1 / 10

Brief summary of Run #3 (29 July) and #4 (3-6 August)

Brief summary of Run #3 (29 July) and #4 (3-6 August). Shinji Machida o n behalf of the beam commissioning team ASTeC /STFC/RAL 9 August 2010. Injection orbit into septum. Established a way to measure ( x , x ’) at the entrance of septum.

Download Presentation

Brief summary of Run #3 (29 July) and #4 (3-6 August)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Brief summary ofRun #3 (29 July) and #4 (3-6 August) Shinji Machida on behalf of the beam commissioning team ASTeC/STFC/RAL 9 August 2010

  2. Injection orbit into septum • Established a way to measure (x, x’) at the entrance of septum. • Position at the last two quadrupole in the injection line (Q17, Q18) is within ~1 mm in horizontal, that is within error bar. • In vertical, a few mm depending on tuning upstream. • In vertical, steering before the septum (V-06) is adjusted to increase a beam in the ring.

  3. Septum mapping (1) • (x, x’) as a function of strength is reproduced. It is consistent with July data, although June data looks different. (x, x’) at entrance might be different in June. • For example, x’ vs septum setting below, • S1: 22 June • S2: 3 Aug • S3: 14 July • S4: ignore.

  4. Septum mapping (2) • (x, x’) at the exit of septum is not as designed. • Change of strength and rotation is not enough to get (x, x’) by Stephan or Scott. • Instead, David calculated kicker strength assuming (x, x’) given.

  5. Kicker calibration • Polarity of kicker 1 and 2 is determined. K1 kicks outward and K2 kicks inward. • Calibration between kicker setting voltage and CT current is measured.

  6. A beam in four sector • A beam went back through 4 sector with more reasonable settings. • QD/QF = 260/220 A, which should give 18.5 MeV/c equivalent beam. • Nominal kicker 1 and almost zero kicker 2, which is consistent with David’s calculation.

  7. Tune measurement • With nominal setting of QD/QF=260/220A, horizontal tune is 0.15-0.18, which is close to the design value 0.177 (hardedge) at 18.5 MeV/c. • Tune with +/-5%, 10% setting was not accurate. Later found out that continuous beam loss within 4 sector happened.

  8. Optics matching • Found that beam loss in the 4 sector can be reduced with the last 4 quadrupole setting in the injection line (Q15, 16, 17, 18). • Meaning that need better optics matching. • Both Yuri’s empirical setting and Jaroslaw’s calculation with MAD-X reduced beam loss.

  9. Time of flight • Measured BPM signal of E07-EBPM-01 and E23-EBPM-01 directly. • Signal is much lower than BPM in ALICE, which is strip line type. EMMA’s one is button. • With the scope we used, which is 10 GS (100 ps sampling), difficult to see change of ToF with various lattice setting. • 5 ps (max) per cell x 16 cell = 80 ps.

  10. Final remarks • “One” of EPICS BPM card seems working now. However, BPM data taking still relies on 7 cables, which gives 7 BPM planes (H or V). • Difficulty to expand momentum range seems mainly due to different (x, x’) from septum. • Overall, however, we understand EMMA much more in details. • Actual data is stored on http://www.astec.ac.uk/emmafiles/analysis/

More Related