LS2 North Experimental Area Consolidation Ongoing activities / Where are we?

LS2 North Experimental Area Consolidation Ongoing activities / Where are we?. F. Gautheron, Y. Kadi, A. Papageorgiou Koufidou, E. Solodko, M. Wilhelmsson (EN-EA-PE) EACM, September 24 th , 2019. PPS Access point BA80 replacement done. PAD/MAD installed 3 weeks ago

mcorpus
Download Presentation

LS2 North Experimental Area Consolidation Ongoing activities / Where are we?

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LS2 North Experimental Area ConsolidationOngoing activities / Where are we? F. Gautheron, Y. Kadi, A. Papageorgiou Koufidou, E. Solodko,M. Wilhelmsson (EN-EA-PE) EACM, September 24th, 2019

  2. PPS Access point BA80 replacement done • PAD/MAD installed 3 weeks ago • Tuesday 10th: functional test by BE-ICS. • From Wednesday 11th September: “en service” • Team moves to next installation in BA81 • Ongoing: instrumentation of the doors YDPS02.80o, YDPS01.800, YDPV01.800, YDPV02.800 • Remaining work: • March - April 2020 :EIS instrumentation & Test (accessoccasionallyperturbated) F. Gautheron et al. - EACM September 24th, 2019

  3. PPS Access point BA81 replacement ongoing • Activity for replacement started on September 11th • Mechanical parts almost done • This week and next week: connection to electrical and communication networks. • Tests and validation: 7-11th October • Expected “en service” on October 14th • Aug- Sept 2020 :EIS instrumentation & Test (accessoccasionallyperturbated) F. Gautheron et al. - EACM September 24th, 2019

  4. Access point SPS-PPS TCC8 & lift • Replacement of the access point bldg. 912 • Replacement of the lift AS516 • Co-activities organized – No conflict expected • W43 [21-25 October]: removal of actual PAD (turnstile) • W44 – 47: removal of the old lift, extraction of big pieces, install. new lift • W48: installation of the new PAD/MAD • From W49: adaptation to punctual necessities between teams (EN-HE/BE-ICS) • Sept – Oct. 2020 :EIS instrumentation & Test (accessoccasionallyperturbated) F. Gautheron et al. - EACM September 24th, 2019

  5. ECN3: renovation activities starting soon • SPS PSS access point in bldg. 911 • Actual BE-ICS planning indicates work during [mid-October / mid-November] • EN-HE rails replacement for the crane in ECN3 [21/10 – 01/11]. • Time slot confirmed long time ago. • Use of the pit/crane to transfer long rails • -> Safety issue since access point and pit are close to each other • BE-ICS is revising its time slot to adapt the intervention. Discussion ongoing with the contractor. No feedback yet. • Oct – Nov. 2020 :EIS instrumentation & Test (accessoccasionallyperturbated) F. Gautheron et al. - EACM September 24th, 2019

  6. Crane consolidation in 888 (EHN2) • August 12-21: old 5t crane removed, new 10t crane installed • Work on the 40t crane started 4 weeks ago, should last until end of September. Load test (40 t) September 19th F. Gautheron et al. - EACM September 24th, 2019

  7. TA 852 ventilation door (TCC8) - Air tightness • Aluminum sheets fixed on the door 2 weeks ago • Passage of pipes through the fence to be closed • Cables trays not yet closed since an optical fiber has still to be pulled, foreseen by EN/EL week 42 • Access restricted w43 – w52 • Replacement of the access point SPS-PPS • Replacement of the local lift • Air tightness work on cable trays and around pipes to be terminated beginning of 2020 F. Gautheron et al. - EACM September 24th, 2019

  8. No further free access to galleries post LS2 Recommendations from the safety review & DSO for ODH & CO2 risks • All gallery access to be locked • EHN1 already done • EHN2 ongoing • Caged ladder (Saleve side) to be locked • Jura side fenced and locked (by end of 2019) • Saleve side access through BA82 • Procedure put in place: IMPACT -> TRAKA (EHN1) -> key + ODH &CO2 portable detectors F. Gautheron et al. - EACM September 24th, 2019

  9. Gas Network Consolidation More info in the David’s talk • Only EHN1 Saleve side during LS2 due to budget cuts • Reduction of the number of mixing areas : 2 • One mixing area already modified, new rack under design, waiting for the instruction (TSO) for the second mixing area. • All gas patch panels already produced, half of them in placed in PPE’s but not connected • 887/R-K52 (PPE 146), 887/R-P40 (PPE 138), 887/R-P58 (PPE 158), 887/R-L75 (PPE 168) • Racks produced & to be transported 887/R-K56 (PPE 156) & R-M84 (H8 beam dump area) • Gas barrack 907: waiting for a final offer for racks. • Check valves (EATM request): to equip all the distribution racks (EHN1, EHN2, ECN3) • Might require 2 -3 weeks of service interruption (looking for a possibility of sectorization instead) • Flowmeters to monitor networks, installation foreseen this year • ATEX extraction bldg. 907 during LS2. Bldg. 909 postponed after LS2 F. Gautheron et al. - EACM September 24th, 2019

