1 / 23

Where New Engineers Deliver New Ideas!

Where New Engineers Deliver New Ideas!. Spring 2008. Our efforts to date have helped the Remembrance Foundation to focus their thoughts about what they want. There continues to be concern about significant cuts and fills in regards to seismic behavior.

Download Presentation

Where New Engineers Deliver New Ideas!

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Where New Engineers Deliver New Ideas! Spring 2008

  2. Our efforts to date have helped the Remembrance Foundation to focus their thoughts about what they want. There continues to be concern about significant cuts and fills in regards to seismic behavior. Some good ideas came out of Phase I that might help with the new concept. Phase I Evaluation

  3. Phase I Time Report Total Hours: 1075 hrs (not counting survey before start of semester) Average Time per person: 35.8 hrs Average time per person per week: 5.97 hrs/week

  4. More Time

  5. Peer Evaluations

  6. Peer Evaluations

  7. Peer Evaluations

  8. Phase II Site Alternative A 1390 ft of trail 30’x100’ Bldg (2) Bridges

  9. Phase II Site Alternative B 1875 ft of trail 30’x100’ Bldg (1) Bridge

  10. Path Criteria All walkways to have a maximum slope of 1:20. Let’s not push it if we don’t have to! Upslope cuts should be kept to 24”. They cannot exceed 30”! We need to leave some allowance for different site conditions. Each of the two major alternatives are to consider An overall “path” width of 10’ An overall “path” width of 20’ The walkways are to be heated. Consider amenities such as benches, lighting, landscaping. Task one person from each Alternative to work on bring utilities to the building

  11. Typical Path Cross Sections

  12. Pod Design Work with Remembrance Foundation to get list of artifacts and sizes. Design pods that can be “plugged in” to the site layouts. Coordinate with site design groups. Consider rectangular as well as round or oval Can have retaining walls up to 4 ft high.

  13. Pod Designs Consider three alternatives for each shape: Half in the hill, half out All in the hill All out of the hill

  14. The Band Stand - To be located on lower slope. - Need to research bandstand sizes. - Design to fit anywhere in the area. - No design for seating… grassy slope will be used. Provide alternatives in Steel and Timber http://www.bboogie.com/Chatham_Band.htm

  15. Environmental, Safety, & Permitting Environmental This is tied in with permitting below Identify all environmental concerns and means for addressing them Safety Determine the safety requirements for the project based on IBC and ADA requirements Communicate criteria to the design groups Permitting Prepare a comprehensive list of all permits that will be required for the project. Identify key design items needed for each permit. Where possible, obtain and fill out permit applications, acquiring required information from the design groups.

  16. Cost Estimating & Specifications Prepare a running estimate of the various alternatives. Present your best guess of project costs at each weekly meeting Identify specifications that need to be written for this project. Prepare a table of contents and draft specifications.

  17. Alternative A Team Freese, David Greva, Ramadan McGee, Steven Runa, Haley  Leader Smith, James Suttie, Jamie Yamat Jr, Anthony

  18. Alternative B Team Balzarini, Charles Halcomb, Steven Mollenkopf, Mathew Mork, David (Mitch)  Leader Nguyen, Binh Redick, Ryan Umanskaya, Lyudmila

  19. Band Stand Design Team Armstrong, Jessica Dougherty, Matthew  Leader Hardy, David Limstrom, Robert

  20. Cost Estimating & Specifications Gilliland, John  Leader Goodell, Christopher Jemison, Jennifer Longden, Katherine Oliveira, Nickolas

  21. Environmental, Safety, & Permitting Eidam, Emily Meehleis, Kurt Parker, Wendy Russell, Kathryn  Leader

  22. Pod Design Team Fedorova, Olga Keib, Elijah  Leader Michael Mott Putman, Jesse

  23. Expectations Assignments may be changed as the needs of the project evolve. Team Leaders Check in with me at least once a week to update on progress and keep in touch. Short (5-10 minute) weekly presentations at the staff meeting. Keep filing your weekly individual reports.

More Related