values • Easements • Access • Encroachments • Growing Backlog - 3500 + Citizen’s Requests

  6. Maintenance Requirements Ditch Cleaning/Debris & Vegetation Ditch Regrading Erosion Control Ditch Widening TV Pipe Pipe Resetting Pipe Washing Cave Repair Curb & Gutter Inlet Driveway Pipes, Culverts, etc. Lake Pipe Ditch Outfall Natural Waterway Streetsweeping Cleaning Inlets & Structures Pipe Washing Cave Repair Lake Maintenance & Dredging Blockage Removals Fish Kills Erosion Control Pipe Resetting Pipe Washing Pipe & Culvert Installation

  7. Maintenance & Service • In most cases – Vegetation is a minor issue. • Real Problems are: • Collapsed Pipes • Undersized Pipes • Off-Grade Pipes • Undersized Ditches • Undersized Culverts • Off-Grade Ditches

  8. What it takes to fix: Annual Additional Funding Needs Current Funding Total Yellow 0.55 M 0.4 M $150,000 Yellow 7.75 M 4.7M $3,130,000 Red 7.64 M 1.3M $6,260,000 Red 15.94 M $9,540,000 * Includes drainage funding - Addresses only current backlogs & priorities

  9. Environmental Program

  10. ENVIRONMENTAL PROGRAM Successes • Nationally Recognized Education Program • HRPDC – Partnering of Hampton Roads Cities for Environmental Education • Public BMP/Lake Inspections • Annual Reports to DEQ • Illicit Discharge Investigations – Partner with Fire Department • Organized City-wide Erosion & Sediment Control Inspections • Amended City Ordinance to Include Fines for Erosion & Sediment Control

  11. ENVIRONMENTAL PROGRAM Current Challenges & Needs

  12. ENVIRONMENTAL PROGRAM Future Challenges • DCR is Taking Over Management of Stormwater Permitting from DEQ • DCR is Pushing for Large Increases in Water Quality Monitoring & Reporting – $$$ ??? • City Currently Negotiating Renewal of its Stormwater Permit with DCR

  13. Maintenance & Service

  14. Maintenance & ServiceSuccesses • In Spite of Limited Resources More Effective • Equipment • Skills for Each Job • Emergency Response • Detailed Plans Developed for Known Choke Points • More Investigation Up Front to Eliminate Wasted Work Effort & Stop and Start • Better Defined Work Methods to Include Surveying • First Stage Repairs to Cave-ins • Use of In-mate Crews • Use of Project Levels to Sort Backlog

  15. Identified Needs - Maintenance

  16. Cave-Ins • Cave-Ins FY 04-05 • 1,088 Cave-In Repair Requests - 496 Repaired by City Crews (124/Crew/Year) - 125 Repaired by Contract ($621,000) 467Added to the existing backlog • Current Backlog over 1,000 Cave-Ins

  17. 2:1 4’ 4’ 2’ 4’ 4’ 4’ 4’ 2’ 18’ Excavation Requirements

  18. Cave-Ins • Best Approach • Less than 6’ Deep – In-House Crew Repair • Over 6’ Deep – Contract • Roughly 50/50 Deep vs. Shallow • Stepwise Approach • First Stage Repair • Letter to Resident • Follow up Repairs as Needed

  19. Capital Program

  20. Capital Projects • Funding has slipped from $2.6 million in 2001 to $1.3 million in 2006 • Construction cost increases have outpaced overall inflation rate (greater than 10%/yr) • Backlog of needed capital projects exceeds $76 million • These projects improve drainage for large number of residents

  21. Identified Annual Needs – Capital Program

  22. Other Items of Concern - Capital • Watershed Studies/Inventory - $250,000/year • 52 watersheds • Lake Maintenance - • 350 subdivision lakes • For most – owners responsible for maintenance • Cost for dredging very high • Past practice was to share cost • Regulatory issue – may become ours by default • Start saving now? – Consultant recommends $250,000/year

  23. Options

  24. Stormwater Fee Comparison FY-06/07 Per ERU / Month * Portsmouth scheduled for 50 cent per year increase. ** Norfolk scheduled for annual inflationary increase

  25. Fee Comparison

  26. Funding Per Mile of Pipe & Ditch FY06/07

  27. Consultant Report • Completed on November 10, 2006 • Identified Three Levels of Service (LOS) with Associated Fee Recommendations • Use 5 Year Average – FY 2008-2012 • Current LOS • Minimum Regulatory LOS – Recommended • Citizen’s Expectation LOS

  28. Consultant Report - Continued • Current Level of Service (LOS) • Avg Need: $5.5 million/year from the stormwater fee which equals $2.87/ERU/Month • With High for 2012 of $6.3 million or $3.19/ERU/Month • To Meet Minimum Regulatory Requirements – Recommended Level • Average need of $10.6M/year or $5.50/ERU/Month • With High for 2012 of $11.9M or $6.05 / ERU/Month • Citizens Expectation LOS • Average need of $13.9M or $7.22/ERU/Month • With High for 2012 of $16M or $8.10/ERU/Month

  29. Option 1

  30. Option 2

  31. Consultant Report – Minimum Regulatory

  32. Consultant Report – Citizen Expectations

  33. Comparison of Revenue $8.1 M $5.1 M $4.8 M $5 M $2.2 M $2.3 M $2.1 M Dollars (Millions) – Adjusted for Inflation

  34. Impact of Annual Fees

  35. Next Steps • Meet with Chamber & other stakeholders • Advertise public hearing – 2 weeks in a row before hearing • Hold non-planning public hearing @ City Council meeting • Council action same night • Revise billing information – January to March, 2007 • Bills mailed in April for CY-2007

  36. StormwaterCommittee ChairmanMr. Adam Jack

  37. Questions?

  38. BackupMaterial

  39. Impact on Funding Per Mile