140 likes | 285 Views
CWPPRA Terracing and Marsh Creation South of Big Mar Project (BA-24). Project Kickoff Meeting April 17, 2013. Meeting Goals. Review project background Discuss project features and potential changes or additional features to investigate
E N D
CWPPRA Terracing and Marsh Creation South of Big Mar Project(BA-24) Project Kickoff Meeting April 17, 2013
Meeting Goals • Review project background • Discuss project features and potential changes or additional features to investigate • Discuss engineering and design tasks necessary to reach 30% design milestone • Discuss other Phase 1 tasks – landrights, permits, NEPA • Develop a schedule for Phase 1 tasks to reach 30% design
Background • Developed to restore the marsh platform scoured by Hurricane Katrina • Will work in concert with the Lake Lery Shoreline Protection Project (BS-16) to reinforce the historic Lake Lery Shoreline • Terraces will reduce wave fetch in the large open water areas and promote conditions conducive to growth of marsh vegetation and submerged aquatic vegetation. • Will also benefit from freshwater, sediments, and nutrients provided by the Caernarvon Freshwater Diversion Project.
Project Features Marsh Creation 335 acres of marsh created and restored • Terracing • ~65,000 linear feet of terraces (50 acres)
Project Features(Cont.) • Marsh Creation • Approximately 2.5 M cubic yards of material would be dredged from a borrow site proposed in Lake Lery • Retention levees gapped/degraded to support estuarine fisheries access and to achieve a functional marsh • Pipeline layout initial design:
Project Features(Cont.) Terraces • Terraces LF was not based on the standard >>> 250 ft apart, 70.2 LF per acre • which would result in 67,883 LF comprising 967 acres of terraces • GIS effort was conducted that placed the terraces 300-400 feet apart with 65,000 LF of terraces in approximately 1,000 acres. Terraces based on: xxx LF/acre and xxx' spacing
Benefits/Costs • Benefits: 307 net acres of intermediate marsh over 20 years. • Fully funded cost = $23,843,953 • Phase 1 cost = $2,258,696 • Approved for Phase 1 funding by the CWPPRA Task Force on January 24, 2013.
Design Considerations • Configuration of terracing • Borrow Area/Dredge pipe route • Dewater locations • Gapping vs. degrading • Tidal creeks • Identify additional /alternative areas that would benefit from terraces or marsh creation
Engineering & Design and other Phase 1 Tasks • Surveys • Wave analysis – same borrow area • Geotechnical Investigation • Gage Installation • Landrights • NEPA • Permit Application • Cultural Resources