150 likes | 300 Views
Progress and Status. Performing Arts Complex. Progression . Theatre Stage. 4.18.2013 Stage has been blacked-out North Rigging Wall is complete Rigging at the gridiron level is near completion. 5.16.2013 Fire curtain installed North Rigging Wall is complete
E N D
Progress and Status Performing Arts Complex
Theatre Stage 4.18.2013 Stage has been blacked-out North Rigging Wall is complete Rigging at the gridiron level is near completion 5.16.2013 Fire curtain installed North Rigging Wall is complete Rigging at the gridiron level is complete AV cable installation
Theatre Seating Area 4.18.2013 Theater scaffold is currently being disassembled CFMF to start at the balcony level in the house 5.16.2013 Theater level framing and drywall nearly complete Balcony level walls and ceilings framed Mep rough in ongoing
Recital Hall Seating Area 4.18.2013 Ceiling MEP rough-in Installing drywall at ceilings Completed seating layout and pre-drilled seat anchors 5.16.2013 Sound light room drywall installed Zig zag walls at the stage are complete Mep rough in complete
Mechanical Room - 316 4.18.2013 Air Handlers are operational Conditioned air milestones have been met Cleaning area in preparation for installation of traffic coating 5.16.2013 Air Handlers are operational Traffic coating installed Light fixtures installed Mechanical complete
Recital Hall Lobby 4.18.2013 Framing East soffits Installing Duct Taps 5.16.2013 Ceiling framing installed Mep above ceiling complete Radius wall completed at recital hall entrances
Theatre Lobby 4.18.2013 Install Drywall at feature cone wall Drywall at the plinth level lobby ceiling Installing framing at Theatre level Lobby Ceiling Brick columns ongoing at plinth lobby 5.16.2013 Install Drywall at feature cone wall Tape & bed radius wall Mep rough in complete Terrazzo installed and first grind complete Elevator installation ongoing
Women’s Restroom - 109 4.18.2013 Walls and ceilings have been painted floor grinding 5.16.2013 custom Italian tile installed Mep trim out ongoing
Southeast Elevation 4.18.2013 Face brick and cast nearly complete at Southeast tower Face brick has started at the elevator tower Preparing Pavilion for steel erection 5.16.2013 Face brick and cast stone complete at Southeast tower Face brick nearly complete at the elevator tower Pavilion steel erected and framing ongoing Plaster soffit at high entry scratch coated
Northeast Elevation 4.18.2013 Face brick at northeast tower completed and washed Face brick nearly complete at the entry columns 5.16.2013 Tile at north and south towers ongoing Entry brick complete Sealants nearly complete at face brick
Northwest Elevation 4.18.2013 Face brick and cast stone nearly complete at North arcade 5.16.2013 Face brick and cast stone nearly complete at North arcade Plaster at the mansard roof nearly complete Grading for walkways complete
Southwest Elevation 4.18.13 Landscaping Main has been installed Outriggers to be installed Rough grading to begin 5.16.13 Grading complete Ribbon curb for pavers ongoing Canopies are complete
College of Education 4.18.2013 Forming and pouring walk ways Installing face brick and Cast stone 5.16.2013 Concrete and pavers complete Cast stone nearly complete Back fill at planters installed Irrigation installed
Utility Corridor 4.18.2013 Poured entry Continuing face brick and cast stone 5.16.2013 Brick and cast stone complete Irrigation installed River rock installed Light poles complete