  10. Flammable Gas Detection & ODH • EHN1– Saleve side (Jura side already migrated & operational) • Barrack gas 907 already equipped (no flammable gas actually in use) • ODH in Galleries (GHN 14,15,16) with previous sensors (No CO2 detection) • FG sensors to be installed once new gas distribution in place (1st semester 2020) • Mixing gas areas • Experimental areas • PPE168 pending – area to be reorganized, no further news. • Cabling once EN-EL manpower available, ~September 2020 • Commissioning will follow • Old system deactivated, but racks not yet removed • EHN2, ECN3 • EHN2 : 2020: BE-ICS OK, budget available (optical fiber ordered by EN-EL-FC) • ECN3 : to be migrated to Syntel system – 2020. BE-ICS OK, budget available F. Gautheron et al. - EACM September 24th, 2019

  11. Cooling & Ventilation - EN-CV • Consolidation of control towers CT2: • Electrical consolidation ongoing (foreseen by the end 2019) • Control system replaced in 2020 (delivery foreseen beginning of April 2020) • Underground technical galleries ventilation study ongoing • Safety review “Install a ventilation system in the gallery in order to avoid local accumulation of gas” • Ongoing study of cooling in BAs for the PSU of Beam lines magnets • Option with H2O cooling for SIRIUS PSU • Option with Air cooling for APOLO PSU F. Gautheron et al. - EACM September 24th, 2019

  12. Radioprotection HSE-RP • CROME deployment in NA • March 2020 : TDC2 (9 monitors) • Avril 2020 : TCC2 (13 monitors) • May/June2020 : EHN1 (46 monitors) • Beginning of August 2020 : TT84/TT85 (2 monitors) • End of August 2020 : EHN2 : (4 monitors) • Commissioning : August to December 2020 • RP tests: October 2020 to February 2021 • Access control to transversal underground galleries (EHN1 & EHN2) • Generalize fences in EHN1 (2/6 actually) all with padlocks (keys in CCC) • EHN2: Dose rate exceeds limits on Jura side (RP survey 2018) : “close gallery GHN21 in addition to GHN22 with EN/EA padlock to prevent access to Jura side” • Access through IMPACT -> TRAKA (in EHN1). Same rule than for ODH/CO2 risks F. Gautheron et al. - EACM September 24th, 2019

  13. Power converters – TE-EPC • Ongoing studies for new PSU (SIRIUS vs APOLO) for beam line magnets • DCCT + FGC3 ordered for VERTEX 1,2 and ATLAS-Morpurgo (EHN1) • Components to be integrated in the new PSUs during LS2 – Lab work • PSU installation foreseen in 2021 (YETS 2021/2022) F. Gautheron et al. - EACM September 24th, 2019

  14. Magnets – TE-MSC • Exchange of water distribution manifolds for magnets cooling • 180 Single connections & new water hoses • EN-CV in charge • Not started ! F. Gautheron et al. - EACM September 24th, 2019

  15. Beam Instrumentation (EN-EA & BE-BI) • Renovation of 26 VME crates + extender interfaces in EHN1 needed for compatibility with BE-CO control systems > LS2 => concerns all beam instrumentation signals => material ordered / consolidation ongoing • Foreseen for LS2 – urgent needs: • 10 XCET (gas panels, gas control system, windows, vacuum pipes), • 5 CEDAR (obsolete gas control system), • 40 XSCI (voltage dividers) • 1 Longitudinal spill detector (new electronics) • Foreseen in 2020: cabling for BLMs, BTVs, vacuum,.. In NA primary beam line TT20 + TDC2 F. Gautheron et al. - EACM September 24th, 2019

  16. Beam intercepting devices • 2019: • Renovation 4 block collimators : study ongoing (EN-EA) • Define technical specifications for XTDV tables • Purchase material (motors+ mechanics) for 5 Magnetic collimators XCMV, XCMH (M2) • 2020: • 2 & 4 block collimators consolidation • 2 collimators 2 blocks (reserve ) & 4 collimators 2 blocks installed (TT81, TT82) • 1 collimator 4 blocks (reserve) + 4 collimators 4 blocks (installed) • Various spare parts for TCC2/TCC8 targets • TCSC leaky cooling circuit • XTDV elevating table for beam dumps (total 8; 4 in 2020) - purchase • Micro-collimator (1) maintenance F. Gautheron et al. - EACM September 24th, 2019

  17. Civil Engineering (SMB-SE) • EHN1 drain siphons renovation => done • Roof repair of gas barracks : • 907: pending • 908: done • 909: pending • 920: pending • Buffer zones completed • Other activities currently under discussion with SMB-SE F. Gautheron et al. - EACM September 24th, 2019

  18. TE-VSC • Cabling for vacuum controls in TDC2/TCC2 • No removal of ancient irradiated cables • Replacement of damaged : • Ion pumps, connectors, gauges, … • 3 window valves for beam line vacuum sectorization F. Gautheron et al. - EACM September 24th, 2019

  19. NA Safetyconcerns … • In addition to the safety improvements already listed : • Flammable gas, ODH, CO2 • New “CROME” RP detection deployment network • Underground galleries access control • … • Identified electrical non-conformities from periodic safety visits • Accessible parts under power • Lack or incorrect differential protection • Grounding issues • AUL cutoff range not indicated or not fully defined • … Priority to what jeopardizes the safety of personnel F. Gautheron et al. - EACM September 24th, 2019