1 / 49

New Nuclear Plant Deployment

New Nuclear Plant Deployment. Gary Fader Director, New Plant Deployment Institute of Nuclear Power Operations. INPO - Our Roots. March 28, 1979 Three Mile Island – a catalyst for industry improvement INPO’s unique role Self-regulation through peer review.

mary-arnold
Download Presentation

New Nuclear Plant Deployment

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. New Nuclear Plant Deployment Gary Fader Director, New Plant Deployment Institute of Nuclear Power Operations

  2. INPO - Our Roots • March 28, 1979 • Three Mile Island – a catalyst for industry improvement • INPO’s unique role • Self-regulation through peer review

  3. President’s Commission on the Accident at Three Mile Island • Set and police standards of excellence • Systematic gathering and analysis of operating experience • Accredited training • Operator training and plant simulators

  4. ’s Mission To promote the highest levels of safety and reliability- to promote excellence -in the operation of nuclear electric generating plants

  5. Our Workforce 2008 • 325 Permanent • 65 On Loan • 10 On Reverse Loan • Budget ~ $90 million

  6. Institute of Nuclear Power Operations National Academy for Nuclear Training World Association of Nuclear Operators

  7. Cornerstone Programs Analysis & Information Exchange Training & Accreditation Evaluations Assistance

  8. Other Activities New Plant Development • Worldwide benchmarking International Program • Information exchange • Technical support Supplier Participant Program • Vendor advice • Industry issues (continued)

  9. Members and Participants Members International Participants (14) Brazil Canada France Japan South Korea Mexico Belgium Romania South Africa Spain Taiwan United Kingdom Slovak Republic Slovenia Supplier Participants (17) 27 U.S. Utility Members who operate nuclear power plants and 38 Utility Associate Member co-owners AREVA Bechtel Black & Veatch Day & Zimmermann General Electric Hitachi Honeywell Louisiana Energy Services Mitsubishi Nuclear Fuel Services PBMR Sargent & Lundy Scientech The Shaw Group Toshiba Washington Group Westinghouse

  10. WANO Organization Coordinating Center Regional Centers Moscow London Atlanta Tokyo Paris

  11. Why Nuclear, Why Now? • Energy needs • Energy independence • Environmental considerations • Safety & efficiency • Licensing confidence • Federal financial incentives

  12. Nuclear Fuel Cycle

  13. Nuclear Fuel • Uranium primarily mined in: • Canada, Australia, Kazakhstan, Russia, Niger, Namibia, others • Conversion to UF6 • US, Canada, France, UK, Russia, others • Enrichment • France, Germany, Netherlands, UK, US, Russia, others

  14. What Happens to Used Nuclear Fuel in the US? • NRC requires contract with DOE for spent fuel removal • Currently, ~ 75,000 metric tons is stored at over 100 nuclear power plants in pools or casks. • DOE plans to store/bury used fuel at Yucca Mountain in Nevada - $13.5 B spent • Cost of storage • All nuclear electricity is taxed at 0.1¢/kW-hr for a disposal fund, which will pay for storage (~$500 million/year, >$22 B not spent)

  15. International • Countries that reprocess spent fuel: • France, UK, Russia, Japan • 1% each Uranium and Plutonium (MOX) recovered • 1/5 original volume for disposal • Remaining waste vitrified, stored

  16. Current Situation in U.S. • Funding reduced for Yucca Mt. • What’s needed: • Interim centralized storage • Technology & business case for reprocessing • Licensing of permanent disposal site • Bipartisan commission proposed to reassess program

  17. Environmental: Nu Clear “Nuclear power produces 70% of US carbon-free electricity” (Steven Chu at Senate confirmation hearing)

  18. Significant Events • Significant events meet one or more of the following criteria: • Degradation of important safety equipment • A major transient or unexpected plant response • Degradation of fuel integrity, primary coolant pressure boundary, or important associated structures • A reactor trip with complications • An unplanned release of radioactivity exceeding the technical specifications or regulations • Operation outside the technical specification limits • Other events considered significant

  19. Unit Capability Factor

  20. Unplanned Capability Loss Percent

  21. 10 CFR 52Combined Licenses, Early Site Permits, and Standard Design Certifications Verification of Inspection, Tests, Analyses, and Acceptance Criteria Reactor Construction Early Site Permit* Standard DesignCertification* Combined LicenseReview and Hearing Reactor Operation

  22. Timelines • Design certification • 2-4 years to prepare • 30-48+ months for NRC review • 12 months for rulemaking • Early Site Permit • 12-18 months to prepare • 21 month NRC review • 12 months for hearing • Combined license • 12-24 months to prepare • 42 month NRC review, assuming DC & ESP are referenced • 12 months for hearings

