Subcontracting

Subcontracting. Construction Engineering 380. Subcontracts. Owner doesn’t “recognize” subcontractors They are representatives of the contractor Prime usually uses flow-down clauses Contractor must be confident they can perform Reputation Financial strength Labor force Job history

merle
Download Presentation

Subcontracting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Subcontracting Construction Engineering 380

  2. Subcontracts • Owner doesn’t “recognize” subcontractors • They are representatives of the contractor • Prime usually uses flow-down clauses • Contractor must be confident they can perform • Reputation • Financial strength • Labor force • Job history • Strength and skill of PM • Past work with team • Estimating ability

  3. Subcontracts • Increasing the number of subcontractors on the job reduces financial risk to GC but increases communication complexity and cash flow problems for the project team (30-30 problem) • Decision to subcontract versus self-perform is a risk/return optimization problem • Self-perform work has potential for greater reward, but carries more risk • Self-perform is less risky when you have long-term trades people and well-understood market

  4. Subcontracts • Subcontracting passes risk on to subcontractor in return for certain cost • Subcontracting can shorten schedule and improve quality/efficiency if subcontractor has access to superior technology or resources (knowledge) • Subcontracting can also reduce schedule flexibility because of contractual constraint

  5. Subcontracts • Must bind subcontractor to a cost and schedule consistent with overall project parameters • Contractor serves as conduit for changes and claims on behalf of the subcontractor • Major subcontractors sometime included in partnering team, working with government agencies and field coordination

  6. Subcontracts • Need to have hoisting, clean-up, work-hours, lock-out, freight and unloading, and labor relations issued spelled out in the subcontract • AGC has several standard subcontract types • Contractor/subcontractor share risk of payment • Subcontractor takes risk of payment • Design-build subcontract

  7. Subcontracts • Subcontracts can be negotiated or competitively bid- usually determined in part by the owner • Subcontractors can be asked to do value engineering, but must be careful about bid comparison and bid shopping • Usually pre-qualify subcontractors- financial strength, certifications, bonding

  8. Contract Time and Claims • Many states have moved toward statutory protection • Mechanic’s liens • Stop notice (subcontractor can stop payment) • Trust fund protection (treat prime like a trustee, making it a criminal not civil case) • Mandated bonding levels