80 likes | 224 Views
SPS 800 MHz RF Power upgrade. Progress report 18 June 2014. SPS 800 MHz power. All eight individual IOT transmitters validated Line #1 tested up to 200 kW CW on load New cavity controllers ready Still very bad news from Electrosys Second Circulator and no spare at all delivered. ?.
E N D
SPS 800 MHzRF Power upgrade LIU-SPS meeting, 18 June 2014 Progress report 18 June 2014
SPS 800 MHz power All eight individual IOT transmitters validated Line #1 tested up to200 kW CW on load New cavity controllers ready Still very bad news from Electrosys Second Circulator and no spare at all delivered ? Short Cavity #2 Load LIU-SPS meeting, 18 June 2014 Short Cavity #1 Load
SPS 800 MHz power Moved circulator toline #2 Line #2 tested up to200 kW CW on load Completed the RF conditioning up to180 kW CW on cavity #2 Yesterday Just started the RF conditioning on cavity #1 (without circulator ! So it will be slow as we will be very careful) ? Short Cavity #2 Load LIU-SPS meeting, 18 June 2014 Load Short Cavity #1 Load
Two x four transmitters Rear view LIU-SPS meeting, 18 June 2014 Front view
Cavities Antennas have been added on both cavities Combiner is still to be provided (LLRF) Two old filters are overheating (has probably been always the case, discovered while checking the antennas) We added a heat cooler New antenna design Sébastien adding a new antenna on all 74 cells LIU-SPS meeting, 18 June 2014
Cavities Antennas have been added on both cavities Combiner is still to be provided (LLRF) Two old filters are overheating (has probably been always the case, discovered while checking the antennas) We added a heat cooler LIU-SPS meeting, 18 June 2014 Old filter overheating while having 200 kW CW during several minutes (NOT the case in operation)
Schedule 2014 Dec Jan Feb May Mar Apr Jun Jul Aug SPS closed 8 Individual transmitters TWC 1 60 kW total TWC 2 60 kW total TWC 1 220 kW total LIU-SPS meeting, 18 June 2014 TWC 2 220 kW total TWC 1 & 2 2 x 220 kW total + Cavity conditioning LLRF antennae calibration LLRF commissioning SPS setup with beam