120 likes | 251 Views
SX5, PX56, and UXC55 Day-to-day Installation Schedule. Monday 5 th September 2005. Gesco: Install CV room (PR758, 5h/day). Bouchon Closed all week from PM COSMI: Reinstall platform AM shift. COSMI: Modify barriers on sides of PR760 rails GESCO: Install vertical ventilation ducts on RB54.
E N D
SX5, PX56, and UXC55 Day-to-day Installation Schedule martin.gastal@cern.ch
Monday 5th September 2005 Gesco: Install CV room (PR758, 5h/day) Bouchon Closed all week from PM COSMI: Reinstall platform AM shift COSMI: Modify barriers on sides of PR760 rails GESCO: Install vertical ventilation ducts on RB54 martin.gastal@cern.ch
Tuesday 6th September 2005 Gesco: Install CV room (PR758, 5h/day) Amec-Spie: Install ventilation electrical parts Hadrelec: Install LV cables Bouchon Closed all week COSMI: Modify barriers on sides of PR760 rails GESCO: Install vertical ventilation ducts on RB54 martin.gastal@cern.ch
Wednesday 7th September 2005 Gesco: Install CV room (PR758, 5h/day) Amec-Spie: Install ventilation electrical parts Hadrelec: Install LV cables Bouchon Closed all week COSMI: Modify barriers on sides of PR760 rails GESCO: Install vertical ventilation ducts on RB54 martin.gastal@cern.ch
Thursday 8th September 2005 (Bank Holiday?) Gesco: Install CV room (PR758, 5h/day) Amec-Spie: Install ventilation electrical parts Cegelec: Maintain PR758 Bouchon Closed all week COSMI: Modify barriers on sides of PR760 rails GESCO: Install vertical ventilation ducts on RB54 martin.gastal@cern.ch
Friday 9th September 2005 Gesco: Install CV room (PR758, 5h/day) Amec-Spie: Install ventilation electrical parts Cegelec: Maintain PR759 Bouchon Closed all week COSMI: Modify barriers on sides of PR760 rails GESCO: Install vertical ventilation ducts on RB54 martin.gastal@cern.ch
Saturday 10th September 2005 Bouchon Closed martin.gastal@cern.ch
Monday 12th September 2005 Gesco: Install CV room DBS: Open Plug till 9:00am Bouchon Open all week GESCO: Install remaining ducts from 9:00am on GESCO: Install vertical ventilation ducts on RB54 MADA: Install net under crane rails +Z martin.gastal@cern.ch
Tuesday 13th September 2005 Gesco: Install CV room Bouchon Open all week GESCO: Install remaining ducts GESCO: Install vertical ventilation ducts on RB54 MADA: Install net under crane rails +Z martin.gastal@cern.ch
Wednesday 14th September 2005 Gesco: Install CV room Bouchon Open all week GESCO: Install remaining ducts GESCO: Install vertical ventilation ducts on RB54 PH-CMI: Lower platform on overhead crane 6:00am + lower 1900kg load DBS: Close Plug PM shift martin.gastal@cern.ch
Thursday 15th September 2005 Gesco: Install CV room Hadrelec: Install LV cabling Securiton: Install fire detection system Bouchon Closed GESCO: Install vertical ventilation ducts on RB54 Veritas: Control Installation of platform martin.gastal@cern.ch
Friday 16th September 2005 Gesco: Install CV room Hadrelec: Install LV cabling AMEC-SPIE: Install ventilation electrical parts Bouchon Closed GESCO: Install vertical ventilation ducts on RB54 Veritas: Control Installation of platform DBS: Open Plug PM shift martin.gastal@cern.ch