Phase 1.1 and 1.2 Construction Updates and Closures

Get the latest updates on Phase 1.1 and 1.2 construction activities, punchlist items, closures, and design status. Stay informed about the progress of the project.

mauricek
Download Presentation

Phase 1.1 and 1.2 Construction Updates and Closures

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. August 9, 2018

  2. Updates • Phase 1.1 • Punchlist items • Arsenal Pump Station • Santa Rosa Pedestrian Crossing • Phase 1.2 • Design Status • Construction Activities • Calder Alley Archaeological Mitigation • Commerce Street Closure

  3. Phase 1.1 Update • SDJV working to complete punchlist items by August 31 • Additional rails • Inlet lighting • Terrazzo bench installation completed • Arsenal Pump Station Completion week of August 6

  4. Phase 1.2 Construction Update • Early Work Package 11: Demolition and Utility relocation • Utility relocation work ongoing • Commerce Street gas, electric, water, wastewater • Calder Alley archeological mitigation has begun • Approximately 2 week duration

  5. Phase 1.2 Construction Update • Early Work Package 12: Heavy Civil Construction • Drilled pier construction • Former Dollar General site • Penners parking area • Houston lot

  6. Commerce Street Closure • Full closure began June 25 • 3-month duration • One lane open beginning late September • 13-month duration • South half of bridge has been demolished • Additional signs being made for pedestrian wayfinding

  7. Phase 1.2 Upcoming Closures

  8. Phase 1.2 Design Update • 100% design plans submitted July 31 • Design review meetings • Subcommittee • Bexar County and COSA • Guaranteed Maximum Price (GMP) submittal September 25 • Presentation of design and GMP to Bexar County Commissioners Court in October

  9. Partner Coordination • Executive Committee • David Smith, County Manager, Bexar County • Lori Houston, Assistant City Manager, City of San Antonio • Mike Frisbie, Director, Transportation and Capital Improvements, City of San Antonio • Suzanne Scott, General Manager, San Antonio River Authority Next Meeting – August 17th

  10. QUESTIONS & COMMENTS