1 / 17

Power Distribution Scheme for Efficient Operation of LEP Klystrons

This document discusses the re-use of LEP RF equipment, focusing on klystrons, circulators, and power distribution for optimized performance. It covers the technical specifications, challenges, and solutions related to the LEP Klystrons system.

mcelfreshc
Download Presentation

Power Distribution Scheme for Efficient Operation of LEP Klystrons

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Linac4: Klystrons and Power DistributionNikolai Schwerg27/05/2010

  2. Starting Point: Re-use LEP RF equipment • Klystrons • 20 LEP Klystrons (3 Manufacturers) • together 50 years of operation left • Re-tuning necessary • Maximum power ? • Circulators • 29 AFT-Circulators (different specifications) • Reflected Power only 300 kW (for most circulators) • Constrains • Phase and Amplitude for DTLs • Space for PIMSs • Similar design for all whole installation

  3. Klystron-Gallery: LEP Klystrons RFQ DTL CCDTL PIMS Amplifier LEP Klystron 2.8 MW-Klystron LEP Klystron 2.8-MW-Klystron

  4. Klystron-Gallery: Final Version RFQ DTL CCDTL PIMS Amplifier 2.8 MW-Klystron

  5. Power Distribution Scheme – LEP Klystrons Ferrite Loads LEP Klystrons LEP Circulators Cavities [Courtesy of J-P. Corso]

  6. Power Distribution Scheme – 2.8 MW Klystron Folded Magic-Tee 2.8 MW Klystron Ferrite Loads Cavities Σ LEP Circulators 0° 0° 180° 0° Δ [Courtesy of J-P. Corso]

  7. Power Distribution Scheme – Alternative Waveguide Routing [Courtesy of J-P. Corso]

  8. Power Distribution Scheme – Alternative 2.8 MW Circulator • AFT claims to be able to built a 2.8 MW circulator without SF6 • Required: • Offer – Price? • Prototype for Testing Magic-Tee 2.8 MW Klystron 2.8 MW Circulator Cavities Ferrite Load Ferrite Load Σ 0° 0° 180° 0° Δ

  9. Quantitative Approach • Use S-Parameters: • Ideal, e.g. Magic-Tee, Cavity, … • Measured, e.g. LHC Circulator as function of T and I • Solve for: • Cavity input signal • Reflection to Klystron • Compare for all Working Points (thousands!)

  10. Test-Stand in Bat. 112 • Klystrons • Tuning of LEP Klystron • Montage and Testing of HV-Box • High Power Test • Circulators • High Power Test • Cavities  RP? • Commissioning • Test of Full Installation • Folded Magic-Tee • Coupling between Circulators • Higher Order Modes • Running by end of 2010 CCDTL/PIMS/DTL Klystron Preparation

  11. Waveguide Connections • Determine: • Waveguide length to Cavities • Number and Type of Bends • Derive Phase Difference • 3-Post Phase Shifter • Being built [Courtesy of J-P. Corso]

  12. Ongoing Activities and Open Questions • Components: • Performance of the Folded Magic-Tee • Properties of 2.8 MW Circulator • RF Power Distribution Layout: • Waveguide Length • Phase Shifter • Coupling of Circulators • Cost and Risk Comparison • Testing: • Building Test-Stand in Bat. 112 • Schedule for Cavity • Components and Full Layout Picture by MEGAindustries: Folded Magic-tee in WR650

  13. Thank you for your Attention -- Discussion --

  14. Klystron Replacement As presented by Olivier Brunner

  15. Folded Magic-Tee • Specifications: • Frequency: 352 MHz • Insertion loss: < 0.1 dB • Isolation between ports 1 and 2: > 37 dB • Balance between ports 2 and 4: < 0.2 dB • VSWR: 1.10:1 MAX (-26 dB) • Power: Peak 2.8 MW Average 10 kW or 150 kW • These values are identical to the values of a standard magic-tee of the same supplier Picture by MEGAindustries: Folded Magic-tee in WR650

  16. Design Constrains / Guidelines • Mechanical: • Limited space in Klystron Hall (approx 3.50 m width) • RF: • Minimum Reflection to Klystron • Higher Order Mode Compensation • Phase and Amplitude balance between both Cavities • Prevention of Arcing • Installation: • Using an identical Design for all Klystrons • Considering two Variants: LEP Klystrons and new Klystrons • Operation: • (Tuneablity) • Accessibility of Loads and Circulators (Ferrite Breaking)

  17. Powering Schemes RFQ DTL CCDTL PIMS Phase I Amplifier LEP Klystron 2.8 MW-Klystron LEP Klystron 2.8-MW-Klystron 6 m 3.7 m 19 m 25 m 22 m Phase II RFQ DTL CCDTL PIMS 50 MeV 100 MeV 160 MeV 3 MeV Amplifier 2.8 MW-Klystron 17

More Related