HiRadMat : report from WG2&3 – WANF dismantling. Agenda. Worksite: activities achieved or in progress WANF cleaning: status Proposal for next weeks AOC or work notification ?. Worksite : activities in progress (W1&2).
E N D
HiRadMat: report from WG2&3 – WANF dismantling Agenda S. Evrard • Worksite: activities achieved or in progress • WANF cleaning: status • Proposal for next weeks • AOC or work notification ?
Worksite : activities in progress (W1&2) S. Evrard B846 access control 2/3 completed (cabling and new grid door OK, PLC upgrade in week 3) Furetdismantled RIA installed, hoses box to be fixed TT61 cleaned, shielding blocks (TCX) ready for installation TNC re-lighting done
WANF cleaning S. Evrard • Work procedure and dose estimate received and validated with DG/SCR • Team of 4 tech. @ Cern today: paper work and VIC achieved • Cleaning in W3
Proposal for 4-5-6 T1 dismantling January 15, 2010 S. Evrard Remove as much as possible during monthly LHC technical stops (outlined area). MTR’s and T1 target during LHC shutdown (need to remove TI2 line investigation in progress
Proposal for W4 Survey network points January 15, 2010 S. Evrard 8 drilling operations to be carried out by GS/SEM
Proposal for 4-5-6 Removal of old AHU in TA7 January 15, 2010 S. Evrard Could be achieved on CV small works contractor
Proposal for 4-5-6 Removal of beam line equipment from TNC January 15, 2010 S. Evrard 2 magnets Beam instrumentation
Proposal for 4-5-6 Other activities January 15, 2010 S. Evrard Redtelephone in TNC (F. Schmitt) Pas de câble de ce type en stock au CERN, un mois nécessaire pour approvisionner, F. Schmitt fera propositions palliatives lors de la réunion (tél. normal en TNC ?). Fire detectionremoval in TNC. (D. Raffourt) Crane crémaillère check (A. Calderone)