Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project. EXIT 5. AUGUSTA METRO AREA. EXIT 5. NORTH AUGUSTA. AUGUSTA. Park & Ride Site. EXIT 5. Palmetto Parkway. October 2009. Issues. Air quality Demand SCDOT to design and construct City to maintain
E N D
Georgia Association of MPOsNovember 29, 2012 North Augusta Park and Ride Project
EXIT 5 AUGUSTA METRO AREA
EXIT 5 NORTH AUGUSTA AUGUSTA
Park & Ride Site EXIT 5 Palmetto Parkway
Issues • Air quality • Demand • SCDOT to design and construct • City to maintain • Sustainable Design: stormwater, energy, landscaping • Security • Image • Maintenance cost
Main JANUARY 2010
Chronology • August 2009 Project conceived • October 2009 User meeting held • January 2010 Sketch design complete • June 2010 ARTS funding approved • January 2011 Design contract advertised • April 2011 URS selected for design • October 2011 URS design contract approved • October 2012 Preliminary plans at 95%
Cost Estimates • January 2010 $ 800,000 • June 2010 $ 1,000,000 • October 2012 $ 1,473,305