An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. September 2010 Closing Report Authors: Date: 2010-09-16 Dorothy Stanley (Aruba Networks)

  2. Abstract This document contains the TGv closing report for September 2010. Dorothy Stanley (Aruba Networks)

  3. Goals and Accomplishments • Completed comment resolution from sixth Recirculation Sponsor Ballot • 1099 comments, 1099 resolutions completed, 0 remain • Next recirculation SB 15Sept to 30Sept on D15.0 • Teleconferences • Sept 30, Oct 12, 14, 19, 21, 26, 28, Nov 2, 4, 2pm Eastern (11am Pacific), 2 hours • Adding Oct 5, 7 11am Pacific, 2pm Eastern (5am HongKong), 2 hours Dorothy Stanley (Aruba Networks)

  4. TGv Timeline – Updated September, 2010 • Initial Working Group Letter Ballot: July 07 – completed • Jan 08 – D2.0, May 08 – D3.0, Nov 08 – D4.0 • Re-circulation Working Group Letter Ballot: November 08 (D4.0) • Mar 09 – D5.0, May 09 – D 6.0, July 09 – D7.0, D7.0(unchanged) • Form Sponsor Ballot Pool: August 09 • Initial Sponsor Ballot: Oct 09 • Oct 09 – D7.0 Approved Sponsor Ballot: Nov 09 • Jan 10 – D8.0, D9.0, March D10.0, May D11.0, June D12.0, July D13.0 August D13, D14, Sept D15.0, Oct D15.0[unchanged] • 18Oct submit for Dec Revcom approval • WG/EC Approval: July 2010 (Conditional) • RevCom/Standards Board Approval: December 2010 – was Sept Dorothy Stanley (Aruba Networks)

  5. Goals for September-November 2010 • Recirculation Sponsor Ballot • Resolve comments from Recirculation Sponsor Ballot • Subsequent Recirculation Sponsor Ballot • Revcom submission Dorothy Stanley (Aruba Networks)

  6. References Dorothy Stanley (Aruba Networks)