80 likes | 184 Views
Abbreviated list of April Global Run (AGR) achievements. A lot of new equipment successfully participated in this AGR. All: clock frequency scan ECAL/RCT/L1: test (28 of 500) new oSLB oRM links Strips: r un with all FEDs & calibration constants at 15°C
E N D
Abbreviated list of April Global Run (AGR) achievements A lot of new equipment successfully participated in this AGR • All: clock frequency scan • ECAL/RCT/L1: test (28 of 500) new oSLBoRMlinks • Strips: run with all FEDs & calibration constants at 15°C • HCAL: Commission new HO SiPMswith self- and DT-triggers in bottom-only and top-only configurations • DT: Commission relocated sector collectors • RPC: First global run with new RE4 chambers • CSC: First global run with new ME4/2 chambers • PPD: First run with Prompt Calibration Loop on cosmics G. Rakness (UCLA)
Some issues encountered (1/2) • Communication is hard… • Shift crew DOCs • Actions performed without telling the experts • DOCs talk directly to DAQ, DCS or Trigger shifter (skip Shift Leader) • Shift crew shift crew • DCS shifter not always aware what should be on • DAQ/DCS shifter had parts of detectors in run but powered off • DOCs DOCs • Trigger key did not always match the detector state/key • Management Shift crew/DOCs • Actions performed without telling Run Field Managers • DTs removed from an overnight run • RC did not inform Tier-0 that run was continuing over the weekend G. Rakness (UCLA)
Some issues encountered (2/2) • New hardware needs commissioning… • Shifters were busy overnights to keep runs going • Why did we keep going out of sync? • Timing between control signals need tuning since FPGAs on new CSCs need longer time to load (bigger) • Spikes in upper trigger sectors which had not been run since collisions • Old problems show up (and fixed) again… • Cables unplugged at Global Trigger • L1MuOpen triggers not included in Express Stream • miniDAQ data with bad menu caused crashes at Tier-0 G. Rakness (UCLA)
Power/cooling/elevator • Sunday evening: power cut affected the cooling at p5 • Although water was still flowing, it was no longer being cooled… and eventually initiated temperature alarms/automatic switch-off for several subsystems... • An elogwhich sort of describes what happened can be found at http://cmsonline.cern.ch/cms-elog/816435 • Discovered that technical incidents are kept track of in TECOPA, not elog… see page 12 of https://twiki.cern.ch/twiki/pub/CMS/AprilGlobalRun2014/TECOPA_slides_20140411.pdf • Elevator going underground cavern stopped… twice... • Wed: relay that tells door where it is w.r.t. opening broke • Thu: piece guiding the door fell out G. Rakness (UCLA)
Action items • Make communication the procedure in the control room • Between & within shift crews, DOCs, and management • Follow up issue with gas • On both CERN gas group side and RPC side… • Test out every new thing which is installed, even if it doesn't give good cosmic rays • E.g., DT links on top-half and calorimeter trigger • Make sure monitoring paths have what we need • E.g., muons in cosmic rays, single objects w/beam • Why do we keep going out of sync? • These are not difficult data taking conditions… G. Rakness (UCLA)
2014 Mid-Week Global Run (MWGR) schedule https://twiki.cern.ch/twiki/bin/view/CMS/CentralShifts2014#Global_run_planning Intend to officially announce the dates for the MWGRs soon G. Rakness (UCLA)
Regarding worries about Trigger and Clock Distribution System (TCDS) • Summary of concerns from subsystems about TCDS… • Upgrade not as transparent as they were led to believe (some work involved) • The time schedule is late (installation in August) • It’s not going to work out of the box (little expertise left in subsystems to commission) • https://indico.cern.ch/event/310364/ • Have discussed w/TCDS & HCAL, and will sit in when they interface at 904 to get a sense of what it takes G. Rakness (UCLA)
To do • Sort out what is happening with shift administration • Andrea won’t be extended past October… Tiziano has someone in mind to replace him but Austin doesn’t think that is a good job for him (I agree with Austin) • Work out LHC/CMS handshake schedule • Technical Coordination, BRIL, … • My items from RC to-do list • Clean up sources to "action list" from the meetings • Make sure that HF is fine as min-bias trigger for low lumi • Come up with best guess-timates for integrated and instantaneous luminosity during LHC startup • Monitor TCDS developments/scheduling • Follow up problems w/ECAL laser calibration data xferto Tier-0 • Follow up SCAL FED G. Rakness (UCLA)