1 / 39

Rate Impact Task Force: Updated Results for SPP Regional State Committee Report

This report presents the updated results of the Rate Impact Task Force's assessment on the rate impact of transmission investments on retail residential and small commercial ratepayers. The report includes cost allocation rules, annual transmission revenue requirements forecast, quantifiable benefits, and graphical outputs of the incremental costs and benefits.

Download Presentation

Rate Impact Task Force: Updated Results for SPP Regional State Committee Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Rate Impact Task Force’s Updated Resultsfor it’s Report to the SPP Regional State Committee January 24, 2011

  2. General Rate Impact Task Force (RITF) Notes • RITF was formed in May, 2010 by the SPP Regional State Committee to develop monthly rate impact of transmission investment on retail residential and small commercial ratepayers • Transmission investments costs were allocated to Transmission Owning Zones by the following Cost Allocation rules: • Traditional Base Plan Funding for Notifications to Construct (NTC) issued before June 19, 2010 • 33% Regional using Load Ratio Share (LRS) + 67% Zonal assignment using Mega Watt-Mile beneficiary metric • Highway Byway Funding for NTCs issued on or after June 19, 2010: • over 300kV using 100% LRS • between 100kV and 300kV using 33% Regional LRS + 67% Zonal direct assignment • under 100kV directly assigned to host Zone 2

  3. General RITF Notes, cont. • Using the Cost Allocation Rules described in the previous slide, an Annual Transmission Revenue Requirements (ATRR) Forecast was developed for each Transmission Owning Zone including: • Accumulated Depreciation, Balanced Portfolio Balancing Transfers, and Construction Work In Progress for Upgrades Novated to Transcos • Incremental ATRR costs are offset by select “quantifiable” benefits of Balanced Portfolio and Priority Projects • Incremental ATRR costs and offsetting benefits were further allocated to Retail Residential and Small Commercial ratepayers by the Transmission Owners reducing ATRR and offsetting benefits to a $ / month level • Net Results presented as 2017 monthly incremental effect

  4. RITF Inputs • Annual Transmission Revenue Requirement Cost Forecast relies on Transmission Owner’s: • Upgrade Level Cost Estimates • Net Plant Carrying Charge % (NPCC), used to Annualize Upgrade Costs • Upgrade’s In-service Date • 3% Annual Straight-Line Depreciation to Rate Base • As used in this presentation, Reliability and Economic Upgrades are terms of “art”. This is not to say that Economic Projects do not provide Reliability benefits or vice-versa. • Select “Quantifiable” Benefits from Economic Upgrades offset costs • Balanced Portfolio: Adjusted Production Costs (APC) + Reliability • Priority Projects: APC + Reliability + Reduction in Losses • Gas Price Impact not included • Benefits of Reliability Upgrades, Transmission Service Upgrades, and Generation Interconnection Upgrades were not included • 11 GW of wind assumption used, Wind Revenue Impact was not included • Positive Benefit Reduces Costs, Negative Benefit Increases Costs

  5. Updates to ATRR Forecast • Annual Transmission Revenue Requirements (ATRR) Zonal Cost Forecast Updated in December 2010: • New Cost Estimates for Economic Upgrades: • Priority Projects (PP) increased from $1.15B to $1.42B • Balanced Portfolio (BP) increased from $692M to $826M • Updated In-Service Dates for PP, from “all-in” in 2015 to individually estimated in-service dates of 2011, 2014, and 2017 • Re-calculated BP Transfers from $31.2M/yr to $64M/yr , as required to ensure all Zone’s Benefit/Cost ratios are at least 1.0 for BP Upgrades • Costs Updated in Each Zone’s ATRR Forecast Results • New Graphical Output: Monthly Incremental Cost Results Split Between Reliability and Economic Upgrades

  6. Differential ATRR of Cost Estimate Updates for Balanced Portfolio and Priority Projects

  7. Differential ATRR of Cost Estimate Updates for Balanced Portfolio and Priority Projects

  8. Incremental Upgrades used in ATRR forecasting

  9. RITF Results Four Types of Customers Considered: • 1,000 kWh/mo residential • 4,000 kWh/mo small commercial • Actual average residential • Actual average small commercial • Focus on 2017 Test Year, Incremental Cost Peak Year • Monthly Net Impact in Addition to Current Typical Bill

  10. Detailed Results by Type • For Each Customer Type Graphs are Presented: • Monthly Cost Incremental to Current Bill (Red Bar) • Monthly Benefits Offsetting Costs (Green Bar) • Green bar below the zero line reduces net monthly costs • Green bar above the zero line increases net monthly costs • Monthly Net Impact Incremental to Current Bill (Orange Bar with $/Month Values) 11

  11. Summary RITF 2017 Results, 1,000 kWh/mo Incremental Residential Costs green benefits bar below the zero line reduces net costs, above the zero line increases net costs 13

