1 / 18

Concrete Structures

Concrete Structures. Units of Measure. Concrete : Cubic Yard Steel : Lb or tons Formwork : Square feet per contact area. Types of Concrete construction. 1. Foundations 2. Columns 3. Slabs and beams. Isolated Footing. Combined Footing. Continuous Wall Footing. Strap Footing.

max
Download Presentation

Concrete Structures

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Concrete Structures DR. Nabil Dmaidi

  2. Units of Measure Concrete : Cubic Yard Steel : Lb or tons Formwork : Square feet per contact area DR. Nabil Dmaidi

  3. Types of Concrete construction 1. Foundations 2. Columns 3. Slabs and beams DR. Nabil Dmaidi

  4. DR. Nabil Dmaidi

  5. Isolated Footing Combined Footing Continuous Wall Footing Strap Footing Raft Foundation Shallow Foundation DR. Nabil Dmaidi

  6. Deep Foundation Caissons Piles DR. Nabil Dmaidi

  7. Columns • Shapes • Square - Rectangle - Circular • Others • Reinforcement • Ordinary - Spiral DR. Nabil Dmaidi

  8. Slabs and Beams: One-Way slabs One-Way Slab, Beam, and Girder One-Way Slab, Supported by Beams or Walls One-Way Joist Slab DR. Nabil Dmaidi

  9. Slabs and Beams: Two-Way Slabs Flat Plate Waffle Slab Flat Slab Two-Way Slab Supported by Beams DR. Nabil Dmaidi

  10. Estimating Issues 1. Formwork is the largest cost item that represents 40% to 60% of concrete structure cost. Distribution of costs for cast-in-place concrete slab wall: DR. Nabil Dmaidi

  11. 2.Waste allowance from 2% to 10% should be added for concrete and concrete formwork. DR. Nabil Dmaidi

  12. 1. Center Line Method Building size: 30’ x 40’ Calculations: 1. Length = 30’10” - 1’6” = 29’4” 2. Width = 40’10” - 1’6” = 39’4” 3. Perimeter = 29’4” + 29’4” + 39’4” +39’4” = 137”4” 4. Volume of concrete = 137.33’ x 1’ x 1.5’ = 206 ft3 30’10” 30’ 40’0” 40’10” DR. Nabil Dmaidi

  13. 2. Sectional Method Calculations: 1.Length = 10.833’+40.833’ = 81.67’ 2.Width = 27.833’+27.833’ = 55.67’ 3.Perimeter = 81.67’+55.67’ = 137.34 Total Linear ft 4.Volume = 137.34’x1’x1.5’ = 206 Cubic feet 5.volume in CY = 206/27 = 7.6 Cubic Yards 30’10” 27’10” 40’10” DR. Nabil Dmaidi

  14. COST OF OTHER COMPONENTS OF CONCRETE WORK 1. Reinforcement Steel 2. Forms 3. Concrete Mix 4. Finishing 5. Curing DR. Nabil Dmaidi

  15. Table 1.DIMENSIONS & WEIGHT OF WELDED WIRE FABRIC DR. Nabil Dmaidi

  16. Table 2SIZES & WEIGHTS OF REINFORCING BAR DR. Nabil Dmaidi

  17. EXAMPLE: How many pounds of rebar are required for the concrete floor area below? 60’ 20’ 6” Concrete slab with #4 rebar 15” on center each way 40’ 30’ DR. Nabil Dmaidi

  18. Step #1: Calculate the total SF of area involved. 20'0" X 30'0" = 600 SF 30'0" X 40'0" = 1 200 SF Total = 1,800 SF floor area Step #2: Calculate the pounds of rebar per SF of floor based on the unit spacing of the rebar at any point of intersection. Unit area: 15" X 15" = 1.25' X 1.25' = 1.56 SF Unit rebar length: 1.25' + 1.25' = 2.5 LF Lbs. of rebar/unit:= 2.5 LF X .668 lbs/ LF = 1.67 lbs • It is now known that there are 1. 67 lbs of rebar per 1.56 SQ FT of floor area. 1.67 / 1.56 = 1.07 lbs/SF of floor area. SO: 1.07 lbs/ SF X 1,800 SF = 1,926 lbs of #4 rebar required. DR. Nabil Dmaidi

More Related