City of WinnipegSOUTHWESTERN RAPID TRANSIT CORRIDOR Bidder Meeting October 16th, 2009
Field Investigations • - Klohn Krippen (2003) - Geotechnical • 4 deep test holes, 1 shallow • Groundwater monitoring • Laboratory testing • AECOM (2009) - Geotechnical • 2 deep test holes ( rock coring) • Groundwater monitoring • Laboratory testing • AECOM (2009) – Hydrogeological • Two test wells drilling • Field pump tests
Location of Test Holes TW 1 TW 2
Clay : 2 m below ground, Elv. 231 m • Bedrock/Till : Elv. 224 to 226 m • Impact on: • Excavation stability • Global stability • Seepage Groundwater Conditions
Geotechnical Concerns • Foundation type • Rebound, heave and settlement • Retaining walls • Base heave • Temporary shoring and excavation plan
Bearing capacity and foundation type • Raft foundation • Design based on the concept of floating foundation • Bearing capacity and settlement pressure are defined
Retaining walls • Reinforced Concrete U-shaped section • Reinforced Concrete Cantilever wall • Coulomb Theory • Design for surcharge from compaction during construction • Design for live load surcharge from Cooper E90 loading
Base heave Clay h Wclay Till/Bedrock FS = Wclay / γw h
TYPICAL EXTREME HISTORICAL
Temporary shoring and Excavation plan • Cut and cover construction • Staged construction, Stage I and II • Site constrains: • Limited space • Utilities • Private property • Proximity to CN tracks • Excavations plan include: • Open excavation • Cantilever / Braced Shoring • Combination of shoring and open excavation
Temporary shoring and Excavation plan • Excavation configurations • Open Excavation, up to 6 m cut • Other geometry < 6m cut 4 1 3 3 1 3 3
Temporary shoring and Excavation plan • Excavation configurations • Braced Shoring up to 9.5 m 4.6 Min ~ 9.5 ~ 5
Temporary shoring and Excavation plan • Excavation configurations • Combination of Braced Shoring and Open excavation varies 5 m Min. 7m bench 5 m Crane pad 4.6 3 1 2-3 varies 7 Max. 3 - 5
Temporary shoring and Excavation planLateral Loads from Surcharge
Temporary shoring and Excavation plan • Base Instability : analogous to bearing capacity
Global Stability • - Stress – stability coupled finite element analysis • Locally acceptable soil parameters • Account for excavation unloading • Model train loading • Design objective FS = 1.30
Performance Monitoring Program • Instrumentation will be installed to monitor • Displacement of railway tracks • Displacement of shoring system • Horizontal subsoil displacement • Excavation heave • Groundwater levels