Save the American River Association APPEAL OF REGIONAL PARKS PERMIT FOR INAUGURAL GOLD RUSH 100K RACE April 9, 2013
Review of the Gold Rush 100K Permit ① “Review of Permit Results” dated 3/25/2013 ② Information Provided by Regional Parks • Public Records Act Request dated March 1, 2013 • Timely response from Regional Parks • Signed Application & Permit • Request for Permit Amendment, IF ANY ③ No Other Information Received ④ Complete Response is Assumed Save the American River Association
Summary of Conclusions ①Gold Rush 100K Permit Violates American River Parkway Plan • Four Instances ② Regional Parks Permitting Process • No Documentation or Evidence Supporting Findings • Lack of Transparency/Public Review & Input • No resource impact monitoring program ③ Other Gold Rush 100K Permit Issues • Potential County Liability for Accidents • Inadequate Permit Conditions ④ Other issues Save the American River Association
COMPLIANCE WITH PARKWAY PLAN ①Parkway Plan is State Law Failure to be comply with Parkway Plan violates State Law ②All uses and facilities must be compatible with goals and policies of Parkway Plan ③A Permit may not be issued unless Regional Parks makes Findings of Fact based upon substantial evidence that: • Impacts on other Parkway users & Parkway natural resources & aesthetics are minimal, • Compliance with all other Plan requirements & County Ordinances will occur, and • The activity/event is compatible with the goals and policies of the Parkway Plan. Save the American River Association
PARKWAY PLAN VIOLATIONS ①Competitive Event Not Allowed on Horse/Hiking Trail ● No specific citation in Parkway Plan ● Only specific citation is bicycle trail competitive events ● Absence of a citation does not imply activity is permitted ②More than 2 Competitive Events in a Month ● Gold Rush 100K race ● Sac Fit Half Marathon ③Violates Nature Study Area Restrictions ●Based Upon Information Provided by Regional Parks ④No Findings of Fact documented by Substantial Evidence ●No Substantial Evidence = Unsubstantiated Opinion Save the American River Association
Horse Trail at Mile 9 Save the American River Association
OTHER PERMIT ISSUES ① Potential County Liability ● Accidents involving horseback riders and individuals a well known risk ● It only takes 1 runner & 1 surprised horse ② Permit Conditions Inadequate ● No instruction re avoidance of accidents, user conflicts, impacts on Parkway resources or appropriate response. ③ Inadequate map ● Current map of course NOT been provided ● All aid station locations & designs not identified Save the American River Association
REGIONAL PARKS PERMITTING PROCESS ① Basis of decisions not documented or supported • Nothing for independent review to confirm decisions • No substantial evidence = unsubstantiated opinion ② Permitting Process Not Transparent • Post applications and Permits on website • Allow public to provide input & have information • Parkway is a public resource of community interest ③ No Resource Impact Monitoring Program • Required by Parkway Plan Policy 3.4 • Needed to accurately assess impacts on resources Save the American River Association
OTHER ISSUES ① Group running on Horse/Hiking trail sensitive ●Concern for safety of horses & riders ●Concern for Parkway Plan compliance ②Staff Policy to Use the Parkway to make money ●“Pay to Play” ●Regional Parks Letter Dated 12/3/2012 ●Must comply with Parkway Plan ●Potential to exclude individual and family use Save the American River Association
PARKWAY PLAN The expression of your community’s desire to: • Provide recreation primarily for individuals and family groups, and • Preserve and protect the open space green belt, • While allowing controlled group activities and special events that: • Are consistent with the Parkway environment, • Only minimally impact other Parkway users, • Only minimally impact Parkway resources, AND • Are compatible with the Plan Goals and Policies. Save the American River Association
REQUESTED ACTION ① Permits that do not comply with the Parkway Plan are at odds with community desires & violate State law ●Gold Rush 100K Permit is one such permit ②SARA requests the Board of Supervisors to: ● Vacate and Remand the Gold Rush 100K permit to Regional Parks with direction to revise the permit as necessary to comply with the American River Parkway Plan. Save the American River Association