490 likes | 638 Views
Unit 1. Conflict : Disputes & Arbitration. Objectives. List and group p otential causes of complaints or disputes during construction Describe the actions available to the parties in the event of complaints or disputes arising
E N D
Unit 1 Conflict : Disputes & Arbitration
Objectives • List and group potential causes of complaints or disputes during construction • Describe the actions available to the parties in the event of complaints or disputes arising • List and describes sources of external advice available to the respective parties involving in the complaint or dispute • Formulate a working plan to review each project with respect to avoiding and/or minimising complaints or disputes using proactive management techniques
Objectives • Establish a contingency plan to accommodate unforseen complaints or disputes • Outline the dispute procedure as required by the Home Building Act 1999
Complaints • Discuss complaints you’ve had on jobs • Processes to avoid and minimise these complaints • List types of complaints you’ve had on the job • Disputes come in all forms • It is important to stop the complaint becoming a dispute • Good communications • Good practice to avoid all disputes
Contracts • What is a Contract ? • Contracts are legally binding agreements between private parties • Enforced by the Government through the courts • Everybody has freedom to contract anything within the law • Parties to the agreement must comply to the terms of the contract • Real or Perceived non compliance can lead to complaints & disputes
Contracts • Contracts should be used in all cases • Home building act requires that projects valued over must have a written contract for the builder to be able to claim payment • There are various types of contract • Standard form MBA, HIA • Standard form Department of Fair Trading • Specific purpose prepared by either builder or client
Contracts • What other ramifications on type of contract • MBA HIA contract usually favour builder • DFT usually favour client • Specific purpose contract – if somebody goes to the trouble, you can guarantee it will favour the drafter of the contract
Contracts • Remember contracts are legal documents • Make sure you understand the requirements as you will be legally bound • Having this understanding of the requirements will be the first step in minimising complaints
Complaints • What is the most common type of complaint ? • Most complaints are caused by lack of communication
Builder and Client Disputes • Obviously between builder (you) and • Client (the person you’re building for) • Client may also include • Architect (Bayline v ……..Child Care) • Engineers • Financers (Wintertons Vs Hambros) • Architects and other professional agents of the client – ultimate dispute is with client
Builders and Client Dispute • Disputes may be wide and varied • Types of finishes specified in contract • More confusingly, items not specified in contract lead to disputes • What type of bath ? • What type of skirting ? • Who pays power fees? • A building contract needs to be very detailed
Builder & Client Disputes • Quality of Work • Is the same standard of work required in a Department of Housing Unit as in a unit at Benalong Point • Variations • Client always thinks it’s included builder thinks it’s an extra
Builder and Client Disputes • Extension of time • Contracts will specify format of claim • How much delay is caused by rain ? • Client can’t make up mind in deciding of tiles • Is it a critical item ? – Not all delays are critical
Builder and Client Disputes • Performance and completion • What is the date for practical completion ? • This is dependent on delays, variations, extension of time • Liquidated damages ? • Is the job complete ?
Builder and Client Disputes • Document interpretation • Specification says granite bench tops • Plans say laminate • Contract should specify order of precedent • Where does precontractual documentation and correspondence fit in ?
Builder and Client Disputes • Progress payments • Has work been completed ? • Is payment due ? • Retention ?
Builder and Client Disputes • Disputes may affect • Cash flow • Company reputation • Which may in turn affect the viability off the company • That’s why conflict resolution is an important business management tool
Builder and Union • Neglect award conditions • Neglect safety • Disputes may start from very minor issues e.g. pie ovens, dim sim allowance • Disputes may cause stoppages which may be very expensive
Builder and Sub Contractor • These types of disputes are similar to client builder disputes • Builder is normally called principal/head contractor • Sub contractor contracts to builder contracts to client – Sub contractor cannot sue client under contract and vice versa
Builder and Sub Contractor • Quality off work • Client, builder and Sub contractor may not necessarily agree with each other on required quality of finishes • Client, builder and Sub contractor may not necessarily agree on materials to be used
Builder and Sub Contractor • Performance and attendance • Sub contractor may also claim extension of times • Delay may not be caused by client issues – this may lead to Sub contractor having more time to complete works than builder has with client • Subcontractor may have many jobs • This conflict will inevitably lead to builder client conflict
Builder and Sub Contractor • Variations • Builder has two different contracts • First contract builder to client second contract builder to contractor • Extremely rare to be same type of contract inevitably there is conflict between the two • Example - Head contract may include rock excavation, Sub contractor may not include it
Builder and Sub Contractor • Payments • Payments scheduled on head contract may not match Sub contract – affecting cash flow • What happens if client doesn’t pay and Sub contractors payment is due – non payment is not caused by Sub contractor
Dispute Resolution • What do you do? • Firstly try identify the cause • You may be in the wrong • It may be a simple misunderstang
Dispute Resolution • Next Step? • Meeting between the parties – try reach mutual agreement
Dispute Resolution • Next Step – Dependant on Contract – Limited by Home Building Act • HIA Contract Specifies meeting must be held within 10 days after formal notice of Dispute • Independent Arbitration – not allowed!
