Status Update: Retail Open Access for ETI within SPP. Stakeholder Meeting September 16 th , 2008 Austin, TX. Activities Completed Since Last Meeting. Met with ERCOT and confirmed that we can use existing processes and procedures Existing SCR 727 extract will provide necessary data
E N D
Status Update: Retail Open Access for ETI within SPP Stakeholder Meeting September 16th, 2008 Austin, TX
Activities Completed Since Last Meeting • Met with ERCOT and confirmed that we can use existing processes and procedures • Existing SCR 727 extract will provide necessary data • Received estimated software costs to aggregate ERCOT retail data and make ready for SPP Settlement systems • Began development of final estimated costs for implementation (system changes, labor, and staffing)
ROA Implementation Cost Estimates * Includes ERCOT Phase II costs Appendix 9 and estimated one time internal ERCOT development work.
Annual ROA Maintenance Cost Estimates * Staffing rates are based on the 2009 CBTF rates