  23. Energy Policy Act Incentives • Standby Support Coverage for delays beyond owner’s control • $500 million for first two plants, • $250 million for next four after a 180 day period • Production Tax Credits • $18/MWh for 6,000 MW caped at $125 million for a 1,000 MW plant • Loan Guarantees • Low emission generation up to 80% of total project cost • 80/20 Debt-equity structure, with debt underwritten by Federal government

  24. Current Statistics • Early site permits: • 3 issued, 1 under review • Design Certifications • 2 issued • 4 under review (AP-1000 amendment) • COL applications: • 17 submitted (26 units) • 23 total expected (34units)

  25. More Statistics • Long-lead equipment orders: • 9 utilities ordered large forgings • 6 steel containment shells AP-1000 • 24 Rx coolant pumps AP-1000 • EPC Contracts: • 4 in place • 1 firm commitment to construct • Financial incentives: • Loan guarantees: 15 applications ($93B vs. $18.5B allocated) • 5 eligible per DOE

  26. More Statistics • Spent fuel disposal • 19 contracts with DOE • Fuel removal starts 20 years from 1st refueling • Removal complete 10 years after shutdown • $5M/yr penalty

  27. More Statistics - Global • NPPs actively under construction: • China (10), India (6), Russia (4), Japan (2), France (1), South Korea (8), Taiwan (2), U.S. (1) • 106 on order/planned in 24 countries • 200 under consideration in 37 countries

  28. Flamanville 3 - France

  29. Flamanville 3 – Reactor Containment

  30. Shin-Kori 1 & 2– South Korea

  31. Advanced Plant Designs • Currently under consideration: • GE Advanced BWR (Certified May 97) • Westinghouse AP-1000 PWR (Certified Jan 06) • GE Economic Simplified BWR (Applic. Aug 05) • AREVA Evolutionary PWR (Applic. Fall 07) • Mitsubishi US Advanced PWR (Applic. Mar 2008) • Others: • Westinghouse (CE) System 80+ (Certified May 97) • Pebble Bed Modular Reactor • Westinghouse AP-600 (Certified Dec 99)

  32. General Design Features • GE Advanced Boiling Water Reactor (vessel internal recirculation pumps, 3 trains active safety systems, 1350 MWe), 4 units operating & 1 under construction in Japan, 2 units under construction in Taiwan • Westinghouse AP-1000 (conventional primary & secondary PWR systems, passive safety systems, 1100 MWe), 4 units under construction in China

  33. General Design Features • GE Economic Simplified BWR (natural circulation main coolant system, passive safety systems, 1500 MWe) • AREVA Evolutionary PWR (conventional primary & secondary systems, 4 trains active safety systems, 1600 MWe), under construction in Finland, France China (2)

  34. General Design Features • Mitsubishi US Advanced PWR (conventional primary & secondary systems, 4 trains active safety systems, advanced accumulator design,1700 MWe), similar plant in licensing in Japan

  35. Control Rooms • All plants use digital instrumentation & controls for control and protection • Some emergency safeguards actions backed up by hard-wired controls • All control rooms use flat-panel screens for operator interface, with large screen displays • Most plants have automated startup & shutdown

  36. Current U.S. Control Room

  37. Lungmen Simulator

  38. Tomari 3 Simulator

  39. Westinghouse Simulator

  40. INPO Activities Provide Info & Experience • Operating experience to influence design • Past US construction experience • International benchmarking for new plant deployment • Construction experience exchange process

  41. INPO Activities Training and Accreditation • Training guidelines • Process for Initial Accreditation of Training in the Nuclear Power Industry

  42. Current INPO Activities • Assistance • Visits to suppliers • Design control / quality program • Engineering human performance • Corrective action • Use of operating experience • Equipment reliability process • Configuration management process • Industry meetings to share construction lessons learned

  43. Current INPO Activities Cont’d • Conduct on-site visits to Watts Bar 2 • Review, Assistance • Revise plant review guidelines • Conduct construction site visits (later) • Quality program implementation • Operational programs development and implementation • Operational readiness

  44. Key Construction Lessons • COL holder organization is in place and integrated with the engineering, procurement, & construction contractor • COL holder oversight (COL holder’s managers continually assess contractor work) • QA organizations in place ( procedures, qualified staff), and workers understand the need for quality construction

  45. Key Construction Lessons • Adequate construction staffing (project managers, QA/QC inspectors, welders, electricians) • Maintaining standardization • Design essentially complete before construction and construction in compliance with design

  46. Questions?

More Related