An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Network Diagramming

  2. Network Analysis • The common term for network analysis is PERT • PERT stands for Program Evaluation and Review Technique • The word PERT, though, has grown to mean network analysis in general

  3. Network Analysis • Goal is to find critical path and bottlenecks What is critical path? Those tasks that have the most schedule pressure

  4. Comparison Gantt Chart Milestone Chart

  5. PERT CHART

  6. 4 6 Terminology and Symbols Event Activity Start Work Sign Contract

  7. Terminology and Symbols Burst Point - Many Tasks Starting when One Finishes

  8. Terminology and Symbols Sink - Many Tasks Finishing before One Can Start

  9. Performing the Analysis • Forward Pass - Working forward through the network to find earliest start and finish times • Backward Pass - Working backward through the network to find latest start and finish times

  10. Earliest Start and Finish Times • The earliest times the tasks can start based on the constraints of the preceding tasks and their relationships to each other. • So, if task A can’t finish till Monday at 5pm, task B can’t start till Monday at 5:01 pm.

  11. Latest Start and Finish Times • The latest times the tasks can start and finish based on the succeeding tasks and the ultimate finish time. • If the contract says the end date for the project is March 11th, then the project has to finish March 11th.

  12. Slack Time • There are two types of slack: • Free slack is float time between tasks based on the relationships of the tasks • Introduced slack is the float time built into the network by contract - this is not in book, but is common in networks, also called total slack

  13. Example 1

  14. Example 1 C E G A B F D

  15. Calculations • Earliest Start = Latest start from proceeding task • Earliest Finish = Earliest Start + Task Length • Latest Finish = Latest Start from Succeeding Task or Contractual Finish • Latest Start = Latest Finish - Task Length

  16. Forward Pass No Introduced Slack

  17. Example 1 A ES = 1 EF = 1 + 1 = 2 C E G A B F B ES = 2 from A EF = 2 + 3 = 5 D

  18. Example 1 C ES = 5 from B EF = 5 + 4 = 9 C E G A B F D D ES = 5 from B EF = 5 + 3 = 8

  19. Example 1 E ES = 9 from C EF = 9 + 6 = 15 C E G A B F F ES = 15 from E (NOT D) always use latest, earliest finish EF = 15 + 3 = 18 D

  20. Example 1 C E G A B F G ES = 18 from F EF = 18 + 1 = 19 D

  21. Backward Pass

  22. Example 1 C E G A B F G LF = 19 LS = 19 - 1 = 18 D

  23. Example 1 E LF = 15 from F LS = 15 - 6 = 9 C E G A B F F LF = 18 from G LS = 18 - 3 = 15 D

  24. Example 1 C LF = 9 from E LS = 9 - 4 = 5 C E G A B F D LF = 15 from F LS = 15 - 3 = 12 D

  25. Example 1 A LF = 2 from B LS = 2 - 1 = 1 C E G A B F B LF = 5 from C (NOT D) Use earliestLatest Start LS = 5 - 3 = 2 D

  26. Start and Finish Times

  27. Critical Path • Critical path (CP) are those tasks with no free slack. So, • LS - ES - introduced slack = 0 • LF - EF - introduced slack = 0

  28. Example 1 Critical path in red. C E G A B F D D has no free slack Critical Path has no free slack

  29. Example 2

  30. Example 3

  31. Estimated Times • When combining data for calculating times the best way is: [best time + (4 X Average) + worst) = ML 6 ML = Most likely

  32. Estimated Times • Best time = 14 • Average = 17 • Worst = 28 • [14 + (4 X 17) + 28] = ML = 18.3 or 19