Works by Others. What are “Works by Others”. Works initiated by any individual or external agency on the Main Roads network (State Road) Main Roads controlled roads can be found at www.mainroads.wa.gov.au > Our Roads > Facts and Figures > Roads Controlled by Main Roads.
E N D
What are “Works by Others” • Works initiated by any individual or external agency on the Main Roads network (State Road) • Main Roads controlled roads can be found at www.mainroads.wa.gov.au> Our Roads > Facts and Figures > Roads Controlled by Main Roads
Who is required to submit an Application All external agencies: • Utility Service Providers • Local Authorities • Developers • Land Owners and • Any other organisation who wish to undertake works, that have not been initiated by Main Roads, in a Main Roads’ road reservation
Why we require an Application • To confirm that the works are acceptable to Main Roads • To investigate any conflicts with other works • To ensure the proposed works will not affect future Main Roads infrastructure plans • To assess the impact on traffic flow • To monitor works occurring on the Main Roads network • To ensure the works comply with the “Utility Providers Code of Practice” • To ensure the Traffic Management Plan complies with the “Traffic Management for Works on Roads – Code of Practice” and Australian Standard 1742.3
Types of Applications • Utility Service Providers & Local Governments to Undertake Works within Road Reserves Managed by Main Roads Western Australia • Application Kit and Guidelines for Organisations Seeking to Undertake Works within Road Reserves – Low Complexity Works • Application Kit and Guidelines for Organisations Seeking to Undertake Works within Road Reserves – Complex Works
Location of Forms www.mainroads.wa.gov.au Our Roads > Conducting Works on Roads Screen shots
What we require for Complex Works • Road design drawings • Geometric design • Drainage design • Profiles and cross sections • Street lighting design • Pavement design • Signing & Lining Plans • Traffic Signal design drawings • Landscaping proposal • Environmental documents • Application Form to work within a Main Roads reservation • Traffic Management Plans
Location of Standards and Specifications www.mainroads.wa.gov.au Building Roads > Tender Preparation > Specifications Building Roads > Standards and Technical
Timeframes Allow a minimum of 10 business days for assessment of an Application.