An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LTU-Dump Installation Status&Schedule

  2. Linac Status and ScheduleInstallation Coordination • Installation Team • Installation Status • Schedule • Safety • Summary

  3. Installation Team • Kathleen Ratcliffe LTU and E-Dump installation manager • Mike Zurawel Undulator installation manager • Ponce Rodriguez Cable installation manager • Richard M. Boyce & Stuart Metcalfe installation coordination managers • Supporting organizations • Building Inspection Office, Cable shop, Communications, Controls, Facility, LCLS CF, MFD and Purchasing • Davis Bacon contractors: J D Collins Co., Harris Constructions, Palmer Electrics, TDN Electric, D.W. Nicholson and Rushford Contractions • Mechanical Engineers • Carl Rago, Don Schafer, Eric Bong, Phil Cutino and Tim Montagne

  4. Status: LTU Installation November 2008 June 2008

  5. Status: Undulator Installation June 2008 November 2008

  6. Status : Dump Installation November 2008

  7. LTU-Dump Floor Settling

  8. Undulator Temperature Monitoring

  9. Undulator Temperature Monitoring Fan Off

  10. Status: What Have Not Been Installed • LTU • Single Beam Dump and TDUND shielding • 150KG quadrupole electrical covers • Vacuum pump down section 82 (TDUND area) • Undulator Hall • Undulator beamline vacuum pump down • 5 ANL Beam Loss Monitors • Dump • Complete interconnection of vacuum chambers • Secure dump pit from personnel

  11. Installation Challenges and Issues • LTU • BTM were just received from supplier for installation • Installing heavy pieces of marble shielding without overhead crane • Undulator • During BFW checkout we found 5 units with broken carbon wire, these wire were replaced. • Some Evac flanges leaked during installation, knife edges were inspected reworked at SLAC • Dump • Installation BYD magnet and chamber without overhead crane • Interference between BYD magnet and chamber, solved by using smaller socket head screw • Verification of BXPM magnet, Jim Turner developed a plan for this verification • Minor interference fit of supports that required modifications

  12. Schedule • LTU Status • Magnet Installation @95% (Davis Bacon) complete • Install Vacuum components (SLAC-MFD) complete • TDUND, Single Beam Dump & Zero Degree Shielding in progress • Cable Installation (Davis Bacon)complete • Check Out in progress • Undulator • Pedestal & Girder installation complete • Leak Check & Pump Down in progress • Cable installation complete • Check Out in progress • Undulator Magnet Installation 3/9/2009 • E-Dump • Complete Stand Installation (Davis Bacon)complete • Complete Magnet Installation (Davis Bacon)complete • Install Dump Shielding (Davis Bacon) complete • Install Vacuum Components/drifts (SLAC-MFD)in progress • Cable Installation (Davis Bacon)complete • Check Out in progress

  13. Installation Assurance & Safety • Tailgate meetings before every shift to discuss daily activities and any safety related issues • Everyone are safety trained before they are allowed to work in the construction area • Everyone are required to sign in and out of construction area • Job walk with contractors before start of each job • Installation weekly meetings • Instituted Quality Control check list sign off for both components and post installation • Safe Performance Observation walk (minimum once a week for managers)

  14. Safety Approval Documents • Statement of Work (SOW) – These documents are written by installation manager for Davis Bacon contractor and are submitted to Building Inspection Office, BIO, for approval. BIO requires 11 signatures for approval • Davis Bacon contractors are required to submit and approval of following documents: • Industrial Injury and Illness Prevention Plan (3 approval signatures) • Site Specific Safety Plan (4 approval signatures) • Job Safety Analysis (3 approval signatures) • Rigging Plans (3 approval signatures) • Work Authorization Form (WAF) – this is approval for SLAC employee to work in installation site (8 approval signatures)

  15. Summary • Progress towards completion of 2008 installation is going well. Only few areas needed to complete in next two weeks • Based on last three installations, 2008 installation was the longest and best organized • Successful collaboration with Argonne National Lab colleagues on Undulator Hall installations • Plans are in development to repair RFBM windows in an event they develop leaks • Post E-beam installation: • Kathleen Ratcliffe will be supporting future installation managers • Mike Zurawel will be area manager for Undulator Hall • Phil Cutino and Don Schafer will be LTU-Dump area engineers