Dispute Resolution – Non Residential • Contracts dealing with non residential building contract will specify Dispute Resolution. • May Specify Arbitration/Concilliation before any court action taken • Legal Action may proceed through the courts or Consumer Claims Tribunal
Dispute Resolution • Home Building Act requires that initial complaint to be made through Department of Fair Trading • DFT will investigate and may issue rectification notice – notice is only advice • DFT will not become involved in contractual matters
Dispute Resolution • If DFT cannot resolve matter options are either • Consumer Claims Tribunal (CCT) – has a mandate to solve disputes through conciliation. If this is not Possible will make binding ruling • Magistrates, District and Supreme Court depending on limits
Consumer Claim Tribunal • View CCT Video
Dispute ManagementSteps to Take • Set up your contract requirements- use quotes from pre printed books with you conditions • Note contract law requires that conditions are brought to notice of your client. Otherwise the conditions will not apply. • These forms will evolve as you pick up mistakes
Dispute ManagementSteps to Take • Similarly use a standard form for your contracts • This will also evolve as you pick up errors • Make sure your clients and subcontractors clearly understand the contract. • Ensure that written contract reflects the agreement and all its conditions
Dispute ManagementSteps to Take • Install a process of quality assurance • This is more value on larger jobs • This may be a requirement on government jobs
Company Working Plan • This is simply a policy or plan of management practices that will reduce the chances of complaints & disputes arising • This policy should be designed to prevent complaints developing into disputes
Documentation • All disputes should be documented • This will provide a good evidence trail in the event the matter is taken further. Importantly- the initial complaint- your response and your offers to settle (remember CTT has a mandate to settle disputes by conciliation)- keep minutes of any meetings, send a confirmation
Documentation • Provides a working plan for future disputes
Contract • It is important that contract reflects your agreement • Complies with the requirements of the Home Building act - Be in writing - Binding Arbitration not allowed
Contract Administration • Contract should be enforceable What should the contract cover • Names of the Parties • Extent of Works • Payment Schedule • Dispute Resolution Process (Note Home Building Act has specific procedures) • Required Notices – Extension of Time etc • List Others ?
Industrial Relations • Employer has legal obligation • OHS – What is primary requirement? • A controller of a workplace must provide a safe workplace to ensure the SAFETY of employees & visitors. Sec 9 OHS act (2000) • An injury is evidence of breach. You have to mitigate
Industrial Relations • Workers Compensation • Must have a policy that covers all employees • If no policy exists then employer is personally liable • If you employ someone under A.B.N are they an employee for Workers Compensation Purposes?
Industrial Relations • Taxation, Rates of Pay, Superannuation • Employers must collect Tax and remit to ATO • 9% of Ordinary Time for superannuation
Industrial Relations • If you employ someone under A.B.N are they an employee for Tax Purposes? – This a tax issue • What is the 80/20 Rule
Industrial Relations • If you employ someone under A.B.N are they an employee for Superannuation Purposes? • – This is a Common Law Issue
Industrial Relations • Management of the previous issues is important to avoid industrial disputes. • If your workforce is not “WORKING” you aren’t making money. – Your Overheads are still accumulating!
Contingency Plans • Forecasting disputes • Records and/or Experience will tell areas that traditionally lead to disputes – What have you found consistently cause disputes • What use can previous records provide?
Planning & Organisation • Once identified you can anticipate disputes • You can take put management strategies in place
Controlling • Define the Problem • Gain the facts • Review the evidence • Consider Alternatives • Develop plan
Co-ordination • You as the builder must co-ordinate the process • Manage the Client/Architect • Manage the Suppliers • Manage the Subcontractors
Review • Forecast & Predict • Planning & Organisation • Controlling • Co-ordinating