1 / 8

SPS 200 MHz RF Upgrade

SPS 200 MHz RF Upgrade. Eric Montesinos LIU-SPS coordination meeting 11 th September 2012. Amplifiers. Drivers (SSA): MS completed : 17 companies selected TS under writing, to be sent out October 2012 FC June 2013 Finals (SSA or Tetrodes ): MS completed : 7 companies selected

armani
Download Presentation

SPS 200 MHz RF Upgrade

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 11th September 2012

  2. Amplifiers Drivers (SSA): • MS completed : 17 companies selected • TS under writing, to be sent out October 2012 • FC June 2013 Finals (SSA or Tetrodes): • MS completed : 7 companies selected • TS (international), to be send out December 2012 • FC September 2013 Combiners (3 dB above 100 kW) • After Finals have been selected • MS + IT 2014 • FC 2014 Transmission lines (coaxial, 345 mm outer) • Same as Combiner From Beam Control 1/16 splitter Drivers 16 SSA Final 16 PAs 3 dB combiners and power loads 120 m and 180 m Coaxial lines To cavity input 120 m away LIU SPS RF

  3. July 2012 Amplifiers Schedule 2018 2017 2016 2013 2014 2015 September CERN approval for Series Production (after LD tests) Drivers September Design Report Review March Company selected March CERN AT October IT sent 30th June First Series FAT December Pre-series FAT December Last Series CERN AT December IT closed June FC Order placed IT : Invitation to Tenders FC : CERN Finance Committee FAT : Factory Acceptance Tests CERN AT : CERN Acceptance Tests LD Tests : Long duration tests : Long Technical Stop, No beams March CERN approval for Series Production (after LD tests) Finals December Design Report Review June Company selected June Pre-series FAT Decmeber IT sent December First Series FAT September CERN AT December Last Series CERN AT March IT closed September FC Order placed LIU SPS RF

  4. New BAF3 RF building • Building BAF3 : • Integration studies completed • Enquiry ‘Etude Genie Civil’ sent out • Results expected soon • Start construction mid-2013 • Building ready mid-2014 • Services ended by mid-2015 LIU SPS RF

  5. LSS3 rearrangement LS1 BPWA: 319 to 31101 AEWB: 319 To 31510 • During LS1: not a lot is possible • Only HBW Damper will be implemented • BPWA and AEWB new locations have been validated • (RF + optic + vacuum + cables + transport) • 4 ECR written • Not validated yet in PLAN (IMPACT) HBW kicker LIU SPS RF

  6. New Schedule 6 months cavities re-arrangement 2 months RF Power conditioning 4 months LLRF commissioning 2011 2012 2013 2014 2015 2016 2017 2018 2019 Studies Tendering Construction Installation LLRF Design and proto Commissioning Start up LLRF Tests LLRF Series New RF Power Amplifiers and LLRF Coaxial Lines Studies Construction Cavities pickups vacuumCV, EL LSS3 Tunnel Integration HBW (kicker and Pickup) Spare sections New power couplers Studies Authorizations Construction New RF Building Services Startup LIU SPS RF

  7. New Spending profile kCHF Red : initial profile Blue : New profile LIU SPS RF

More Related