  12. Summary RITF Results, 4,000 kWh/mo Incremental Small Commercial Costs green benefits bar below the zero line reduces net costs, above the zero line increases net costs

  13. Summary RITF 2017 Results, Incremental Actual Average Residential Costs green benefits bar below the zero line reduces net costs, above the zero line increases net costs 17

  14. 18

  15. Summary RITF Results, Incremental Actual Average Small Commercial Costs green benefits bar below the zero line reduces net costs, above the zero line increases net costs 19

  16. Investment Splits by Type

  17. ATRR Cost Split Between Reliability, TSR, GI and Economic Upgrades • 2017 Total Incremental ATRR: $822M/yr • 2017 Reliability, Transmission Service, Generation Interconnection, and Sponsored Upgrades ATRR: $453M/yr; 55% of total • 2017 Economic Upgrades ATRR, Balanced Portfolio, Priority Projects: $369M/yr; 45% of total

  18. 2017 Cost Results, 1,000 kWh/mo Residential (not offset by Benefits)

  19. 2017 Cost Results, 4,000 kWh/mo Small Commercial (not offset by Benefits) 23

  20. 2017 Cost Results, Average Residential (not offset by Benefits)

  21. 2017 Cost Results, Average Small Commercial (not offset by Benefits)

  22. CWIP vs. AFUDC • Select projects have approval from FERC to recover Construction Work In Progress (CWIP) before an individual upgrade is placed in-service. • The following slides explore the difference between CWIP and traditional Allowance for Funds Used During Construction (AFUDC) to the Ratepayer. • AFUDC is treated as a capital investment and is added to the Rate Base of an Upgrade when it is placed in rates. There is no recovery of AFUDC before the facility is placed in rates. • For the preceding slides, CWIP is included in the cost forecast but did not effect the 2017 results because the last project eligible for CWIP is completed in 2014.

  23. CWIP vs. AFUDC, cont. • The Present Value (PV) of the ATRR stream of the Novated Balanced Portfolio (KETA Plan) projects and Priority Projects (V Plan) were compared when construction was hypothetically financed with AFUDC verse CWIP. • A discount rate of 6% was chosen as representative of a consumers costs of funds (i.e. mortgage). This rate is higher than inflation and lower than a utility’s long term cost of capital. • Higher discount rate favors the use of AFUDC • Lower discount rate favors the use of CWIP

  24. Novated Economic Upgrades

  25. CWIP Estimates for Novated Econ. Upgrades 29

  26. ITC’s Hypothetical AFUDC Calculations 30

  27. Prairie Wind Present Value of Discounted Cash Flows: AFUDC v. CWIP, Priority Projects Difference = Present Value (PV) of AFUDC scenario less PV of CWIP scenario, therefore positive value is a CWIP savings to the Ratepayer. Discount Rate of 6% chosen as higher than inflation, lower than corp. cost of capital. CWIP v. AFUDC break even at a discount rate of 6% occurs in 2034, 19 years after the in-service date.

  28. ATRR for Priority Projects Novated to Prairie Wind, AFUDC vs. CWIP Total AFUDC added to Upgrade: $28.1M

  29. ITC Present Value of Discounted Cash Flows: AFUDC v. CWIP, Balanced Portfolio’s KETA Plan Difference = PV of AFUDC scenario less PV of CWIP scenario, therefore positive value is a CWIP net savings to the Ratepayer. 6% Discount Rate chosen as higher than inflation and lower than corp. cost of capital. CWIP v. AFUDC break even at a discount rate of 6% occurs in 2027, 14 years after the in-service date.

  30. ITC Great Plains, Balanced Portfolio’s KETA Project, AFUDC v. CWIP

  31. ITC Present Value of Discounted Cash Flows: AFUDC v. CWIP, Priority Project’s V-Plan Difference = PV of AFUDC scenario less PV of CWIP scenario, therefore positive value is a CWIP net savings to the Ratepayer. Discount Rate of 6% chosen as higher than inflation and lower than corp. cost of capital. CWIP v. AFUDC break even at discount rate of 6% occurs in 2028, 14 years after the in-service date.

  32. ITC Great Plains, Priority Project’s V Plan, AFUDC v. CWIP

  33. CWIP Cost Allocation per Year, 2009-2014

  34. RITF Roster Barry Smitherman - (Chairman) Michael Siedschlag - (Member) Thomas Wright - (Member) Larry Altenbaumer - (Member) Ricky Bittle - (Member) Mike Palmer - (Member) Les Dillahunty - (Staff Secretary) 38

  35. Pat Bourne Director Transmission Policy pbourne@spp.org 501-614-3249 Dan Jones, PE Lead Regulatory Policy Engineer djones@spp.org 501-688-1717 Dee Edmondson Engineer I dedmondson@spp.org 501-688-1778 39

More Related